Framing My Next Rental Property | 60 Day Home Build CHALLENGE!!

Case Lucas Robinson
31 Aug 202318:05

Summary

TLDRIn this engaging episode three of a home build series, the host details the completion of the framing process for their second home. The video covers the delivery of lumber, the work of the framing crew, and the challenges faced, including a weekend break and a non-productive day due to a reduced crew. The host discusses the use of engineered wood products, specifically Web trusses, for easier installation of electrical and plumbing systems. They also highlight changes made to the design for a more open and modern feel, such as removing a post and modifying the front door area. The summary of the build includes the delivery of siding materials, the framing of the second floor and attic, and the final touches to meet the 60-day build goal. The host also shares insights on maximizing space and value, such as leaving areas open for appraisal purposes. The total cost for framing is revealed to be $26,662, and the video concludes with a teaser for the upcoming siding installation and further progress in the series.

Takeaways

  • πŸ—οΈ The video documents the completion of the framing process for a home build project, detailing the various stages and challenges faced.
  • πŸ“… The framing process took place over several days, with some delays due to crew availability and the need for additional materials.
  • πŸ› οΈ The use of engineered wood products, specifically Web trusses, facilitated the routing of electrical wires, plumbing, and HVAC ducts through the frame.
  • πŸšͺ A mistake was identified where a bathroom door was omitted in the initial framing, which was caught and rectified during the process.
  • 🧱 The framing crew faced a non-productive day due to a lack of workers, highlighting the importance of reliable labor for timely project completion.
  • πŸ“ The framing included careful measurements and adjustments to ensure structural integrity and to address any issues such as misaligned or non-flush joints.
  • 🏠 The house design features an open concept on the first floor with designated areas for living, dining, and kitchen spaces, as well as a utility room and powder bathroom.
  • πŸ›οΈ On the second floor, there are two guest rooms, a shared bathroom (Jack and Jill style), and a master bedroom with an en-suite bathroom and a sizable closet.
  • πŸ”¨ Additional materials, including 2x6 lumber, were ordered to complete the framing, specifically for overhangs and raptors.
  • πŸ’° The total cost for the framing phase was $26,662, which included both material and labor expenses.
  • ⏰ Despite some setbacks, the project remains on track to be completed within the 60-day goal, with a contingency of 10 to 12 days for potential delays.

Q & A

  • What was the main task completed in the video?

    -The main task completed in the video was the framing of the house, which involved constructing the bottom floor walls, joists, and the second floor walls.

  • Why did the framing crew take a break on day 18 and 19?

    -The framing crew took a break on day 18 and 19 because those days were a Saturday and a Sunday, which are typically non-working days for the crew.

  • What is the purpose of using engineered wood products like web trusses?

    -Engineered wood products like web trusses are used because they provide an open space that allows for the easy installation of electrical wires, plumbing, and HVAC ducts within the structure of the house.

  • Why did the framing progress slow down on day 21?

    -The framing progress slowed down on day 21 because only two framers were present instead of the usual crew, leading to a non-productive day with only the stairs being completed.

  • What material was delivered for the siding of the house?

    -The siding material delivered included OSB (Oriented Strand Board) for the exterior walls and roof deck sheathing, as well as lap siding for the exterior walls.

  • What is the planned overhang measurement for the roof?

    -The planned overhang measurement for the roof is 24 inches, which is wider than the previous house where an overhang of 12 or 16 inches was used.

  • What is the total cost for the framing phase of the home build?

    -The total cost for the framing phase of the home build is $26,662, which includes both material and labor costs.

  • What issue was identified with the front door area?

    -An issue identified with the front door area was that the wall was not cut down to make the space more open. The plan is to cut the wall to allow a clear view up the stairs and into the second story.

  • What was the issue with the bathroom in the framing?

    -The issue with the bathroom was that the framers did not frame a door into the bathroom. This was caught and rectified so that there would be a door for access to the bathroom.

  • What is the square footage of the garage?

    -The square footage of the garage is 448 square feet, which is considered quite large in the context of the video.

  • What is the purpose of leaving the area under the stairs open?

    -Leaving the area under the stairs open serves as additional living space, which can increase the value of the house when it is appraised. It is estimated to add about $2,000 to $3,000 in value.

