Precio Unitario de Zapata Corrida

Ingenieria Integral
11 Jun 202222:38

Summary

TLDRThis educational video script offers a detailed tutorial on analyzing a 60-centimeter wide reinforced concrete slab, 1 meter long and 20 centimeters thick, designed for a linear meter. It covers material calculations for concrete, rebar, and wire, including waste percentages, and provides a step-by-step guide on determining quantities and costs. The script also explains labor calculations for both the rebar and concrete pouring teams, considering efficiency and unit prices. Finally, it addresses equipment needs and indirect costs, concluding with the total cost per linear meter of the slab.

Takeaways

  • 🏗️ The video is a tutorial for architects, engineers, and students on analyzing a 'zapata corrida' (a type of concrete slab), specifically one that is 60 centimeters wide.
  • 📏 The analysis covers a linear meter of the slab, which is 60 centimeters wide, 1 meter long, and 20 centimeters thick, made with 250-grade concrete and reinforced with medium-sized rebar every 20 centimeters in both directions.
  • 📋 The tutorial includes a list of materials needed, such as concrete, rebar, and wire, and provides a method to quantify the amount of each material required for the construction.
  • 📘 The script references a book by engineer Suárez for concrete mix ratios and strength information, which is essential for calculating the amount of cement, sand, gravel, and water needed.
  • 🛠️ The cost of materials is calculated by multiplying quantities by unit prices, including a basic price for on-site concrete production and a 5% waste factor for concrete.
  • 🧵 The amount of rebar needed is determined by the spacing and the length of the slab, with a 3% waste factor for steel, and the weight of the rebar is converted from meters to tons.
  • 🔢 The quantity of wire required is calculated based on the number of intersections and the average length of wire used for each tie, considering a 50% waste factor.
  • 👷‍♂️ The labor cost is estimated by the number of workers needed for each task, such as rebar tying and concrete pouring, and their respective daily wages, including a real salary factor.
  • 👷‍♀️ The tutorial explains how to calculate the productivity of the labor force, which is measured in terms of how many tons of rebar can be tied or how many cubic meters of concrete can be poured per workday.
  • 🚜 Equipment costs are factored in, including the use of a concrete mixer and a vibrator, with their respective productivity rates considered in the calculation.
  • 💰 The total direct cost is the sum of materials, labor, and equipment, and an indirect cost of 30% is added to this subtotal to determine the final cost per linear meter of the slab.

Q & A

  • What is the main topic of the video?

    -The main topic of the video is to analyze a 60-centimeter wide flat slab, specifically a flat slab with a thickness of 20 centimeters, made of concrete with a resistance of 250, and reinforced with rebar at every 20 centimeters in both directions.

  • What is the purpose of the analysis in the video?

    -The purpose of the analysis is to calculate the materials, manpower, equipment, and all the necessary elements for the execution of a flat slab construction project.

  • What are the dimensions of the flat slab being analyzed?

    -The flat slab being analyzed is 60 centimeters wide, 1 meter long, and 20 centimeters thick.

  • What is the concrete strength used for the flat slab?

    -The concrete strength used for the flat slab is 250.

  • What is the rebar spacing mentioned in the video?

    -The rebar spacing mentioned in the video is every 20 centimeters in both directions.

  • What does the video cover regarding the calculation of materials needed?

    -The video covers the calculation of concrete in cubic meters, rebar in tons, and wire in kilograms needed for the construction of the flat slab.

  • How does the video approach the calculation of concrete volume?

    -The video approaches the calculation of concrete volume by using the dimensions of the slab (width, length, and thickness) and accounting for a 5% waste factor.

  • What is the role of the 'ingeniero Suárez al azar' mentioned in the video?

    -The 'ingeniero Suárez al azar' is referred to for reference in his book on construction, which provides the proportions needed to produce concrete with a resistance of 250 and other relevant information for structural analysis.

  • How is the cost of materials calculated in the video?

    -The cost of materials is calculated by multiplying the quantities of cement, sand, gravel, and water by their respective unit prices, and then summing these amounts to get the total material cost for one cubic meter of concrete.

  • What is the process for calculating the amount of rebar needed?

    -The process for calculating the amount of rebar needed involves determining the number of rebar pieces required for both the longitudinal and transversal directions, converting the linear meters of rebar to kilograms, and then to tons, while also accounting for a 3% waste factor.

