SOP 2 PELEBARAN PERKERASAN

Mitra Arsitek Official
21 Jul 202011:34

Summary

TLDRThe transcript outlines standard operational procedures for road widening and strengthening projects. It details the process of adding width and strength to existing roads according to operational plans, including alignment correction, excavation and disposal of existing materials, and installation of foundation layers. The script emphasizes the importance of meeting design specifications, obtaining directorial approval for material use, and ensuring safety measures are in place. It also discusses the need for proper mixing of new and old materials, maintaining surface conditions, and conducting quality control tests to ensure the road's stability and durability.

Takeaways

  • ⚠️ The process involves expanding and strengthening the width of an old road according to standard operational procedures.
  • 🛠️ Work includes adding width to the existing road to meet the required traffic lane width as shown in the plan or directed by the board.
  • 🔍 Alignment improvement work is necessary to straighten roads and reduce curves and crests.
  • 🚧 Excavation and removal of existing materials, as well as trimming the edges of the road, are part of the preparation for the expansion work.
  • 🏗️ Installation of a base layer, aggregate, and asphalt layers are required according to the lines and dimensions provided in the drawings or approved by the board.
  • 👷‍♂️ Work begins based on specifications, work drawings or details, design, and approval to start work from the project.
  • 🚧 Traffic control measures, including temporary signs and barriers, are implemented when road shoulder work is part of the expansion.
  • 🌳 Tree felling is only carried out if absolutely necessary for the road expansion and must be replaced with new plantings.
  • 📏 The contractor must maintain the surface of the prepared base in a dry and stable condition until the required asphalt application.
  • 🔬 Quality control is emphasized through frequent testing of materials, including plastic index tests, gradation tests, and density tests.

Q & A

  • What does the term 'pelebaran perkerasan' refer to in the context of the script?

    -In the context of the script, 'pelebaran perkerasan' refers to the process of widening and strengthening an existing road according to the standard operational procedure plan.

  • What are the main activities included in the road widening and strengthening project?

    -The main activities include adding width to the existing road, alignment correction, excavation and removal of existing materials, edge trimming, installation of base layers, and ensuring good soil base conditions for the work.

  • What is the purpose of alignment correction in the road widening process?

    -The purpose of alignment correction is to make the road straighter and reduce curves and crests at bends or on gradients to improve road safety and efficiency.

  • What are the requirements for the materials used in the road widening and strengthening work?

    -The materials used must be approved by the director and should not be mixed with the excavated materials. They must also meet the specifications and design requirements, including proper compaction and quality control.

  • How is the excavation depth determined for the road widening and strengthening project?

    -The excavation depth is determined according to the plan shown in the drawings or as directed by the director, and it must be in accordance with the specifications.

  • What is the significance of the edge trimming process in road construction?

    -Edge trimming is significant as it ensures that the exposed edges of the road are hard, stable, and free from cracks or other instabilities, creating a clean vertical surface that meets the specified requirements.

  • What are the specifications for the width of the road widening work?

    -The width of the road widening must be sufficient to accommodate the required traffic lanes as per the design shown in the drawings or as directed by the director.

  • What is the minimum practical width for road widening as mentioned in the script?

    -The minimum practical width for road widening mentioned in the script is 0.5 meters. If the theoretical required width is less than 0.5 meters but more than 0.3 meters, the 0.5-meter width must be implemented.

  • What are the conditions under which no road widening work is necessary?

    -No road widening work is necessary if the theoretical required width is less than 0.3 meters.

  • What are the requirements for surface preparation before the road widening and strengthening work?

    -The surface must be prepared, compacted, and inspected as required by the specifications. The contractor must maintain the surface in a dry and stable condition until the required paving for the widening and strengthening is done.

  • What are the quality control measures for the asphalt layer in the road widening project?

    -Quality control measures include conducting a minimum number of tests for plastic index, gradation, and density, and ensuring that the asphalt layer meets the dimensional tolerances, compaction, and thickness requirements as specified.

Outlines

00:00

🚧 Road Expansion and Reinforcement Works

The paragraph discusses the standard operational procedures for road expansion and reinforcement works. It covers tasks such as adding width and strength to existing roads according to operational plans. The process includes improving road alignment to make roads straighter and reducing curves and crests, excavation and removal of existing materials, and preparing the subgrade for good conditions. It also details the installation of foundation layers, aggregates, and base courses according to given dimensions and specifications. The paragraph emphasizes the importance of safety measures for personnel and the surrounding environment, as well as the need for temporary traffic signs during construction. It also specifies the requirements for the approval of materials and the execution of work based on specifications and design details.

