Gantt Chart Excel Tutorial - How to make a Basic Gantt Chart in Microsoft Excel

Subjectmoney
7 Jun 201308:14

Summary

TLDRThis tutorial from excelfornoobs.com guides viewers on creating a basic Gantt chart in Microsoft Excel 2013. It starts with entering task data including start dates and durations. Then, it demonstrates how to insert a 3D stacked bar chart, configure it with task data, and adjust the chart's axis to display tasks in the correct order. The tutorial also shows how to remove unnecessary bars and gaps, and adjust the date bounds to match the project's start date. Finally, it suggests exploring more advanced tutorials for automated progress tracking in Gantt charts.

Takeaways

  • πŸ“Š **Gantt Chart Definition**: A Gantt chart is a graphical representation that depicts the timeline of a project's tasks.
  • πŸ“… **Data Input**: To create a Gantt chart, first input your tasks, start dates, and duration into columns in Excel.
  • πŸ”‘ **Chart Creation**: Insert a bar chart in Excel to start building the Gantt chart.
  • 🎨 **Chart Customization**: Select a 3D stacked bar chart for a more visual representation.
  • πŸ“‘ **Series Data Entry**: Add data series for start dates and duration (days to complete) to the chart.
  • πŸ”„ **Reversing Order**: Use the 'categories in reverse order' option to correctly sequence tasks from earliest to latest.
  • 🚫 **Removing Unnecessary Bars**: Format data series to 'no fill' to remove unnecessary bars representing non-working periods.
  • πŸ—“οΈ **Adjusting Date Bounds**: Format the axis to adjust the date range, ensuring the chart starts on the project's actual start date.
  • πŸ”’ **Understanding Date Numbers**: Excel represents dates with a serial number system; adjust the chart's minimum bound to match your project's start date.
  • πŸ–ΌοΈ **Final Touches**: Use the design tab to format the chart with titles, colors, and layout to your preference.
  • πŸ” **Advanced Tutorials**: There are more advanced tutorials available for creating automated Gantt charts that reflect task progress.

Q & A

  • What is the purpose of a Gantt chart in project management?

    -A Gantt chart is used to show the time frame of an overall project, broken down by each individual task, indicating the start date and duration of each task.

  • Which version of Microsoft Excel is the tutorial using?

    -The tutorial is using Microsoft Excel 2013.

  • How many columns of data are required to create a basic Gantt chart according to the tutorial?

    -Three columns of data are required: one for task names, one for start dates, and one for the duration of each task.

  • What type of chart is used as a basis for creating a Gantt chart in the tutorial?

    -A 3D stacked bar chart is used as the basis for creating a Gantt chart.

  • How do you add a new series to the chart in the tutorial?

    -You add a new series by clicking the 'Add' button in the 'Edit Series' dialog box and selecting the appropriate data range.

  • What does the 'Series Values' field in the 'Edit Series' dialog box represent?

    -The 'Series Values' field represents the range of cells that contain the data to be plotted for that series, such as start dates or duration of tasks.

  • How can you change the order of the tasks on the Gantt chart?

    -You can change the order of the tasks by right-clicking on the axis, selecting 'Format Axis', and then choosing 'Categories in reverse order'.

  • Why might you want to remove the fill from the bars representing the start date?

    -You might want to remove the fill from the bars representing the start date to clean up the chart and only show the duration of tasks, not the gaps between them.

  • How does Excel represent dates in the context of the tutorial?

    -In Excel, dates are represented by a serial number system, where each day is assigned a unique number.

  • What is the serial number for May 22nd, 2013, as mentioned in the tutorial?

    -The serial number for May 22nd, 2013 is 41414.

  • How can you adjust the date range displayed on the Gantt chart?

    -You can adjust the date range by right-clicking the date axis, selecting 'Format Axis', and manually entering the minimum and maximum bounds.

Outlines

00:00

πŸ“Š Creating a Basic Gantt Chart in Excel

The paragraph provides a step-by-step guide on creating a basic Gantt chart in Microsoft Excel 2013. It begins by explaining what a Gantt chart is and its purpose in project management. The tutorial then instructs viewers to input data into three columns: Task, Start Date, and Days Complete. The Start Date column indicates when each task will commence, while the Days Complete column shows the duration of each task. After entering the data, the tutorial proceeds to guide users on how to insert a bar chart, select data for the chart, and format it to display the tasks in the correct order. The process includes adding series for start dates and duration, editing axis labels to list tasks, and adjusting the chart to display tasks in reverse order and to remove unnecessary date gaps.

