KELOMPOK 3 - Proses Penanganan Klaim
Summary
TLDRIn this video, the presenters from Group 3 of the Civil Engineering department at Halu Oleo University explain the process of handling claims in construction projects. They discuss the causes of construction claims, such as inaccurate design information and project delays, as well as the types of claims, including additional costs and time. The video highlights the importance of contract administration, the role of contract managers, and methods for evaluating and resolving claims. They also discuss a case study, demonstrating how claims arise due to design changes and additional work by the owner, with common solutions including engineering judgment.
Takeaways
- 😀 Construction claims are formal requests related to issues in executing construction projects, often involving disputes between contractors and clients.
- 😀 Claims may involve requests for additional time, compensation, or other adjustments to the original contract terms.
- 😀 The causes of construction claims include incorrect design information, incomplete design, poor site investigations, slow claim responses, and poor communication.
- 😀 Common types of claims in construction projects include additional costs, indirect costs, time extensions without compensation, and compensation claims.
- 😀 Effective contract administration from the start is crucial in handling claims successfully.
- 😀 Contract managers play a key role in managing claims, from their initial occurrence to resolution, and must gather all relevant information for evaluation.
- 😀 Investigation steps for handling claims include gathering project documents, understanding the organizational structure, and assessing the impact of the claims.
- 😀 All amendments to the contract related to claims should be documented through change orders to ensure formal recognition.
- 😀 If claims are not resolved through regular negotiation, they may escalate to legal disputes or arbitration as per the contract terms.
- 😀 The case study highlights that design changes and additional work requested by owners are the main causes of contractor claims in construction projects.
- 😀 Common methods for resolving claims include engineering judgment, and contractors typically seek compensation for additional costs incurred due to changes in scope.
Q & A
What is the main topic of the script?
-The main topic of the script is the process of handling claims in construction projects, focusing on the reasons behind claims, types of claims, and how they are managed and resolved.
What is a construction claim as described in the script?
-A construction claim is a formal request related to the execution of construction work, such as additional time or compensation, that arises due to issues between the service provider and the client or among subcontractors.
What are some of the primary causes of construction claims mentioned in the script?
-Some of the primary causes include inaccurate or incomplete design information, poor site investigation, slow response to claims, and poor communication.
How does the script describe the types of construction claims?
-The types of construction claims mentioned in the script include claims for additional costs and time, indirect or overhead costs, claims for additional time without costs, and compensation claims.
What is the role of contract administration in handling claims?
-Contract administration plays a crucial role in managing claims by ensuring proper documentation and accuracy in managing the contract from the moment it is signed.
What are the initial steps in handling a construction claim according to the script?
-The initial steps include gathering all documents related to the claim, investigating the issue, analyzing the impact, and understanding the losses involved.
What are the essential documents needed for evaluating a construction claim?
-Essential documents include the contract document, changes to the work, summaries of the work, meeting minutes, and correspondence with the service provider.
What should happen after receiving a construction claim?
-After receiving a construction claim, all related documents should be collected, and the project team should analyze the claim to prepare a response.
How should changes to a contract be handled during a claim resolution process?
-Once the claim is resolved, change orders must be issued, and any modifications to the contract should be carefully documented and overseen.
What happens if the claim resolution process does not lead to an agreement?
-If the claim resolution process fails to lead to an agreement, the dispute may escalate to a legal or arbitration process as per the contract's terms.
What was the case study discussed in the script regarding claims in construction?
-The case study discussed in the script involved a construction claim made by a contractor to the building owner, focusing on how claims arise from design changes, additional work, and how claims are processed and resolved.
What were the primary causes of claims in the case study?
-The primary causes of claims in the case study were design changes and additional work requested by the building owner.
What conclusions did the author draw from the case study?
-The author concluded that claims are more commonly initiated by building owners due to design changes and additional work, and contractors often seek additional costs in their claims.
What methods were used to conduct the study in the case?
-The study used two methods: literature review, gathering information from books and journals, and field study, which involved interviews with companies involved in the case study.
Outlines

Esta sección está disponible solo para usuarios con suscripción. Por favor, mejora tu plan para acceder a esta parte.
Mejorar ahoraMindmap

Esta sección está disponible solo para usuarios con suscripción. Por favor, mejora tu plan para acceder a esta parte.
Mejorar ahoraKeywords

Esta sección está disponible solo para usuarios con suscripción. Por favor, mejora tu plan para acceder a esta parte.
Mejorar ahoraHighlights

Esta sección está disponible solo para usuarios con suscripción. Por favor, mejora tu plan para acceder a esta parte.
Mejorar ahoraTranscripts

Esta sección está disponible solo para usuarios con suscripción. Por favor, mejora tu plan para acceder a esta parte.
Mejorar ahoraVer Más Videos Relacionados

Interdisciplinary nature of modern construction projects

KEREN BANGET NIH !!!!! TUTORIAL PEMBUATAN BETON , PROGRAM STUDI TENIK SIPIL UNIVERSITAS KADIRI 😊🤩

Sistem Pendeteksi Awal Kebakaran Hutan Berbasis IoT

4 Things You Should Know About CIVIL ENGINEERING

Aula Prática 1 - Granulometria Conjunta em Solos

CARA PELAKSANAAN UJI GESER LANGSUNG, UJI KUAT TEKAN BEBAS, DAN TRIAXIAL TEST || RJJ 3B 2021
5.0 / 5 (0 votes)