05:00

🌳 Road Widening and Tree Felling Procedures

This paragraph focuses on the procedures for road widening, including the preparation of the road surface, the minimum practical width requirements, and the conditions under which theoretical widths less than certain measurements necessitate specific actions. It also addresses the need for tree felling when necessary for road expansion, with a stipulation that felled trees must be replaced with new plantings. The paragraph outlines the requirements for the dimensions and geometry of the road expansion area, the maintenance of surface conditions by contractors, and the inspection of prepared surfaces before the application of materials. It also discusses the quality control measures, including the frequency of tests for plastic index, gradation, and density, and the conditions for the application of asphalt layers, ensuring they meet dimensional and density tolerances as per operational standards.

10:03

🛠 Asphalt Laying and Road Repair Standards

The final paragraph outlines the standards for laying asphalt and repairing roads. It discusses the use of various asphalt mixtures and the conditions under which temporary traffic signs are removed and the road is reopened. It also covers the procedures for asphalt layer inspection, including the frequency of density tests and the use of core or field tests. The paragraph specifies the tolerances for thickness and density that must be met, as well as the quality control measures that must be in place. It also describes the process for the application of asphalt layers, including the use of mechanical compactors and the requirements for the surface preparation before laying the asphalt. The paragraph concludes with the steps for the final opening of the road to traffic after all repairs and inspections have been completed and approved.

Mindmap

Keywords

💡Standard Operating Procedure

Standard Operating Procedure (SOP) refers to a set of step-by-step instructions compiled by an organization to help perform specific tasks. In the context of the video, SOPs are crucial for ensuring that road widening and strengthening projects are carried out according to established guidelines, maintaining consistency and quality in the work.

💡Road Widening

Road widening is the process of increasing the width of an existing road to accommodate more traffic lanes or to improve safety. The video script mentions road widening as a key operation, which includes adding width to old roads as per the required traffic lanes, as shown in the design plans or directed by the management.

💡Strengthening

Strengthening in the context of road construction refers to the process of enhancing the structural integrity and load-bearing capacity of the road. The script discusses strengthening as part of the road widening process, which involves ensuring that the road can support increased traffic and weight.

💡Alignment Improvement

Alignment improvement is the process of making roads straighter and adjusting curves and gradients for better driving conditions. The script mentions that the work includes alignment improvement to make roads straighter and reduce curves and crests, which is essential for traffic flow and safety.

💡Excavation and Embankment

Excavation and embankment are earthworks involved in road construction, where soil or rock is removed (excavation) or piled up (embankment) to shape the road. The script refers to these processes, emphasizing the need for sufficient space for machinery and the proper handling of excavated materials.

💡Subgrade Preparation

Subgrade preparation is the process of preparing the ground beneath the road surface to ensure a stable and durable foundation. The script highlights the importance of subgrade preparation, including compaction and maintenance of good soil conditions, which is essential for the longevity of the road.

💡Foundation Layer

A foundation layer in road construction is the base layer of material, usually a mix of aggregate and binder, that supports the road surface. The script discusses the installation of foundation layers according to given dimensions and specifications, which is crucial for the structural integrity of the road.

💡Traffic Control

Traffic control refers to the management of road user behavior to ensure the safe and efficient flow of traffic. The script mentions the installation of temporary traffic signs and signals, which is vital for managing traffic during construction and ensuring the safety of workers and the public.

💡Safety Equipment

Safety equipment in a construction context includes all the tools and protective gear used to ensure the well-being of workers and the public. The script emphasizes the use of safety equipment by all personnel involved in the road widening and strengthening work, highlighting the importance of safety in construction sites.

💡Environmental Considerations

Environmental considerations in construction projects involve taking steps to minimize the impact on the surrounding environment. The script touches on this by mentioning the replacement of felled trees with new plantings, demonstrating a commitment to environmental sustainability in road construction.

💡Quality Control

Quality control is the process of ensuring that the construction work meets the required standards and specifications. The script discusses various quality control measures, such as testing the density and consistency of materials, which are essential to ensure the road's durability and performance.

Highlights

The process involves expanding and strengthening the width of old roads according to standard operational procedures.

