Framing My Next Rental Property | 60 Day Home Build CHALLENGE!!
Summary
TLDRIn this engaging episode three of a home build series, the host details the completion of the framing process for their second home. The video covers the delivery of lumber, the work of the framing crew, and the challenges faced, including a weekend break and a non-productive day due to a reduced crew. The host discusses the use of engineered wood products, specifically Web trusses, for easier installation of electrical and plumbing systems. They also highlight changes made to the design for a more open and modern feel, such as removing a post and modifying the front door area. The summary of the build includes the delivery of siding materials, the framing of the second floor and attic, and the final touches to meet the 60-day build goal. The host also shares insights on maximizing space and value, such as leaving areas open for appraisal purposes. The total cost for framing is revealed to be $26,662, and the video concludes with a teaser for the upcoming siding installation and further progress in the series.
Takeaways
- ποΈ The video documents the completion of the framing process for a home build project, detailing the various stages and challenges faced.
- π The framing process took place over several days, with some delays due to crew availability and the need for additional materials.
- π οΈ The use of engineered wood products, specifically Web trusses, facilitated the routing of electrical wires, plumbing, and HVAC ducts through the frame.
- πͺ A mistake was identified where a bathroom door was omitted in the initial framing, which was caught and rectified during the process.
- 𧱠The framing crew faced a non-productive day due to a lack of workers, highlighting the importance of reliable labor for timely project completion.
- π The framing included careful measurements and adjustments to ensure structural integrity and to address any issues such as misaligned or non-flush joints.
- π The house design features an open concept on the first floor with designated areas for living, dining, and kitchen spaces, as well as a utility room and powder bathroom.
- ποΈ On the second floor, there are two guest rooms, a shared bathroom (Jack and Jill style), and a master bedroom with an en-suite bathroom and a sizable closet.
- π¨ Additional materials, including 2x6 lumber, were ordered to complete the framing, specifically for overhangs and raptors.
- π° The total cost for the framing phase was $26,662, which included both material and labor expenses.
- β° Despite some setbacks, the project remains on track to be completed within the 60-day goal, with a contingency of 10 to 12 days for potential delays.
Q & A
What was the main task completed in the video?
-The main task completed in the video was the framing of the house, which involved constructing the bottom floor walls, joists, and the second floor walls.
Why did the framing crew take a break on day 18 and 19?
-The framing crew took a break on day 18 and 19 because those days were a Saturday and a Sunday, which are typically non-working days for the crew.
What is the purpose of using engineered wood products like web trusses?
-Engineered wood products like web trusses are used because they provide an open space that allows for the easy installation of electrical wires, plumbing, and HVAC ducts within the structure of the house.
Why did the framing progress slow down on day 21?
-The framing progress slowed down on day 21 because only two framers were present instead of the usual crew, leading to a non-productive day with only the stairs being completed.
What material was delivered for the siding of the house?
-The siding material delivered included OSB (Oriented Strand Board) for the exterior walls and roof deck sheathing, as well as lap siding for the exterior walls.
What is the planned overhang measurement for the roof?
-The planned overhang measurement for the roof is 24 inches, which is wider than the previous house where an overhang of 12 or 16 inches was used.
What is the total cost for the framing phase of the home build?
-The total cost for the framing phase of the home build is $26,662, which includes both material and labor costs.
What issue was identified with the front door area?
-An issue identified with the front door area was that the wall was not cut down to make the space more open. The plan is to cut the wall to allow a clear view up the stairs and into the second story.
What was the issue with the bathroom in the framing?
-The issue with the bathroom was that the framers did not frame a door into the bathroom. This was caught and rectified so that there would be a door for access to the bathroom.
What is the square footage of the garage?
-The square footage of the garage is 448 square feet, which is considered quite large in the context of the video.
What is the purpose of leaving the area under the stairs open?
-Leaving the area under the stairs open serves as additional living space, which can increase the value of the house when it is appraised. It is estimated to add about $2,000 to $3,000 in value.
What is the total square footage of the house?
-The total square footage of the house is 1,768 square feet, which is considered efficient and well-laid out for a rental property.
