Tehnik Pemasangan bekisting kolom Yang baik dan benar

Prinsip Tukang
5 Nov 202203:39

Summary

TLDRThis video provides a detailed guide on the installation and assembly of reinforced concrete columns for multi-story buildings. It explains the process of fitting a column formwork and the techniques for securing the steel ties (referred to as 'sabuk') that hold the formwork in place. The narrator highlights the use of hollow steel bars for reinforcement and discusses the proper distances between each tie. Throughout the video, practical tips are shared for achieving strong and stable columns, with a focus on precision and safety in construction practices. The content is aimed at providing valuable insights for construction workers and professionals.

Takeaways

  • 😀 The video discusses the installation and reinforcement of column formwork in construction.
  • 😀 The focus is on the use of hollow steel for the support belts (sabuk) of the columns.
  • 😀 The column in the example has a 60x60 cm square size and a standard height of 3.5 to 4 meters.
  • 😀 The formwork (bekisting) and reinforcement must be installed carefully to ensure structural integrity.
  • 😀 The sabuk or support belt for the column is placed every 1 meter vertically.
  • 😀 The sabuk is made using 5x5 cm hollow steel with a thickness of 4mm, ensuring strength and stability.
  • 😀 Proper installation and tying of the sabuk are crucial for maintaining the column's structural form.
  • 😀 The reinforcement installation includes doubling the hollow steel and tying it securely with wires to ensure strength.
  • 😀 The formwork and reinforcement must be balanced and adjusted before being loaded to prevent displacement.
  • 😀 The video encourages construction workers to follow proper procedures to maintain safety and quality in building construction.

Q & A

  • What is the main topic of the video transcript?

    -The main topic of the video is about the installation of formwork for concrete columns, specifically focusing on the proper setup, tieing techniques, and materials used in the construction process.

  • What are the dimensions of the concrete column discussed in the video?

    -The column discussed in the video has dimensions of 60x60 cm, with a standard height of 3.5 to 4 meters.

  • What material is used for the steel ties (sabuk) in the column formwork?

    -The steel ties (sabuk) used in the column formwork are made from hollow steel, specifically 5x5 cm hollow steel with a thickness of 4 mm.

  • What is the spacing for the steel ties (sabuk) along the height of the column?

    -The spacing for the steel ties (sabuk) is 1 meter between each tie, from the bottom to the top of the column.

  • How many steel ties (sabuk) are used for each meter of column height?

    -There are four steel ties (sabuk) used per meter of column height.

  • What is the purpose of the hollow steel ties (sabuk) in the formwork process?

    -The hollow steel ties (sabuk) help secure and maintain the formwork structure in place, ensuring that the column is correctly formed and held together during the concrete pouring process.

  • How is the formwork secured to ensure stability during installation?

    -The formwork is secured by tying the steel bars or hollow steel ties (sabuk) tightly, followed by adjusting the formwork for balance and stability before loading the concrete.

  • What is the final step after securing the formwork with steel ties?

    -The final step is to ensure the formwork is balanced and stable before proceeding to pour the concrete into the column mold.

  • How does the video highlight the importance of proper formwork installation?

    -The video emphasizes the importance of correctly setting up the formwork and tying the steel ties securely, as this ensures the strength and stability of the concrete column and the safety of the construction process.

  • What does the speaker ask the viewers to do at the end of the video?

    -At the end of the video, the speaker encourages viewers to support the channel by liking, commenting, and subscribing if they found the content useful.

Outlines

plate

This section is available to paid users only. Please upgrade to access this part.

Upgrade Now

Mindmap

plate

This section is available to paid users only. Please upgrade to access this part.

Upgrade Now

Keywords

plate

This section is available to paid users only. Please upgrade to access this part.

Upgrade Now

Highlights

plate

This section is available to paid users only. Please upgrade to access this part.

Upgrade Now

Transcripts

plate

This section is available to paid users only. Please upgrade to access this part.

Upgrade Now
Rate This

5.0 / 5 (0 votes)

Related Tags
ConstructionReinforced ConcreteFormworkColumn InstallationConstruction TipsBuilding TechniquesStructural IntegrityReinforcementConstruction TutorialDIY ConstructionCivil Engineering