The expansion work includes adding width to the existing road to meet the required traffic lane width as shown in the design or directed by the board.

Improvement works are carried out to align the road more straightly and to reduce curves and crests on slopes.

Excavation and removal of existing materials are part of the process to prepare the road for expansion.

The road edge is trimmed to ensure a hard, stable, and undamaged surface to form a clean vertical edge.

Installation of a temporary road base layer is required according to the lines and dimensions given in the plan or approved by the board.

The commencement of expansion and strengthening work is based on specifications, work drawings, or design details, and approval to start work.

Safety equipment must be used by all personnel involved, and the work environment must be kept safe.

Temporary traffic signs are installed when road shoulder work is part of the road expansion.

Materials to be used for expansion must first get approval from the board.

The excavation for expansion must provide enough space for normal compaction equipment such as rollers.

If the width of the excavation exceeds the required expansion width, the excavated material must be refilled and compacted with new material.

The materials used for expansion must not be mixed with the excavated material unless approved by the board.

The depth of excavation must be in accordance with the plan, and excavated materials should not be used for expansion unless approved.

Mixing of new and old materials is generally not allowed unless the old material is of good quality and the board allows it.

The expansion and strengthening work must meet all dimensional tolerances and quality requirements specified in the specifications.

The road edge must be trimmed to a stable and undamaged surface to form a clean vertical edge according to specifications.

The width of the expansion must be sufficient for the traffic lane width as per the design shown in the plan or as directed.

The actual required width of expansion varies along the road, and the minimum practical width is considered to be 0.5 M.

If the theoretical required width of expansion is less than 0.3 M, no expansion work is needed.

The surface of the expansion area must be prepared, compacted, and inspected as required by the specifications.

The contractor must maintain the surface in a dry and stable condition until the required expansion is filled with material.

Tree felling is only carried out if absolutely necessary for the road expansion, and felled trees must be replaced.

The dimensions and geometry of the expansion area must meet the specifications and have the required density.

The contractor must repair any part of the expansion area that does not meet the requirements or is damaged.

The asphalt layering process must comply with the specifications regarding production, application, and compaction.

The asphalt layer must meet dimensional tolerances, compaction, and density requirements as specified.

The final stage involves the removal of temporary work and cleanup or restoration of the site.

The last step is the opening of temporary traffic signs.