Outlines
ποΈ Framing Progress and Challenges
The video script details the ongoing process of the home build, focusing on the framing stage. The narrator discusses the progress made on days 16 to 21, including the delivery of lumber, the work of the framing crew, and the completion of approximately 35% of the frame. The crew faced a non-productive day due to a lack of workers, but managed to complete the second floor walls and interior walls by the end of day 21. The script also mentions the delivery of siding materials, the installation of engineered wood products like Web trusses for easier wiring and plumbing, and the plan to finish framing by Wednesday. Issues such as a non-flush joint and the absence of a framed door for the bathroom are highlighted, with solutions proposed for each. The narrator emphasizes the goal of completing the house in 60 days, with adjustments made for unforeseen challenges.
π Framing Adjustments and Material Shortages
This paragraph discusses the need for adjustments in the framing to create a more open feel in the house, such as cutting a wall down for better visibility of the stairs and second stories. The narrator also catches a mistake where the bathroom door was omitted and ensures it will be corrected. A trip to Home Depot to purchase additional materials is mentioned, with a shortage of funds by only $250. The framing crew's need for more materials on the last day and the successful acquisition of these items are also covered. The paragraph concludes with the completion of the frame by 7 p.m. on day 22, with some cleanup remaining for the next day. The framing work is described as complete, despite the messy site, and the narrator outlines the changes made to the design for a modern look, including the decision not to install a post for the front porch area.
π House Layout and Design Decisions
The narrator provides a detailed walkthrough of the house layout, starting with the decision to avoid an expensive beam and post in favor of an open concept for the rental property. The first floor is described with its living room, kitchen, dining area, powder bathroom, utility room, and laundry room. The garage is noted to be a good size at 448 square feet. The narrator also discusses the strategic framing under the stairs to create an open storage area that contributes to the living space square footage, thereby increasing the property's value. The second floor is highlighted to include two guest rooms, a Jack and Jill bathroom style setup, and a master bedroom with an en-suite bathroom and closet. The tour concludes with the narrator's satisfaction with the efficient layout and open floor plan of the house.
π Project Costs and Timeline
The final paragraph of the script provides a financial breakdown of the framing phase, with material costs amounting to $20,967 and labor costs at $5,695, leading to a total of $26,662 for the framing. The narrator reflects on the progress of the build on day 22 and anticipates the siding contractor's arrival on day 23 to install siding, windows, and doors, which will take two days. The plan to move on to the roof and mechanicals after the siding is also mentioned. The script acknowledges a potential delay of 10 to 12 days and notes that four days have already been used due to setbacks, including a plumbing inspection failure and a day when the framing contractor brought only two workers. The video concludes with an encouragement for viewers to subscribe for future updates.
Mindmap
Keywords
π‘Framing
π‘Joist
π‘OSB
π‘Lap Siding
π‘Overhang
π‘Fascia
π‘Trusses
π‘Rafters
π‘Utility Room
π‘Jack and Jill Bathroom
π‘Master Suite
Highlights
Introduction to the third episode of a home build series focusing on completing the framing.
Day 16 and 17 involved lumber delivery and framing crew completing 35% of the frame.
The crew took a break on Day 18 and 19, which were a weekend.
On Day 20, the framing of the bottom floor walls and joists was completed.
Engineered wood product, Web trusses, were used for easier installation of electrical and plumbing systems.
The framing process started from the bottom up, with the first floor walls followed by joists.
Day 21 saw the continuation of the framing with the second floor walls and interior walls completed.
The framing crew encountered a non-productive day due to a lack of workers.
Siding material delivery on Day 21 included OSB for sheathing and roof decking.
A wider 24-inch overhang is planned for the house, compared to the previous house's 12 or 16-inch overhang.
The framing was completed by Day 22, with a total of four days spent on framing.
A change in design was requested for the front door area to make it more open and visually appealing.
A bathroom door was added after it was initially missed in the framing.
A Home Depot trip was necessary to acquire additional framing materials.
The framing of the front entry with an overhang and a modern style without a post was completed.
The house layout includes an open concept living room, kitchen, and dining area on the bottom floor.
The upstairs features two guest rooms, a Jack and Jill bathroom, and a large master bedroom suite.
The total cost for framing, including materials and labor, was $26,662.
The project remains on track to be completed in 60 days with a contingency for delays.