  • How is the amount of wire needed calculated in the video?

    -The amount of wire needed is calculated by determining the number of ties to be made at each intersection of rebar, measuring the average length of wire used for each tie on-site, and then accounting for a 50% waste factor.

  • What is the approach to calculating labor costs in the video?

    -Labor costs are calculated by determining the specialized workforce needed (such as rebar workers and bricklayers), calculating the daily cost of each worker, and then determining the productivity rate (how many tons of rebar or cubic meters of concrete they can process per day) and multiplying it by the unit price of the workforce.

  • What is the role of equipment in the cost calculation?

    -Equipment such as the mixer and vibrator are considered in the cost calculation by determining their productivity (how many cubic meters they can process) and then applying a percentage to the total labor cost for equipment and safety gear.

  • How is the indirect cost calculated in the video?

    -The indirect cost is calculated by multiplying the direct cost (which includes material, labor, and equipment) by a percentage that represents the overhead charges, in this case, 30%.

  • What is the final cost per linear meter of the flat slab construction?

    -The final cost per linear meter of the flat slab construction, after accounting for material, labor, equipment, direct and indirect costs, is 130 and 1.48 pesos.

Outlines

00:00

📏 Material List and Concrete Calculation for Slab Analysis

The video begins with an introduction to the analysis of a 60 cm wide slab, 1 meter long, and 20 cm thick made of concrete with a resistance of 250. The presenter outlines the need to create a material list for the project, which includes concrete, rebar, and binding wire. The focus is on quantifying the amount of concrete needed for a linear meter of the slab, taking into account a 5% waste factor. A table is used to assist with calculations, and the video references a book by Engineer Suárez for concrete mix ratios and prices. The aim is to determine the cost of materials per cubic meter of concrete.

05:02

🔍 Rebar Quantification and Calculation for Slab Reinforcement

This paragraph delves into the process of calculating the amount of rebar needed for the slab. The video explains how to determine the number of rebar pieces required in both the longitudinal and transversal directions, given a 20 cm spacing. It discusses the importance of considering the rebar's length and the structural implications of the slab's design. The presenter calculates the total weight of the rebar in kilograms and then converts it to tons, including a 3% waste factor for steel. The goal is to ascertain the quantity of rebar needed per linear meter of the slab.

10:04

🛠️ Wire Calculation and Labor Estimation for Slab Construction

The script moves on to calculate the amount of wire needed for the slab's reinforcement, detailing the number of ties to be made at each intersection. It provides an average length for wire cuts based on field measurements and includes a 50% waste factor for the wire. The paragraph also addresses the labor required for the construction, breaking down the specialized crews needed, such as the ironworker's team and the mason's team, and their respective costs. The presenter discusses the concept of labor efficiency and how it affects the cost of the workforce per day of work.

15:04

👷‍♂️ Workforce Efficiency and Equipment Requirements for Slab Casting

This section focuses on determining the efficiency of the workforce for both steel reinforcement and concrete casting. It explains how to measure the average number of workdays needed to process a ton of steel and a cubic meter of concrete. The video provides specific figures for the efficiency of steelworkers and masons, including the number of workers required for casting a cubic meter of concrete. It also touches on the equipment needed, such as a mixer and vibrator, and their respective outputs.

20:05

💰 Direct and Indirect Costs Calculation for Slab Project

The final paragraph wraps up the video by explaining how to calculate the direct and indirect costs of the slab project. It covers the summation of material, labor, and equipment costs to establish the direct cost. An indirect cost, which is typically a percentage of the direct cost, is also factored in, with the video using a 30% indirect cost as an example. The presenter concludes by providing a total cost for each linear meter of the 60 cm wide slab, including both direct and indirect expenses.

Mindmap

Keywords

💡Reinforced Concrete

Reinforced concrete is a composite material that combines steel reinforcement bars, known as rebars, with concrete to improve its tensile strength. In the video, the construction of a 'zapata corrida' (a type of concrete slab) is discussed, where rebar is used to strengthen the concrete slab, ensuring it can withstand the loads and pressures it will be subjected to.

💡Linear Meter

A linear meter refers to a unit of length equal to one meter. In the context of the video, the analysis is performed for a linear meter of the slab, which means the calculations and measurements are based on a one-meter length of the construction element being discussed.