Transcripts

play00:00

standar operasional prosedur pekerjaan

play00:02

pelebaran perkerasan lebaran perkerasan

play00:06

adalah pekerjaan menambah lebar

play00:08

perkerasan pada jalan lama sesuai dengan

play00:11

rencana standar operasional prosedur

play00:14

pelebaran perkerasan mencakup pekerjaan

play00:17

pekerjaan sebagai berikut penambahan

play00:20

lebar perkerasan lama sampai lebar jalur

play00:23

lalu lintas yang diperlukan dalam

play00:24

rancangan yang ditunjukkan pada gambar

play00:27

atau yang diperintahkan direksi

play00:29

pekerjaan perbaikan alinyemen demikian

play00:33

hingga sungguh Jalan menjadi lebih lurus

play00:35

dan lengkung pada tikungan maupun pada

play00:38

puncak tanjakan dapat dikurangi

play00:41

penggalian dan pembuangan bahan yang ada

play00:44

pemangkasan tepi perkerasan jalur lalu

play00:46

lintas lama sampai bahan yang keras

play00:49

senyap dan pemeliharaan kondisi formasi

play00:52

tanah dasar yang baik untuk pekerjaan

play00:54

pelebaran pemasangan lapis pondasi

play00:58

agregat dan lap

play01:00

seasonal menurut garis dan dimensi yang

play01:02

diberikan dalam gambar atau yang

play01:04

disetujui oleh direksi pekerjaan

play01:06

pelaksanaan pekerjaan pelebaran

play01:09

perkerasan dimulai berdasarkan

play01:12

spesifikasi dan gambar kerja atau detail

play01:15

desain serta persetujuan untuk mulai

play01:17

kerja dari bijektif pekerjaan penggunaan

play01:21

perlengkapan keselamatan kerja baik bagi

play01:24

setiap personil yang terlibat maupun

play01:26

lingkungan kerja dan sekitarnya

play01:28

pemasangan rambu lalu lintas sementara

play01:31

apabila pekerjaan bahu Jalan merupakan

play01:33

bagian pelebaran jalan bahan yang akan

play01:38

digunakan harus terlebih dahulu mendapat

play01:40

persetujuan dari direksi pekerjaan

play01:47

pembentukan badan jalan meliputi

play01:50

pekerjaan satu lebar galian dan

play01:53

penggalian bahan yang ada dengan

play01:55

ketentuan sebagai berikut galian untuk

play01:57

pelebaran perkerasan harus

play02:00

menyediakan ruang gerak yang cukup untuk

play02:02

alat penggilas atau roller normal

play02:05

bilamana lebar kalian melebihi lebar

play02:08

pelebaran perkerasan yang diperlukan

play02:10

maka bahan galian tersebut harus

play02:13

diisikan kembali dan dipadatkan

play02:15

bersama-sama dengan setiap bahan yang

play02:18

akan digunakan untuk pelebaran

play02:20

perkerasan bahan yang digunakan untuk

play02:22

pelebaran perkerasan tidak boleh

play02:24

bercampur dengan bahan galian yang

play02:26

diisikan kembali kedalaman penggalian

play02:29

harus sesuai dengan yang ditunjukkan

play02:31

dalam gambar rencana bahan galian tidak

play02:34

boleh digunakan sebagai bahan untuk

play02:37

pelebaran perkerasan baik langsung

play02:39

ataupun dicampur dengan bahan lain

play02:42

kecuali jika disetujui oleh direksi

play02:44

pekerjaan dua pencampuran berbutir yang

play02:49

baru dan lama dengan ketentuan

play02:51

pencampuran di tempat antara bahan

play02:53

berbutir yang baru dengan lama umumnya

play02:56

tidak diperkenankan bilamana Bang jangan

play02:58

lama tampak atau

play03:00

ketahui terbuat dari bahan agregat yang

play03:02

baik maka direksi pekerjaan dapat

play03:05

memerintahkan kontraktor menggali lubang

play03:07

uji atau speed untuk memastikan mutu

play03:10

penghujan lama dapat digunakan dan

play03:13

dicampur dengan bahan yang baru dan

play03:15

dipadatkan kembali bilamana telah

play03:17

dilaksanakan dengan cara ini pekerjaan

play03:20

pelebaran perkerasan tetap harus

play03:22

memenuhi semua toleransi dimensi dan

play03:24

mutu yang disyaratkan dalam spesifikasi

play03:27

VGA pemangkasan tepi jalur lalu lintas

play03:30

dengan ketentuan tepi perkerasan jalur

play03:33

lalu lintas yang terekspos harus

play03:35

dipangkas sampai mencapai banyak yang

play03:38

keras yang tidak lepas atau retak atau

play03:40

ketidakstabilan lainnya untuk membentuk

play03:42

permukaan vertikal yang bersih memenuhi

play03:45

ketentuan yang spesifikasi tentang

play03:47

pelaksanaan pengembalian kondisi dan

play03:50

pekerjaannya keempat lebar pekerjaan

play03:53