Transcripts
welcome back to my channel this is
episode three of my second home build
and in this video we're completing the
framing so let's get into the video
[Music]
[Music]
so day 16 and 17 I was out of town so
you won't see me in any of these clips
physically but day 16 I had the lumber
delivered and then on day 17 my framing
crew got to work and they were able to
complete about 35 of the entire frame
day 18 and 19 fell on a Saturday and a
Sunday so my crew took the weekend off
so let's pick it back up with day 20 of
the build we're still framing this is
the second day of the the framework they
knocked all this out the first day we
had 10 people here and today is day two
and we have two people here so so far
they've finished all of the bottom floor
walls
this is all the bottom floor walls and
they've also put up the next part of the
build which would be the joist
so if you come this way these this would
be the next part of the build after the
walls and these are called the joist and
basically what you do is when you frame
the house you start from the bottom up
you do the first floor walls and then
next part of the build is the joists and
these joists are called an engineered
wood product they are four trusses
they're called Web trusses because if
you look up you see how it's open a lot
of people will install two by twelves
right there but these trusses are where
the electrical wires and the plumbing
and the HVAC ducts have to run if you
have trusses it makes a lot easier
because you can run all your stuff
through there since it's open so they
did the first four walls and they've
done the trusses and now they're working
on the second floor wall so now we have
two people here probably won't be too
much going on today but he said he did
say we will finish the framing by
Wednesday which will be four days total
framing so hopefully he uh he stays true
to that so we can finish the building 60
days
uh one question
right here
it's no uh it's not flush I'm gonna put
maybe is
how
how to repair it go inside yeah you can
cut it okay so yeah cut it
and make it flush
oh right here you did that
man when you when you put the nail yeah
you want to fix it
yeah okay okay no there's no problem so
it's day 21 of the build right now we're
on the third day of the framing it's
Tuesday and I was hoping to have all the
framing done today but yesterday half of
the framers or all the framers decided
not to work there was only two guys
there so we really didn't get anything
done other than the stairs going from
the bottom floor to the top floor so
kind of a non-productive day yesterday
and those are what I'll have to avoid to
be able to build a house in 60 days all
right so it's five o'clock we're coming
towards the end of the day these guys
probably won't work too much longer
today we did get some accomplished today
so we got the the second floor walls
done and then we also got the second
floor interior walls so all of the
second floor walls are done tomorrow
they're going to come back out and we're
going to knock out the attic Framing and
the rafters and the framing will all be
done so one more full day of framing
also at some point today we got the
siding material delivered I purchased
all this from my roofing supply store
this is the OSB 484 foot by eight foot
OSB
and that will go on the walls on the
exterior walls for sheathing and then
also on the roof for the roof deck then
also we have the soffit right here but
we have the soffit and the siding so
this looks like all of the lap siding
six and a quarter lap siding on the last
house I think I did eight inch lap
siding so it was an extra two inches
whereas this one is only six and a
quarter so it's going to be less wide
panel on the last house I did a I
believe a 12 or a 16 inch overhang so
the overhang is where at the top where
the roof overhangs off of the house but
on this house I'm going to be doing a 24
inch overhang so this pin this is going
to be the soffit 24 inches it's a wider
overhang I'm going to do it and see how
how it looks I think it's going to look
pretty Sleek tomorrow we're going to
finish the framing and then also the
siding crew is going to start so we're
going to have two Crews here working at
the same time
so so far there's one two things that
I've caught where we're kind of making a
change right here is the front door you
walk in there's the stairs and I'm going
to do a metal handrail going up the
stairs so one thing I'm going to request
for them to do is cut this wall down
right here so instead of walking in the
front door and having it enclosed we're
going to cut it off open it up so that
way you'll be able to look up the stairs
and into the the second stories they're
going to cut it make it flush and it'll
be more open make it feel more open so
that's one problem so far that's
happened with the framing next is
you come through right here this is
supposed to be a bathroom well it is a
bathroom except they did not frame a
door in so maybe if if I wouldn't have
caught this there's a chance that they
wouldn't have caught it either and there
would be no door going into the bathroom
so I would have of course that would
have caused problems of the Futures but
I did catch it there's going to be a
door right here to walk into the
bathroom so they'll get that taken care
of
it's a good one
so we're at Home Depot we uh I think the
material cost was I'm like 20 some
thousand dollars and I only came up like
250 dollars short it's the last day of
the framing the contractor texted me and
said they need 30 more 2 by 6 by 12.
