Progres Pembangunan IKN Tahap 1 Tembus 97%
Summary
TLDRThe mega project of the new capital city, Nusantara (IKN), is progressing well, with 97.2% completion as of December 2024. The project, divided into three stages, is primarily funded through the national budget (APBN), with ongoing development for government facilities. Progress on housing for civil servants is also notable, with architectural work nearing completion. Among the residential units, SN1 is at 91.3%, SN2 at 85.3%, SN3 at 85.1%, and SN4 at 87.8%. The overall effort aims to ensure that the capital's core government infrastructure is fully operational in the near future.
Takeaways
- 😀 The first phase of the mega project for the capital city, Nusantara (IKN), is 97.2% completed as of December 2024.
- 😀 The project is progressing with the goal of making the central government area functional by the end of the year.
- 😀 The development is split into three phases, with funding sourced from the state budget (APBN) and non-APBN funds.
- 😀 The Ministry of Public Works and Housing (PUPR) is handling projects funded by the state budget.
- 😀 A total of 16 project packages are underway, with an average progress rate of 92%.
- 😀 The first residential developments for civil servants, known as SN1, SN2, SN3, and SN4, are near completion.
- 😀 The completion of SN1 housing is at 91.3%, SN2 at 85.3%, SN3 at 85.1%, and SN4 at 87.8%.
- 😀 The focus is on architectural completion for these residential units as they move toward final stages.
- 😀 The completion of phase 1 is on track to meet the deadlines set for 2024.
- 😀 The overall progress demonstrates significant achievements in both construction and housing development for the IKN project.
Q & A
What is the current progress of the first stage of the Nusantara (IKN) mega project as of December 2024?
-As of December 2024, the first stage of the Nusantara (IKN) mega project has reached 97.2% progress.
What is the primary target for the Nusantara (IKN) project in 2024?
-The primary target for the Nusantara (IKN) project in 2024 is the functionalization of the central government area.
How is the Nusantara (IKN) project divided?
-The Nusantara (IKN) project is divided into three stages, with the third stage being a project supported by funding from the State Budget (APBN).
What is the role of the Ministry of Public Works and Public Housing (PUPR) in the Nusantara project?
-The Ministry of Public Works and Public Housing (PUPR) is involved in the project with funding from the State Budget (APBN).
How many work packages are there in the Nusantara project, and what is the average progress of these packages?
-There are 16 work packages in the Nusantara project, and the average progress of these packages is 92%.
What is the progress of the first residential area (SN1) in the Nusantara project?
-The progress of the first residential area (SN1) in the Nusantara project has reached 91.3%.
What is the progress of the second residential area (SN2) in the Nusantara project?
-The progress of the second residential area (SN2) in the Nusantara project has reached 85.3%.
What is the current progress of the third residential area (SN3) in the Nusantara project?
-The third residential area (SN3) in the Nusantara project has reached 85.1% progress.
What is the progress of the fourth residential area (SN4) in the Nusantara project?
-The fourth residential area (SN4) in the Nusantara project has reached 87.8% progress.
What type of housing is being developed in the Nusantara project?
-The housing being developed in the Nusantara project includes residences for civil servants (ASN).
Outlines

Этот раздел доступен только подписчикам платных тарифов. Пожалуйста, перейдите на платный тариф для доступа.
Перейти на платный тарифMindmap

Этот раздел доступен только подписчикам платных тарифов. Пожалуйста, перейдите на платный тариф для доступа.
Перейти на платный тарифKeywords

Этот раздел доступен только подписчикам платных тарифов. Пожалуйста, перейдите на платный тариф для доступа.
Перейти на платный тарифHighlights

Этот раздел доступен только подписчикам платных тарифов. Пожалуйста, перейдите на платный тариф для доступа.
Перейти на платный тарифTranscripts

Этот раздел доступен только подписчикам платных тарифов. Пожалуйста, перейдите на платный тариф для доступа.
Перейти на платный тарифПосмотреть больше похожих видео

[LIVE] Konferensi Pers "Skema Pemindahan ASN ke Ibu Kota Nusantara (IKN)"

Proyek IKN dalam Tahap Pembangunan, Direncanakan Rampung 2024 | tvOne Minute

SIARAN PERS MENPAN RB ‼️ PELAKSANAAN SELEKSI CPNS DAN PPPK 2024 ‼️

Mengenal Desa Bukit Raya, Smart Village Cikal Bakal Kota Cerdas di IKN Nusantara

Why Indonesia is spending billions to build its new capital Nusantara | DW News

15 Proyek Raksasa Prabowo, Efisiensi Anggaran untuk Proyek Ini? - [Metro Siang]
5.0 / 5 (0 votes)