pelebaran dengan ketentuan lebar

play03:56

pelebaran perkerasan harus cukup untuk

play03:58

lebaran

play04:00

hai lalu lintas sesuai dengan lebar

play04:02

rancangan sebagaimana yang ditunjukkan

play04:04

dalam gambar atau sebagaimana

play04:06

diperintahkan Jack pekerjaan serta

play04:09

pelebaran tambahan yang cukup sehingga

play04:12

memungkinkan setiap lapisannya gempar

play04:15

bertangga terhadap lapisan dibawahnya

play04:17

atau terhadap perkerasan lama susunan

play04:22

bertangga ini diperlukan untuk

play04:24

memungkinkan penggilasan yang sedikit

play04:26

keluar dari tepi hamparan dan untuk

play04:29

memperoleh daya dukung samping yang

play04:31

memadai dan harus dibuat berturut-turut

play04:34

selebar 5 cm untuk setiap lapisan atau

play04:38

overlay yang dihampar pelebaran

play04:42

perkerasan yang diperlukan seperti yang

play04:45

ditunjukkan pada gambar untuk setiap

play04:48

ruas jalan hanya merupakan nilai

play04:50

rata-rata saja dan lebar pelebaran

play04:52

aktual yang diperlukan dari m ke m

play04:55

sepanjang jalan bervariasi sebagaimana

play04:58

yang diperlukan dan sebagai

play05:00

Hai sayang diperintahkan direksi

play05:01

pekerjaan dengan tujuan untuk mencapai

play05:04

lebar rancangan rata-rata pada setiap

play05:06

titik bagaimanapun juga lebar pelebaran

play05:11

0,5 M akan dipandang sebagai lebar-lebar

play05:14

praktis minimum bilamana lebar pelebaran

play05:18

teoritis yang diperlukan kurang dari 0,5

play05:21

M Tetapi lebih besar dari 0,3 M maka

play05:24

lebar pelebaran 0,5 M harus dilaksanakan

play05:28

dan bilamana lebar pelebaran teoritis

play05:31

yang diperlukan lebih kecil dari 0,3 M

play05:34

maka tak perlu diadakan pekerjaan

play05:36

pelebaran 5 penyiapan bentuk permukaan

play05:39

dengan ketentuan formasi kalian pada

play05:43

lokasi pelebaran perkerasan harus

play05:45

disiapkan dipadatkan dan diuji

play05:47

sebagaimana disyaratkan dalam

play05:49

spesifikasi tentang penyiapan badan

play05:52

jalan kontraktor harus memelihara

play05:54

permukaan tersebut dalam keadaan kering

play05:57

dan stabil sampai penghamparan

play06:00

yang diperlukan untuk pelebaran

play06:01

perkerasan yang harus diisi dengan bahan

play06:04

tersebut segera mungkin setelah

play06:06

pekerjaan penggalian formasi yang

play06:09

disiapkan harus diperiksa oleh direksi

play06:12

pekerjaan sesaat sebelum penghamparan

play06:15

bahan yang diperlukan untuk pelebaran

play06:17

perkerasan dan bahan tersebut tidak

play06:20

boleh dihampar sebelum pekerjaan

play06:22

penyiapan badan jalan disetujui oleh

play06:24

direksi pekerjaan 6 penebangan pohon

play06:28

untuk pelebaran dengan ketentuan

play06:30

penebangan pohon hanya akan dilaksanakan

play06:33

bilamana mutlak diperlukan untuk

play06:35

pelaksanaan pelebaran jalan baik pada

play06:38

jalur lalu lintas maupun pada bahu jalan

play06:40

pohon-pohon yang sudah ditebang harus

play06:43

diganti dengan cara penanaman pohon baru

play06:45

di daerah bro atau diluar bahu Jalan

play06:48

penebangan pohon tidak boleh

play06:50

dilaksanakan bilamana kestabilan reklame

play06:53

terganggu pemeriksaan formasi daerah

play06:57

penyebaran dengan Ketua merah pelebaran

play07:00

harus mempunyai dimensi dan geometri

play07:02

yang sesuai dengan gambar cerita

play07:04

mempunyai kepadatan yang memenuhi

play07:06

kepadatan badan jalan kontraktor harus

play07:10

memperbaiki setiap bagian formasi

play07:13

daerah-daerah pelebaran yang tidak

play07:15

memenuhi syarat atau mengalami kerusakan

play07:17

dengan cara yang diperintahkan oleh

play07:19

direksi pekerjaan pengerjaan atau

play07:23

penghamparan dan pemadatan lapis pondasi

play07:25

agregat dengan ketentuan yang

play07:28

disyaratkan Dalam standar operasional

play07:30

prosedur pekerjaan lapis pondasi agregat

play07:33

yang terkait dengan penghamparan dan

play07:35

pemadatan pemeriksaan lapis pondasi

play07:38

agregat ketua frekuensi pengujian

play07:42

pengendalian mutu harus ditingkatkan

play07:44

sedemikian rupa sehingga tidak kurang

play07:47

dari 5 pengujian indeks plastisitas atau

play07:50

plastik indeks 5 pengujian gradasi