  • What is the total square footage of the house?

    -The total square footage of the house is 1,768 square feet, which is considered efficient and well-laid out for a rental property.

Outlines

00:00

πŸ—οΈ Framing Progress and Challenges

The video script details the ongoing process of the home build, focusing on the framing stage. The narrator discusses the progress made on days 16 to 21, including the delivery of lumber, the work of the framing crew, and the completion of approximately 35% of the frame. The crew faced a non-productive day due to a lack of workers, but managed to complete the second floor walls and interior walls by the end of day 21. The script also mentions the delivery of siding materials, the installation of engineered wood products like Web trusses for easier wiring and plumbing, and the plan to finish framing by Wednesday. Issues such as a non-flush joint and the absence of a framed door for the bathroom are highlighted, with solutions proposed for each. The narrator emphasizes the goal of completing the house in 60 days, with adjustments made for unforeseen challenges.

05:01

πŸ” Framing Adjustments and Material Shortages

This paragraph discusses the need for adjustments in the framing to create a more open feel in the house, such as cutting a wall down for better visibility of the stairs and second stories. The narrator also catches a mistake where the bathroom door was omitted and ensures it will be corrected. A trip to Home Depot to purchase additional materials is mentioned, with a shortage of funds by only $250. The framing crew's need for more materials on the last day and the successful acquisition of these items are also covered. The paragraph concludes with the completion of the frame by 7 p.m. on day 22, with some cleanup remaining for the next day. The framing work is described as complete, despite the messy site, and the narrator outlines the changes made to the design for a modern look, including the decision not to install a post for the front porch area.

10:01

🏠 House Layout and Design Decisions

The narrator provides a detailed walkthrough of the house layout, starting with the decision to avoid an expensive beam and post in favor of an open concept for the rental property. The first floor is described with its living room, kitchen, dining area, powder bathroom, utility room, and laundry room. The garage is noted to be a good size at 448 square feet. The narrator also discusses the strategic framing under the stairs to create an open storage area that contributes to the living space square footage, thereby increasing the property's value. The second floor is highlighted to include two guest rooms, a Jack and Jill bathroom style setup, and a master bedroom with an en-suite bathroom and closet. The tour concludes with the narrator's satisfaction with the efficient layout and open floor plan of the house.

15:02

πŸ“Š Project Costs and Timeline

The final paragraph of the script provides a financial breakdown of the framing phase, with material costs amounting to $20,967 and labor costs at $5,695, leading to a total of $26,662 for the framing. The narrator reflects on the progress of the build on day 22 and anticipates the siding contractor's arrival on day 23 to install siding, windows, and doors, which will take two days. The plan to move on to the roof and mechanicals after the siding is also mentioned. The script acknowledges a potential delay of 10 to 12 days and notes that four days have already been used due to setbacks, including a plumbing inspection failure and a day when the framing contractor brought only two workers. The video concludes with an encouragement for viewers to subscribe for future updates.

Mindmap

Keywords

πŸ’‘Framing

Framing refers to the process of constructing the skeletal structure of a building, which includes the walls, floors, and roof. In the video, framing is the main task being completed, with the crew working on the bottom floor walls, joists, and trusses, which are essential for the structural integrity and to facilitate the passage of utilities like electrical wires and HVAC ducts.

πŸ’‘Joist

A joist is a horizontal structural member used for supporting the floor of a building. In the context of the video, the joists are engineered wood products known as web trusses, which are designed to be open for the easy installation of utilities. They are a key component in the progression from the first floor walls to the second floor construction.

πŸ’‘OSB

OSB, or Oriented Strand Board, is a type of engineered wood product made from strands of wood arranged in specific orientations for added strength. In the video, OSB is used as sheathing for the exterior walls and the roof deck, which is a common application in modern construction for its durability and cost-effectiveness.

πŸ’‘Lap Siding

Lap siding is a type of exterior siding for houses where each horizontal board or panel laps over the one beneath it, creating a flush surface. The video mentions the use of six and a quarter inch lap siding, which is narrower than what was used in the previous house built by the narrator, thus illustrating a design choice for a sleeker appearance.