05:00

πŸ”§ Refining the Gantt Chart

This paragraph continues the tutorial by addressing issues with the initial Gantt chart setup. It explains how to remove unnecessary bars that do not represent any task and how to adjust the date axis to remove gaps and accurately reflect the project's start date. The tutorial demonstrates converting dates to a serial number format to set the chart's bounds correctly. It concludes with tips on customizing the chart's design, including changing the layout, title, and colors. Additionally, it encourages viewers to explore more advanced tutorials on creating automated Gantt charts that reflect project progress.

Mindmap

Keywords

πŸ’‘Gantt Chart

A Gantt chart is a type of bar chart that illustrates a project schedule. It is used to show the start and finish dates of the terminal elements and summary elements which are usually high-level phases, and activities of a project. In the video, the Gantt chart is used to represent the timeline of tasks within a project, with each task's duration and start date clearly marked.

πŸ’‘Microsoft Excel 2013

Microsoft Excel 2013 is a spreadsheet program that is part of the Microsoft Office suite. It is widely used for data organization, calculations, and creating various types of charts, including Gantt charts. The video specifically mentions Excel 2013 as the platform on which the Gantt chart is being created.

πŸ’‘Task

In the context of project management, a task is a piece of work that is undertaken as part of a project. The video script refers to tasks as individual components of a larger project, each with a specific start date and duration.

πŸ’‘Start Date

The start date is the point in time at which a task is scheduled to begin. In the tutorial, the start date is an essential piece of data that determines when each task's bar will appear on the Gantt chart.

πŸ’‘Days Complete

This refers to the duration of a task, indicating how many days a task is expected to last. In the script, the 'days complete' column in the Excel spreadsheet is used to set the length of each task's bar on the Gantt chart.

πŸ’‘Bar Chart

A bar chart is a way of displaying data using bars. In the video, the creation of a Gantt chart begins with the selection of a bar chart in Excel, which will be customized to represent the project timeline.

πŸ’‘3D Stacked Bar Chart

This is a specific type of bar chart where the bars are stacked on top of each other and displayed in three dimensions. The script mentions selecting a 3D stacked bar chart as the starting point for creating the Gantt chart.

πŸ’‘Select Data Source

In Excel, the 'Select Data Source' dialog box allows users to choose the data that will be plotted in a chart. The video script describes using this feature to link the task data to the Gantt chart.

πŸ’‘Format Axis

This refers to the process of customizing the appearance and properties of the axis in a chart. The script explains how to use 'Format Axis' to adjust the order of tasks and to remove unwanted gaps in the date axis of the Gantt chart.

πŸ’‘Date Bound

The date bound is the range of dates displayed on the axis of a chart. In the context of the video, adjusting the date bound ensures that the Gantt chart only shows relevant dates, starting from the project's actual start date.

πŸ’‘Serial Number System

Excel uses a serial number system to represent dates, where each day is assigned a number. The script explains how to convert a date to its corresponding serial number to set the chart's start date accurately.