play07:53

butiran dan satu pengujian kepadatan

play07:55

krim maksimum harus dilakukan untuk tiap

play07:58

500 M3

play08:00

Khan yang dibawa kelapangan bilamana

play08:02

lapis pondasi agregat telah dicampur

play08:05

dengan bahan Lama Maka frekuensi minimum

play08:07

dari pengujian yang disyaratkan harus

play08:10

diterapkan pada tiap bahan baru yang

play08:12

dibawa kelapangan dan Sebagai tambahan

play08:15

harus diterapkan juga pada bahan yang

play08:17

telah dicampur di lapangan untuk

play08:20

pengujian tambahan kontraktor harus

play08:22

mengambil contoh dari bahan yang telah

play08:24

dicampur sampai kedalaman rancangan pada

play08:27

lokasi yang ditunjukkan oleh pekerjaan

play08:30

frekuensi pengujian pengendalian

play08:32

kepadatan dan kadar air paling sedikit

play08:34

harus satu pengujian sesuai SNI 03 28 28

play08:41

1992 untuk setiap 50meter pekerjaan

play08:45

pelebaran pada masing-masing sisi dari

play08:47

Jalan jika diterapkan pelebaran 2xist

play08:50

diukur sepanjang sumbu Jalan lapis

play08:53

pondasi agregat pada pekerjaan ini harus

play08:56

memenuhi toleransi dimensi tebal

play09:00

kran dan kepadatan yang disyaratkan

play09:02

Dalam standar operasional prosedur

play09:04

pekerjaan lapis pondasi agregat

play09:07

kontraktor harus memperbaiki setiap

play09:10

lapis pondasi agregat yang tidak

play09:12

memenuhi syarat atau mengalami kerusakan

play09:14

dengan cara yang diperintahkan oleh

play09:16

direksi pekerjaan pengerjaan produksi

play09:20

penghamparan dan pemadatan lapis

play09:23

beraspal harus sesuai dengan ketentuan

play09:26

yang disyaratkan dalam spesifikasi yang

play09:28

berhubungan dengan produksi penghamparan

play09:31

dan pemadatan lapisan beraspal kecuali

play09:34

beberapa hal sebagai berikut ini sebelum

play09:37

bahan dihampar lapis resap pengikat yang

play09:39

sesuai harus disemprotkan pada lapis

play09:42

Pondasi yang sudah dipersiapkan dan

play09:44

lapis perekat yang sesuai juga harus

play09:47

tepat pada permukaan vertikal dari tepi

play09:50

perkerasan lama pada pelebaran yang agak

play09:53

sempit penghamparan dapat dilakukan

play09:55

dengan cara manual tetapi dalam

play09:57

batas-batas temperatur seperti

play09:59

penghampar

play10:00

dengan mesin pemadatan harus dilakukan

play10:02

menggunakan alat pemadat mekanis atau

play10:05

alat pemadat bergerak bolak-balik yang

play10:07

disetujui alat pemadat kecil yang

play10:09

bermesin sendiri dapat digunakan

play10:12

bilamana lebar pekerjaan pelebaran cukup

play10:15

untuk menampung seluruh roda alat

play10:17

pemadat pemeriksaan lapis beraspal

play10:20

dengan ketentuan pengujian kepadatan

play10:22

dari bahan terhampar yang ditentukan

play10:25

dengan pengujian benda uji Inti atau

play10:27

harus dilaksanakan dengan frekuensi yang

play10:30

tidak kurang dari satu pengujian setiap

play10:33

100 m pekerjaan pelebaran untuk

play10:36

masing-masing sisi jalan atau jika

play10:38

diterapkan pelebaran dua sisi diukur

play10:41

sepanjang sumbu Jalan rapist beraspal

play10:44

pada pekerjaan ini harus memenuhi

play10:46

toleransi dimensi tebal penghamparan dan

play10:49

kepadatan yang disyaratkan Dalam standar

play10:52

operasional prosedur yang sesuai rapi

play10:55

beraspal pada pekerjaan ini dapat

play10:57

terdiri atas laporan aspal 1

play11:00

atau boruto dan leburan aspal dua lapis

play11:03

atau budak campuran aspal panas Rush tak

play11:07

dan latasbusir campuran aspal dingin

play11:09

atau lapisan atas kadang pembersihan dan

play11:13

pembongkaran lalu lintas apabila

play11:16

perbaikan telah dilakukan Dan hasilnya

play11:18

telah disetujui oleh direksi pekerjaan

play11:21

maka Tahap selanjutnya adalah tahap

play11:24

pembongkaran pekerjaan sementara dan

play11:27

perapihan atau pembersihan lapangan

play11:29

Tahap terakhir adalah pembukaan rambu

play11:32

lalu lintas sementara

Rate This

5.0 / 5 (0 votes)

الوسوم ذات الصلة
Road ExpansionCivil EngineeringSafety StandardsQuality ControlInfrastructureConstructionTraffic ManagementMaterial HandlingEnvironmental ImpactProject Planning
هل تحتاج إلى تلخيص باللغة الإنجليزية؟