I don't know how we're gonna fit it all
in my truck
consider my bed's only five foot they're
gonna stick out seven foot yeah this
will be interesting
what the hell is that three times eight
200 yeah like 300 bucks sure ain't bad
all right
[Music]
30.
enjoy the boat
and see how this looks
maybe it'll stay
oh we're good
[Music]
tell us
okay yeah
mucho
oh my God
all right
so we needed that material for right
here in the front those are two by sixes
we're doing a little overhang right here
in the front and we need those two by
sixes for the last couple Raptors then
we'll be finished up so that was a
success
foreign
so it's day 22 we're coming to an end
it's like 7 p.m and the frame is now
complete uh another day the framers just
have to come back and do some cleaning
and stuff but here it is so now let's go
uh let's go take a look we have a
quite a bit of mess going on over there
we still got some two by sixes yeah two
by sixes we got some more two by sixes
here looks like right here we got some
two by six two by fours anyways this all
this extra stuff there's quite a bit of
good extra stuff that will be used for
tomorrow's uh cornice the uh the fascia
the fascia framing the site is
definitely a wreck but the framers
finished up they got to come back and
clean another day so anyways let's go
check out the frame this is the front
entry and as you can see there's quite a
bit of an overhang right here probably
like a four foot overhang me and the
head framer were arguing not arguing
necessarily but we're talking about this
post
it came with in the uh material that we
were supposed on the plans I I'm not
sure if it was on the planes but either
way I ordered the post the framer wanted
to install this post right here and I
don't want to post right here it's kind
of like a country ranch style looking
feature on a house and I want this to be
modern so with that said I don't want
that post there we did install instead
they framed this area
uh to withstand putting a post so it can
all be open coming into the front porch
area
this will be the front door so coming
through
Once you walk in the house
to the left will be the living room and
then the kitchen area one thing I
definitely would not have done if this
was my house is this right here is going
to be like it's basically acting as a
post it's supporting this big ass beam
right here and this beam and that has to
hold the second floor up well if it was
my house I would have paid to get an
expensive ass beam put in here long that
way it doesn't have to be stopped right
here we would be able to do without this
post but since it's a rental property I
just decided hey I'm going to go ahead
and do this kind of framing to avoid
that expensive beam because that in
itself would probably be about a about a
three thousand dollar beam if I had to
guess it might have been another two or
three grand to do that it's a pretty
open concept you walk into the left
right here this will be the living room
area the couch will be this way TV that
way then right here
will be the island
here's the electrical plug so we'll have
electrical for the island it'll be about
seven feet right here this is gonna be
the pantry and then cabinets on that
wall cabinets on that wall that's gonna
be a window right there so living room
kitchen coming this way
on the bottom floor will be dining area
right here and coming this way
is
the primers still have a little bit of
work but they're going to put a door
here this will be the downstairs powder
bathroom this is going to be the
exterior door on the back side of the
house
and right here will be the utility room
so this will be the laundry room with
washer dryer you know maybe a shelf
pretty pretty good sized laundry room
for a rental property so now let's go
take a look upstairs where all the
bedrooms and bathrooms are oh one thing
is well let me go this way this is the
door of course to the garage pretty big
garage actually 448 square foot it looks
massive right now so anyways it's a good
garage one thing that I'm doing here is
under the stairs there's going to be a
little closet for investment purposes
I've made the framer frame this
accordingly so basically you open the
door and then there's this big area
right here and then it wraps around if
you can see we're not going to change
anything right here it's all going to be
open for uh storage and what that'll do
most people would probably put a wall
right here and they would cancel that
about 10 square foot they would just
wall it in and instead of me Walling it
in it's all going to be open and
considered living space whenever the
appraiser appraises the house they will
calculate that square footage Under the
Stairs
as living square footage and that 10
square foot probably 10 12 15 square
foot adds a value to the house of
probably about 200 a square foot yeah
two to three or four thousand two to
three thousand dollars just for leaving
that open so anyways going up the stairs
here
once you come up the stairs we've got
these wind