πŸ’‘Overhang

An overhang in construction refers to the part of the roof that extends beyond the exterior walls of a building. The video discusses a 24-inch overhang, which is wider than the previous project's overhang, and is intended to give the house a more modern and sleek look.

πŸ’‘Fascia

Fascia is the horizontal trim at the eaves and rake of a roof, which helps to cover the ends of the rafters and provide a finished appearance to the edge of the roof. In the video, the fascia framing is part of the exterior finishing touches that will be addressed after the framing is complete.

πŸ’‘Trusses

Trusses are the triangular structural units that act as the main support for a roof. They are prefabricated and are used to create the necessary pitch and strength for the roof. In the video, the installation of trusses is part of the framing process, and they are chosen over traditional two by twelves for their utility in routing services through the open web spaces.

πŸ’‘Rafters

Rafters are the structural members that support the roof of a building. They are sloped from the ridge beam to the eaves and are part of the framing system. In the video, the crew is preparing to complete the attic framing and install the rafters, which will finalize the roof structure.

πŸ’‘Utility Room

A utility room is a space in a home designated for appliances and tasks such as laundry, washing, and sometimes storage. In the video, the narrator outlines the utility room's location, which will house a washer and dryer, and may include additional storage, emphasizing the practicality and efficiency of the space for a rental property.

πŸ’‘Jack and Jill Bathroom

A Jack and Jill bathroom is a bathroom that is accessible from two different rooms, typically two bedrooms, allowing it to serve both spaces. In the video, the narrator describes the bathroom layout where this design is used, providing shared access to a vanity, toilet, and bathtub/shower combo for two guest rooms.

πŸ’‘Master Suite

A master suite is a large private living space within a home that typically includes a bedroom, bathroom, and often a walk-in closet. In the video, the master suite is highlighted as a significant part of the house, with a focus on maximizing space and providing a comfortable and efficient layout for the master bedroom, bathroom, and closet.

Highlights

Introduction to the third episode of a home build series focusing on completing the framing.

Day 16 and 17 involved lumber delivery and framing crew completing 35% of the frame.

The crew took a break on Day 18 and 19, which were a weekend.

On Day 20, the framing of the bottom floor walls and joists was completed.

Engineered wood product, Web trusses, were used for easier installation of electrical and plumbing systems.

The framing process started from the bottom up, with the first floor walls followed by joists.

Day 21 saw the continuation of the framing with the second floor walls and interior walls completed.

The framing crew encountered a non-productive day due to a lack of workers.

Siding material delivery on Day 21 included OSB for sheathing and roof decking.

A wider 24-inch overhang is planned for the house, compared to the previous house's 12 or 16-inch overhang.

The framing was completed by Day 22, with a total of four days spent on framing.

A change in design was requested for the front door area to make it more open and visually appealing.

A bathroom door was added after it was initially missed in the framing.

A Home Depot trip was necessary to acquire additional framing materials.

The framing of the front entry with an overhang and a modern style without a post was completed.

The house layout includes an open concept living room, kitchen, and dining area on the bottom floor.

The upstairs features two guest rooms, a Jack and Jill bathroom, and a large master bedroom suite.

The total cost for framing, including materials and labor, was $26,662.

The project remains on track to be completed in 60 days with a contingency for delays.

Transcripts

play00:00

welcome back to my channel this is

play00:02

episode three of my second home build

play00:03

and in this video we're completing the

play00:05

framing so let's get into the video

play00:10

[Music]

play00:26

[Music]