Highlights

Introduction to creating a basic Gantt chart in Microsoft Excel 2013

Explanation of what a Gantt chart is and its purpose

How to enter data into Excel for the Gantt chart

Setting up task names, start dates, and duration

Instructions on creating a chart using the Insert tab

Choosing the 3D stacked bar chart option

Accessing the Select Data Source dialog box

Entering the first series for the start dates

Moving the chart to access the data source

Adding a new series for the duration of tasks

Editing the horizontal axis labels with task names

Fixing the order of tasks in the Gantt chart

Removing unnecessary bars representing start dates

Adjusting the date axis to remove gaps

Understanding how dates are represented as numbers in Excel

Setting the minimum bound for the date axis

Finalizing the Gantt chart and customizing its appearance

Invitation to explore more advanced tutorials on creating Gantt charts

Transcripts

play00:00

guys welcome to excel for noobs.com in

play00:02

this tutorial i'm going to show you how

play00:03

to create a basic gantt chart in

play00:05

microsoft excel 2013 now what a gantt

play00:08

chart is is a chart that shows the time

play00:10

frame of an overall project broken down

play00:13

by the each individual by each

play00:15

individual task that the project is to

play00:17

consist of showing the time frame that

play00:20

each task is uh

play00:22

to take from start date to finish

play00:25

all right so you can see here first we

play00:26

have to enter in our data into excel

play00:28

before we can even create our chart so

play00:30

here i have three columns i have a task

play00:32

column these are all of my task tests

play00:34

one through eight the project is to

play00:35

consist of we have the start date

play00:38

these days dates represent the day that

play00:41

each task is to start so task 8 will

play00:44

start on july 15th and then we have the

play00:46

days complete column

play00:48

showing how long

play00:49

each project is to last so pro

play00:52

or each task is to last task 8 should

play00:54

last 12 days so if it starts on july

play00:57

15th

play00:58

task 8 should urge

play01:00

task 8 should end on july

play01:04

27th

play01:06

okay so we have our data now we can go

play01:08

ahead and get started creating our chart

play01:12

what we're going to do is click

play01:14

the insert button and in the

play01:18

chart the insert tab and in the charts

play01:20

group

play01:21

we're going to select

play01:23

our insert bar chart which is like a

play01:25

sideways bar chart basically

play01:29

okay so we click the insert bar chart

play01:31

and

play01:32

we are going to click

play01:35

on

play01:35

[Music]