s I'll be feel pretty open I'm gonna do
a metal handrail a handrail will start
right here and go on that way it's a
pretty open feeling I don't necessarily
know what you want to call this area
but there's an open area here you can
call it a maybe I don't know a foyer
maybe the right word anyways you can put
a desk here or something cool look out
the window or it can just be open or
whatever you want to do let's go check
out the guest rooms first there's gonna
be a linen a linen closet there'll be a
door with some shelves for uh you know
blanket stuff like that storage closet
there's two guests we'll say two guest
rooms in the master bedroom here's a
guest room
you know decent sized guest room not too
small and the last house I built it was
relatively small in comparison so here
is
guest room number one
this window I'll have to check on the
plans but this window seems a little
off-centered but maybe it's how it's
supposed to be anyways window there
here's the closet good size closet for a
you know small rental house so closet
there coming in here right across right
through that wall is the other guest
room and how I elected to do it is Jack
and Jill bathroom style so coming into
this door there's going to be a vanity
with a sink here
then right here don't step on those nose
there's gonna be a toilet right there a
little sliding door here
then coming right here
there's going to be a bathtub right
there
bathtub shower combo we're missing a 2x4
right here but there'll be a window
right there
then coming through
this will be a vanity with a sink wash
your hands for the other bedroom
and then coming through here will be the
other guest room so it goes guest room
sink bathtub toilet sink other guest
rooms so it's all kind of connected for
the guest rooms and then here's the
closet for the uh other guest room so
let's go take a look now
and the master part of the house
so going down the hallway here
it's going to kind of look crazy because
there's all this bracing but I'll go
take I'll go stand here this is going to
be the master bedroom it's actually
standing in here is a massive for a
relatively small house it's a massive uh
master bedroom it's got a big window on
the left I assume the bed will go right
here TV right there
nine foot ceilings uh feels like a
pretty pretty good sized master bedroom
for a small rental house then coming
through here through the maze this is
coming through this little little
doorway is going to be a pocket door
it'll slide in and out is going to be
the master bathroom
and master closet
um it's kind of designed to be like
connected open try to make it feel big
it's really not that big but anyways so
where you are standing right now is
going to be shower tub combo
for the master bathroom and right here
will be the vanity wash your hands right
here
will be the toilet
or you can use the restroom handle
business this is going to be a wall then
right around the wall is going to be
the master closet so right here is the
master closet so this is the master
closet it's relatively big master closet
this house is only
1768 square foot and I feel like kind of
maximize the efficiency you know it's a
very efficient laid out house open floor
plan downstairs upstairs is the two
guest rooms with the Jack and Jill bath
on one side and then on this whole side
is the master bedroom master bathroom
and master closet so that is a
tour of the finished frame so for the
cost on the framing trade of this home
build the material cost twenty thousand
nine hundred and sixty seven dollars
the labor cost five thousand six hundred
and ninety five dollars and that brings
us to the grand total for the framing of
26
662 dollars so we're coming to the end
of day number 22 of my home build and
the framing is all 99 complete tomorrow
will be day 23 and the siding contractor
will show up and he's going to install
the siding the windows and the doors all
that will take up day 23 and day 24 so
the next two days and then we're on to
the roof and then we're on to the
Mechanicals and so on so on so we're
still on track to complete the building
60 days I think I allocated about
10 to 12 days for delays and so far I
think we've already used four
considering
one day we failed a plumbing inspection
that took up a day or two and then
during the framing phase we had the
framing contractor show up on Monday
with just two people the Bill's gone
good that's it next part's deciding so
stay tuned for that video make sure to
subscribe below so you don't miss out on
the future videos and thanks for
watching
Browse More Related Video
Revealing How Much it Cost to Build My First House for a Rental Property!!
Siding, Windows & Doors Installation (COST REVEALED!) | 60 Day Home Build Challenge!
The Cost To Build My Second Home Build! (FULL BUDGET BREAKDOWN)
The Foundation, Permits, Ordering Material | 60 Day Home Build CHALLENGE!
CHALLENGING Myself To Build A House In 60 Days!!
How to Work with an Insecure Boss: The Harvard Business Review Guide
5.0 / 5 (0 votes)