play00:32

so day 16 and 17 I was out of town so

play00:35

you won't see me in any of these clips

play00:37

physically but day 16 I had the lumber

play00:40

delivered and then on day 17 my framing

play00:43

crew got to work and they were able to

play00:44

complete about 35 of the entire frame

play00:48

day 18 and 19 fell on a Saturday and a

play00:51

Sunday so my crew took the weekend off

play00:54

so let's pick it back up with day 20 of

play00:57

the build we're still framing this is

play00:59

the second day of the the framework they

play01:02

knocked all this out the first day we

play01:04

had 10 people here and today is day two

play01:06

and we have two people here so so far

play01:08

they've finished all of the bottom floor

play01:11

walls

play01:12

this is all the bottom floor walls and

play01:15

they've also put up the next part of the

play01:17

build which would be the joist

play01:20

so if you come this way these this would

play01:22

be the next part of the build after the

play01:24

walls and these are called the joist and

play01:27

basically what you do is when you frame

play01:29

the house you start from the bottom up

play01:30

you do the first floor walls and then

play01:32

next part of the build is the joists and

play01:35

these joists are called an engineered

play01:36

wood product they are four trusses

play01:40

they're called Web trusses because if

play01:43

you look up you see how it's open a lot

play01:46

of people will install two by twelves

play01:48

right there but these trusses are where

play01:50

the electrical wires and the plumbing

play01:53

and the HVAC ducts have to run if you

play01:57

have trusses it makes a lot easier

play01:58

because you can run all your stuff

play02:00

through there since it's open so they

play02:02

did the first four walls and they've

play02:03

done the trusses and now they're working

play02:06

on the second floor wall so now we have

play02:08

two people here probably won't be too

play02:10

much going on today but he said he did

play02:12

say we will finish the framing by

play02:13

Wednesday which will be four days total

play02:15

framing so hopefully he uh he stays true

play02:17

to that so we can finish the building 60

play02:19

days

play02:25

uh one question

play02:28

right here

play02:31

it's no uh it's not flush I'm gonna put

play02:36

maybe is

play02:37

how

play02:39

how to repair it go inside yeah you can

play02:42

cut it okay so yeah cut it

play02:45

and make it flush

play02:47

oh right here you did that

play02:53

man when you when you put the nail yeah

play02:58

you want to fix it

play03:03

yeah okay okay no there's no problem so

play03:07

it's day 21 of the build right now we're

play03:10

on the third day of the framing it's

play03:12

Tuesday and I was hoping to have all the

play03:15

framing done today but yesterday half of

play03:17

the framers or all the framers decided

play03:19

not to work there was only two guys

play03:20

there so we really didn't get anything

play03:22

done other than the stairs going from

play03:24

the bottom floor to the top floor so

play03:27

kind of a non-productive day yesterday

play03:29

and those are what I'll have to avoid to

play03:31

be able to build a house in 60 days all

play03:33

right so it's five o'clock we're coming

play03:35

towards the end of the day these guys

play03:37

probably won't work too much longer

play03:38

today we did get some accomplished today

play03:40

so we got the the second floor walls

play03:43

done and then we also got the second

play03:45

floor interior walls so all of the

play03:47

second floor walls are done tomorrow

play03:49

they're going to come back out and we're

play03:50

going to knock out the attic Framing and

play03:52

the rafters and the framing will all be

play03:54

done so one more full day of framing

play03:56

also at some point today we got the

play03:59

siding material delivered I purchased

play04:01

all this from my roofing supply store

play04:03

this is the OSB 484 foot by eight foot

play04:07

OSB

play04:09

and that will go on the walls on the

play04:12

exterior walls for sheathing and then

play04:15

also on the roof for the roof deck then

play04:18

also we have the soffit right here but

play04:22

we have the soffit and the siding so

play04:24

this looks like all of the lap siding

play04:26

six and a quarter lap siding on the last

play04:29

house I think I did eight inch lap

play04:31

siding so it was an extra two inches

play04:32

whereas this one is only six and a

play04:34

quarter so it's going to be less wide

play04:36

panel on the last house I did a I

play04:39

believe a 12 or a 16 inch overhang so

play04:43

the overhang is where at the top where

play04:45

the roof overhangs off of the house but

play04:48

on this house I'm going to be doing a 24

play04:50

inch overhang so this pin this is going

play04:52

to be the soffit 24 inches it's a wider

play04:55

overhang I'm going to do it and see how

play04:57

how it looks I think it's going to look

play04:58

pretty Sleek tomorrow we're going to

play05:00

finish the framing and then also the

play05:02

siding crew is going to start so we're

play05:04

going to have two Crews here working at

play05:05

the same time

play05:12

so so far there's one two things that

play05:17

I've caught where we're kind of making a

play05:19

change right here is the front door you

play05:22

walk in there's the stairs and I'm going

play05:24

to do a metal handrail going up the

play05:26

stairs so one thing I'm going to request

play05:29

for them to do is cut this wall down

play05:31

right here so instead of walking in the

play05:33

front door and having it enclosed we're

play05:35

going to cut it off open it up so that

play05:37

way you'll be able to look up the stairs

play05:39

and into the the second stories they're

play05:42

going to cut it make it flush and it'll

play05:44

be more open make it feel more open so

play05:46

that's one problem so far that's

play05:49

happened with the framing next is

play05:52

you come through right here this is

play05:54

supposed to be a bathroom well it is a

play05:56

bathroom except they did not frame a

play05:59

door in so maybe if if I wouldn't have

play06:01

caught this there's a chance that they

play06:03

wouldn't have caught it either and there

play06:06

would be no door going into the bathroom

play06:07

so I would have of course that would

play06:09

have caused problems of the Futures but

play06:10

I did catch it there's going to be a

play06:12

door right here to walk into the

play06:13

bathroom so they'll get that taken care

play06:15

of

play06:17

it's a good one

play06:18

so we're at Home Depot we uh I think the

play06:21

material cost was I'm like 20 some

play06:23

thousand dollars and I only came up like

play06:26

250 dollars short it's the last day of

play06:28

the framing the contractor texted me and

play06:30

said they need 30 more 2 by 6 by 12.

play06:33

I don't know how we're gonna fit it all

play06:34

in my truck

play06:36

consider my bed's only five foot they're

play06:38

gonna stick out seven foot yeah this

play06:40

will be interesting

play06:41

what the hell is that three times eight

play06:42

200 yeah like 300 bucks sure ain't bad

play06:45

all right

play06:46

[Music]

play06:58

30.

play07:02

enjoy the boat

play07:09

and see how this looks

play07:11

maybe it'll stay

play07:13

oh we're good

play07:16

[Music]