play01:36

you can do either 2d stacked bar chart

play01:39

or 3d stacked bar chart

play01:42

so i'm going to click on the 3d stacked

play01:43

bar chart

play01:45

and then you can see that a blank chart

play01:46

area appears

play01:48

in the chart area

play01:49

i will now right click

play01:52

and in the shortcut menu i'm going to

play01:54

click on select data

play01:58

okay so you can see the select data

play02:00

source dialog box appears you can also

play02:02

see that our chart area and select data

play02:05

source dialog box is kind of blocking

play02:07

our data over here so we're going to

play02:08

move that out of the way but first let's

play02:10

enter in our first series

play02:12

right here in legend entries we're going

play02:14

to click the add button

play02:16

and the edit series dialog box will

play02:18

appear with the box for series name and

play02:20

series name we're going to enter we're

play02:22

going to select the start date column

play02:24

header

play02:26

and then

play02:27

in series values we're going to remove

play02:29

the default data and we're going we're

play02:31

going to enter in the

play02:33

we're going to select the range of cells

play02:34

that has our start dates and then we'll

play02:37

click ok

play02:39

ok

play02:40

now i'm going to click ok so i can move

play02:42

this out of the way

play02:44

and so i can also get this chart

play02:47

out of the way okay now in a blank area

play02:49

of the chart somewhere up here i'm going

play02:51

to right click again to get to um the

play02:54

select data source dia log box and you

play02:56

can see i'm clicking on select data and

play02:58

it appears just now i can access my that

play03:01

over here all right now i need to add a

play03:03

new series we're going to click the add

play03:05

button

play03:06

and in series name i will select days to

play03:08

complete

play03:12

in series values again remove the

play03:14

default data and select the range of

play03:16

cells that has our data is complete

play03:19

click ok

play03:20

and again we're back at our select data

play03:22

source dialog box now on the horizontal

play03:24

axis label

play03:26

click the edit button and i'm going to

play03:28

select task 1 through task eight

play03:33

and click ok

play03:36

now we have all of our data

play03:38

so we can close our select data source

play03:39

dialog box

play03:42

okay so you can see that we're on our

play03:44

way to having a gantt chart what is

play03:46

going on

play03:48

okay you can see we're on our way to

play03:49

having a gantt chart i'm just kind of

play03:50

resizing it

play03:52

now you can see a few problems our tasks

play03:54

right here in reverse order so we need

play03:56

to fix that

play03:58

we have these blue bars here which

play03:59

represent

play04:00

um the start date and

play04:03

then we have our dates

play04:06

which uh there's a large gap see our

play04:08

project's gonna start on may 22nd

play04:11

we don't really want our chart the

play04:14

bounds of our dates to go all the way to

play04:16

april 16th so we want to remove that we

play04:19

want this chart i want to remove those

play04:21

uh

play04:22

these boundaries these um

play04:25

these gaps of dates

play04:28

so uh the first thing we're going to do

play04:30

is just get our

play04:31

we want to get our task in the right

play04:33

order so just click right here on the

play04:35

task and then right click

play04:38

and click on format axis and the

play04:41

shortcut menu

play04:43

and then the the axis options will

play04:45

appear over here to the right the format

play04:46

axis dialog box and in access position

play04:49

you're gonna click categories in reverse

play04:51

order

play04:53

okay so the first problem is solved now

play04:56

let's get rid of these bars there's

play04:58

nothing going on

play05:00

during this time

play05:02

for these projects so we don't need any

play05:04

bars there to represent anything

play05:06

all we want is to uh we want bars that

play05:09

represent

play05:10

the task

play05:12

when they're going to be um

play05:14

when they will the time frame of the

play05:15

task so we click on the bars

play05:18

which represent the start date

play05:21

and then we're going to right click

play05:23

and then click format data series

play05:27

and the format data series dialog box

play05:28

appears we will click on the fill button

play05:31

and then we'll select no fill

play05:34

then we can close this all right

play05:36

final problem let's get rid of this gap

play05:39

in the dates so we just uh

play05:41

let's get rid of this

play05:43

padding of the dates i mean you can see

play05:45

it's more than a month the chart

play05:47

shows a date that's more than a month

play05:48

before our startup date so let's get rid

play05:50

of that

play05:51

so we click on the dates

play05:52

then we right click

play05:54

and again select

play05:57

format axis

play05:59

okay you can see over here our bounds

play06:01

these are our dates these numbers

play06:03

represent our dates actually let me

play06:05

close this and kind of explain how dates

play06:07

work i'm going to copy this date and

play06:10

enter into another cell may 22nd our

play06:12

start date now i'm going to convert this

play06:15

to

play06:16

a number format

play06:18

and you can see

play06:19

that

play06:20

um our dates are actually represented

play06:23

by a number and that's how it works

play06:25

dates in excel are represented by a

play06:27

serial number system so the uh number

play06:30

the serial number for may 22nd 2013 is

play06:33

41 416 and that's where we want our

play06:36

chart to start

play06:38

so just we're going to keep that there

play06:39

so we remember that number so again

play06:41

click on the dates

play06:43

right click

play06:45

format axis and then here in the minimum

play06:47

bound

play06:48

we will enter

play06:50

the date

play06:52

that we want our chart bounds

play06:54

to show so we're custom

play06:57

manually entering in

play06:59

that number which represents may 22 2013

play07:01

and we hit enter and there you can see

play07:04

now our chart starts on may 22nd

play07:07

22nd 2013.

play07:09

we can close that

play07:12

and then

play07:14

um let me remove this and now you can

play07:17

see that we have our gantt chart here

play07:19

now all you have to do is you can change

play07:21

different um

play07:22

formatting to the chart so we can go to

play07:23

the design and we can change the layout

play07:25

i like this layout

play07:27

you can

play07:28

change the title

play07:33

and you can mess around and change the

play07:35

color and anything else you want to

play07:36

change all right thanks for watching

play07:38

guys now you know how to make a basic

play07:40

gantt chart in microsoft excel 2013

play07:43

don't forget to check out all of our

play07:44

other tutorials and we also have

play07:47

a more advanced tutorial on how to

play07:48

create a gantt chart that is that

play07:50

automatically shows the progress

play07:53

of a project and each task it shows the

play07:55

days completed of each task

play07:58

and it shows the days remaining

play08:01

for each task

play08:02

and it's automated using the now

play08:05

function and a nested if function so be

play08:07

sure to look that up alright thanks for

play08:09

watching

play08:10

and have fun with excel

Rate This
β˜…
β˜…
β˜…
β˜…
β˜…

5.0 / 5 (0 votes)

Related Tags
Excel TutorialGantt ChartProject ManagementData VisualizationTask PlanningMicrosoft ExcelTime TrackingChart FormattingBusiness ToolsTutorial