PTM dan Alat Berat
Summary
TLDRIn this video, Annisa, a civil engineering student from Politeknik Negeri Bengkalis, explains key concepts related to mechanical soil transfer (PTM) and heavy machinery. She covers the importance of heavy machinery in construction projects, factors affecting their productivity (such as material type, weather, and operator skills), and how to calculate earthworks volume. Annisa also highlights various heavy machinery used in PTM, including bulldozers, loaders, and cranes, explaining their functions and applications. She concludes by discussing the calculation of production work for bulldozers, illustrating the process with practical examples.
Takeaways
- 😀 PTM (Pemindahan Tanah Mekanis) refers to all activities related to soil excavation, transport, leveling, and compaction using heavy equipment.
- 😀 The productivity of heavy equipment in PTM projects is influenced by factors such as altitude, material type, weather conditions, operator skill, terrain conditions, and equipment maintenance.
- 😀 The type of material being worked with determines the choice of heavy machinery. For example, scrapers are used for earth excavation.
- 😀 Weather conditions, especially rainfall, can significantly impact the efficiency and timeline of PTM work.
- 😀 Operator experience directly affects the efficiency of heavy equipment. More experienced operators can complete tasks more effectively.
- 😀 The condition of the terrain, such as soft or peat soil, requires different equipment types, like bulldozers with tracks instead of rubber-tired machines.
- 😀 Well-maintained equipment contributes to better productivity and performance in PTM activities.
- 😀 The **Section Method** is commonly used for calculating excavation and embankment volumes in road construction. This method involves dividing the road into sections and calculating material volumes at each station.
- 😀 Heavy equipment types commonly used in PTM include tractors (for pulling), bulldozers (for leveling), excavators (for digging), and dump trucks (for transporting material).
- 😀 Productivity calculations for bulldozers involve determining the blade volume, cycle time, work production per hour, and adjustments for operational efficiency.
- 😀 Accurate volume calculations and productivity estimations are crucial in civil engineering projects to ensure that construction tasks are completed efficiently and within the expected timeframes.
Q & A
What does PTM stand for and what does it involve?
-PTM stands for 'Pemindahan Tanah Mekanis' or Mechanical Soil Movement. It involves activities related to excavation, transportation, backfilling, leveling, and compaction of soil or rock using heavy machinery.
Why are the physical properties of soil important in PTM projects?
-The physical properties of soil, such as density, volume, hardness, cohesiveness, shape, and compaction level, influence the choice of machinery and techniques used in PTM projects, as they affect the ease of excavation and compaction.
What role does heavy machinery play in PTM?
-Heavy machinery plays a crucial role in PTM by assisting in the construction of structures, facilitating tasks such as excavation, transportation, and compaction, which would be difficult or time-consuming to perform manually.
What are some factors that affect the productivity of heavy machinery?
-Factors that affect the productivity of heavy machinery include altitude, material type, weather conditions, operator skill, terrain conditions, and the condition of the equipment.
How does altitude impact heavy machinery performance?
-At higher altitudes, the air density decreases, leading to reduced oxygen levels. This can affect the combustion process in engines, reducing the performance of heavy machinery.
What is the Grid Method and how is it used to calculate excavation and fill volumes?
-The Grid Method involves dividing the area into grid sections and calculating the excavation and fill volumes by measuring the soil depth at various points. This method is commonly used for building projects.
Can you explain the Sectional Method used in road construction volume calculations?
-The Sectional Method involves dividing the road into segments (stations) and calculating the excavation and fill volumes for each segment. By determining the average excavation and fill for each station, total volumes can be calculated for the entire road.
What are the different types of heavy equipment mentioned in the script?
-The script mentions several types of heavy equipment, including tractors, bulldozers, loaders, cranes, and dump trucks, each serving specific purposes like excavation, material transport, and construction assistance.
How does a bulldozer's work cycle affect its productivity?
-A bulldozer's productivity is influenced by its work cycle, which includes the cutting cycle, return cycle, and constant cycle time. The efficiency of these cycles, along with external factors like weather and terrain, affects the overall output.
What formula is used to calculate the bulldozer's work volume per cycle?
-The formula used to calculate the bulldozer's work volume per cycle is: Volume = 0.8 × (Height of blade)^2 × Width of blade.
Outlines

This section is available to paid users only. Please upgrade to access this part.
Upgrade NowMindmap

This section is available to paid users only. Please upgrade to access this part.
Upgrade NowKeywords

This section is available to paid users only. Please upgrade to access this part.
Upgrade NowHighlights

This section is available to paid users only. Please upgrade to access this part.
Upgrade NowTranscripts

This section is available to paid users only. Please upgrade to access this part.
Upgrade NowBrowse More Related Video

CARA PELAKSANAAN UJI GESER LANGSUNG, UJI KUAT TEKAN BEBAS, DAN TRIAXIAL TEST || RJJ 3B 2021

Ilmu Ukur Tanah Basic (Part 1)

Pendahuluan - Perpindahan Kalor dan Massa

Video Presentasi Dasar Mekanika dan Hidrolika pada alat berat Kelompok 2

Cara Mengoperasikan Mesin Injection Molding #polibatam #LabInjectionmolding

Petualangan Prodi Politeknik Negeri Indramayu 2024
5.0 / 5 (0 votes)