play07:41

tell us

play07:45

okay yeah

play07:49

mucho

play07:58

oh my God

play08:03

all right

play08:05

so we needed that material for right

play08:06

here in the front those are two by sixes

play08:08

we're doing a little overhang right here

play08:11

in the front and we need those two by

play08:13

sixes for the last couple Raptors then

play08:16

we'll be finished up so that was a

play08:18

success

play08:23

foreign

play08:49

so it's day 22 we're coming to an end

play08:52

it's like 7 p.m and the frame is now

play08:55

complete uh another day the framers just

play08:58

have to come back and do some cleaning

play08:59

and stuff but here it is so now let's go

play09:02

uh let's go take a look we have a

play09:05

quite a bit of mess going on over there

play09:07

we still got some two by sixes yeah two

play09:10

by sixes we got some more two by sixes

play09:12

here looks like right here we got some

play09:14

two by six two by fours anyways this all

play09:16

this extra stuff there's quite a bit of

play09:18

good extra stuff that will be used for

play09:20

tomorrow's uh cornice the uh the fascia

play09:24

the fascia framing the site is

play09:26

definitely a wreck but the framers

play09:28

finished up they got to come back and

play09:30

clean another day so anyways let's go

play09:31

check out the frame this is the front

play09:33

entry and as you can see there's quite a

play09:36

bit of an overhang right here probably

play09:38

like a four foot overhang me and the

play09:40

head framer were arguing not arguing

play09:42

necessarily but we're talking about this

play09:44

post

play09:45

it came with in the uh material that we

play09:48

were supposed on the plans I I'm not

play09:50

sure if it was on the planes but either

play09:51

way I ordered the post the framer wanted

play09:53

to install this post right here and I

play09:56

don't want to post right here it's kind

play09:57

of like a country ranch style looking

play10:00

feature on a house and I want this to be

play10:03

modern so with that said I don't want

play10:04

that post there we did install instead

play10:06

they framed this area

play10:08

uh to withstand putting a post so it can

play10:12

all be open coming into the front porch

play10:14

area

play10:14

this will be the front door so coming

play10:16

through

play10:17

Once you walk in the house

play10:19

to the left will be the living room and

play10:22

then the kitchen area one thing I

play10:24

definitely would not have done if this

play10:26

was my house is this right here is going

play10:28

to be like it's basically acting as a

play10:30

post it's supporting this big ass beam

play10:33

right here and this beam and that has to

play10:36

hold the second floor up well if it was

play10:38

my house I would have paid to get an

play10:40

expensive ass beam put in here long that

play10:43

way it doesn't have to be stopped right

play10:44

here we would be able to do without this

play10:46

post but since it's a rental property I

play10:49

just decided hey I'm going to go ahead

play10:50

and do this kind of framing to avoid

play10:52

that expensive beam because that in

play10:54

itself would probably be about a about a

play10:56

three thousand dollar beam if I had to

play10:58

guess it might have been another two or

play10:59

three grand to do that it's a pretty

play11:00

open concept you walk into the left

play11:02

right here this will be the living room

play11:05

area the couch will be this way TV that

play11:09

way then right here

play11:11

will be the island

play11:13

here's the electrical plug so we'll have

play11:15

electrical for the island it'll be about

play11:17

seven feet right here this is gonna be

play11:19

the pantry and then cabinets on that

play11:21

wall cabinets on that wall that's gonna

play11:23

be a window right there so living room

play11:25

kitchen coming this way

play11:27

on the bottom floor will be dining area

play11:30

right here and coming this way

play11:34

is

play11:36

the primers still have a little bit of

play11:37

work but they're going to put a door

play11:38

here this will be the downstairs powder

play11:40

bathroom this is going to be the

play11:42

exterior door on the back side of the

play11:43

house

play11:44

and right here will be the utility room

play11:46

so this will be the laundry room with

play11:48

washer dryer you know maybe a shelf

play11:50

pretty pretty good sized laundry room

play11:52

for a rental property so now let's go

play11:55

take a look upstairs where all the

play11:57

bedrooms and bathrooms are oh one thing

play11:59

is well let me go this way this is the

play12:01

door of course to the garage pretty big

play12:03

garage actually 448 square foot it looks

play12:06

massive right now so anyways it's a good

play12:08

garage one thing that I'm doing here is

play12:11

under the stairs there's going to be a

play12:13

little closet for investment purposes

play12:15

I've made the framer frame this

play12:17

accordingly so basically you open the

play12:20

door and then there's this big area

play12:22

right here and then it wraps around if

play12:24

you can see we're not going to change

play12:26

anything right here it's all going to be

play12:28

open for uh storage and what that'll do

play12:31

most people would probably put a wall

play12:33

right here and they would cancel that

play12:35

about 10 square foot they would just

play12:36

wall it in and instead of me Walling it

play12:39

in it's all going to be open and

play12:41

considered living space whenever the

play12:43

appraiser appraises the house they will

play12:45

calculate that square footage Under the

play12:47

Stairs

play12:48

as living square footage and that 10

play12:51

square foot probably 10 12 15 square

play12:54

foot adds a value to the house of

play12:56

probably about 200 a square foot yeah

play12:59

two to three or four thousand two to

play13:01

three thousand dollars just for leaving

play13:02

that open so anyways going up the stairs

play13:05

here

play13:07

once you come up the stairs we've got

play13:09

these wind

play13:10

s I'll be feel pretty open I'm gonna do

play13:12

a metal handrail a handrail will start

play13:15

right here and go on that way it's a

play13:17

pretty open feeling I don't necessarily

play13:19

know what you want to call this area

play13:21

but there's an open area here you can

play13:23

call it a maybe I don't know a foyer

play13:25

maybe the right word anyways you can put

play13:27

a desk here or something cool look out

play13:29

the window or it can just be open or

play13:31

whatever you want to do let's go check

play13:33

out the guest rooms first there's gonna

play13:34

be a linen a linen closet there'll be a

play13:36

door with some shelves for uh you know

play13:38

blanket stuff like that storage closet

play13:41

there's two guests we'll say two guest

play13:43

rooms in the master bedroom here's a

play13:46

guest room

play13:47

you know decent sized guest room not too

play13:49

small and the last house I built it was

play13:50

relatively small in comparison so here

play13:53

is

play13:55

guest room number one

play13:57

this window I'll have to check on the

play13:58

plans but this window seems a little

play14:00

off-centered but maybe it's how it's

play14:01

supposed to be anyways window there

play14:03

here's the closet good size closet for a

play14:07

you know small rental house so closet

play14:10

there coming in here right across right

play14:12

through that wall is the other guest

play14:14

room and how I elected to do it is Jack

play14:17

and Jill bathroom style so coming into

play14:19

this door there's going to be a vanity

play14:21

with a sink here

play14:23

then right here don't step on those nose

play14:26

there's gonna be a toilet right there a

play14:27

little sliding door here

play14:29

then coming right here

play14:32

there's going to be a bathtub right

play14:34

there

play14:35

bathtub shower combo we're missing a 2x4

play14:39

right here but there'll be a window

play14:40

right there

play14:41

then coming through

play14:43

this will be a vanity with a sink wash

play14:47

your hands for the other bedroom

play14:50

and then coming through here will be the

play14:52

other guest room so it goes guest room

play14:55

sink bathtub toilet sink other guest

play14:58

rooms so it's all kind of connected for

play15:00

the guest rooms and then here's the

play15:02

closet for the uh other guest room so

play15:06

let's go take a look now

play15:08

and the master part of the house

play15:11

so going down the hallway here

play15:14

it's going to kind of look crazy because

play15:15

there's all this bracing but I'll go

play15:17

take I'll go stand here this is going to

play15:20

be the master bedroom it's actually

play15:23

standing in here is a massive for a

play15:26

relatively small house it's a massive uh

play15:28

master bedroom it's got a big window on

play15:30

the left I assume the bed will go right

play15:32

here TV right there

play15:34

nine foot ceilings uh feels like a

play15:37

pretty pretty good sized master bedroom

play15:39

for a small rental house then coming

play15:41

through here through the maze this is

play15:44

coming through this little little

play15:45

doorway is going to be a pocket door

play15:48

it'll slide in and out is going to be

play15:50

the master bathroom

play15:52

and master closet

play15:54

um it's kind of designed to be like

play15:56

connected open try to make it feel big

play15:58

it's really not that big but anyways so

play16:01

where you are standing right now is

play16:03

going to be shower tub combo

play16:06

for the master bathroom and right here

play16:09

will be the vanity wash your hands right

play16:12

here

play16:13

will be the toilet

play16:15

or you can use the restroom handle

play16:17

business this is going to be a wall then

play16:19

right around the wall is going to be

play16:21

the master closet so right here is the

play16:23

master closet so this is the master

play16:25

closet it's relatively big master closet

play16:28

this house is only

play16:30

1768 square foot and I feel like kind of

play16:34

maximize the efficiency you know it's a

play16:37

very efficient laid out house open floor

play16:40

plan downstairs upstairs is the two

play16:42

guest rooms with the Jack and Jill bath

play16:44

on one side and then on this whole side

play16:46

is the master bedroom master bathroom

play16:48

and master closet so that is a

play16:52

tour of the finished frame so for the

play16:55

cost on the framing trade of this home

play16:57

build the material cost twenty thousand

play17:00

nine hundred and sixty seven dollars

play17:03

the labor cost five thousand six hundred

play17:07

and ninety five dollars and that brings

play17:09

us to the grand total for the framing of

play17:12

26

play17:14

662 dollars so we're coming to the end

play17:17

of day number 22 of my home build and

play17:20

the framing is all 99 complete tomorrow

play17:23

will be day 23 and the siding contractor

play17:26

will show up and he's going to install

play17:27

the siding the windows and the doors all

play17:30

that will take up day 23 and day 24 so

play17:33

the next two days and then we're on to

play17:35

the roof and then we're on to the

play17:36

Mechanicals and so on so on so we're

play17:38

still on track to complete the building

play17:39

60 days I think I allocated about

play17:42

10 to 12 days for delays and so far I

play17:46

think we've already used four

play17:47

considering

play17:48

one day we failed a plumbing inspection

play17:50

that took up a day or two and then

play17:51

during the framing phase we had the

play17:54

framing contractor show up on Monday

play17:55

with just two people the Bill's gone

play17:57

good that's it next part's deciding so

play17:59

stay tuned for that video make sure to

play18:02

subscribe below so you don't miss out on

play18:03

the future videos and thanks for

play18:04

watching

Rate This
β˜…
β˜…
β˜…
β˜…
β˜…

5.0 / 5 (0 votes)

Related Tags
Home BuildFraming PhaseDIY ProjectModern DesignEfficiency60-Day ChallengeConstructionDrone FootageTruss SystemBudgetingRental Property