💡Thickness

Thickness in this script refers to the dimension of the slab measured from top to bottom. The script mentions a thickness of 20 centimeters for the 'zapata corrida,' which is a critical measurement for determining the volume of materials required for construction.

💡Steel Rebar

Steel rebar, also known as reinforcement bar, is used to strengthen concrete structures. The script details the use of medium-sized rebar spaced every 20 centimeters in both directions within the slab, which is essential for the structural integrity of the construction.

💡Concrete Slab

A concrete slab is a flat, horizontal surface made from concrete. In the video, the construction of a 'zapata corrida' is analyzed, which is a specific type of concrete slab used in construction projects.

💡Material List

A material list is an inventory of all the materials required for a construction project. The video script includes the creation of a material list for the 'zapata corrida,' detailing the types and quantities of materials such as concrete, rebar, and binding wire needed for the construction.

💡Unit of Measure

In construction, a unit of measure is used to quantify the amount of materials needed. The script discusses calculating the concrete in cubic meters, rebar in tons, and binding wire in kilograms, which are all units of measure for the respective materials.

💡Waste Percentage

Waste percentage is the amount of material that is expected to be unusable or lost during a construction process. The script mentions a 5% waste factor for concrete, which is taken into account when calculating the total amount of concrete needed for the slab.

💡Cement

Cement is a binder used in the production of concrete, critical for holding the concrete together. The script references the need to calculate the amount of cement, sand, and aggregate required to produce the specified concrete resistance of 250, which is a measure of the concrete's strength.

💡Labor Cost

Labor cost refers to the expenses associated with paying the workers involved in a construction project. The video script discusses calculating the labor cost for both the rebar team and the concrete pouring team, including the number of workers, their roles, and the cost per day of work.

💡Equipment Cost

Equipment cost is the expense related to using machinery and tools necessary for construction. The script mentions the use of a mixer for the concrete and a vibrator for compacting it, and it discusses calculating the cost of using this equipment as part of the overall project expenses.

💡Direct Cost

Direct cost is the total cost of materials, labor, and equipment directly involved in the construction process. The script explains how to calculate the direct cost by summing the costs of materials, labor, and equipment for the 'zapata corrida' project.

💡Indirect Cost

Indirect cost refers to the additional costs not directly tied to the construction process itself, such as management or overhead costs. The video script mentions an indirect cost of 30%, which is applied to the direct cost to determine the total cost of the project.

Highlights

Introduction to analyzing a 60 cm wide slab with a 1-meter linear analysis.

Description of the slab: 60 cm by 1 meter by 20 cm thick, made with 250-grade concrete and medium rebar at 20 cm intervals.

Explanation of materials needed including concrete, rebar, and binding wire.

Calculation of concrete volume with a 5% waste factor for a 1-meter linear slab.

Use of a table to assist in calculating concrete, rebar, and wire quantities.

Determination of cement, sand, gravel, and water quantities for concrete mix.

Price calculation for materials based on supplier costs.

Quantification of rebar needed per linear meter of slab.

Calculation of rebar weight and conversion to tons with a 3% waste factor for steel.

Determination of wire quantity needed for each linear meter of slab.

Estimation of labor costs for steel fixing and concrete pouring crews.

Calculation of labor productivity rates for steel fixing and concrete pouring.

Inclusion of equipment costs such as mixers and vibrators in the total cost calculation.

Addition of indirect costs, considering a 30% overhead rate.

Final cost calculation for the 60 cm wide slab per linear meter.

Conclusion summarizing the total cost per linear meter of the slab.

Invitation for viewers to subscribe and comment for future videos.

Transcripts

play00:04

[Música]

play00:09

[Música]

play00:14

hola arquitectos ingenieros y

play00:16

estudiantes de youtube el día de hoy

play00:18

vamos a analizar una zapata corrida

play00:20

vamos a analizar una zapata corrida de

play00:22

60 centímetros de ancho y el análisis va

play00:25

a ser por un metro lineal recuerda son

play00:27

análisis de presión itario por lo tanto

play00:30

se analiza un metro solamente bueno

play00:34

entonces vamos a iniciar hay que leer la

play00:37

descripción

play00:38

zapata z 2 de 60 centímetros del perdón

play00:42

de puntos 60 metros por un metro de

play00:45

largo

play00:46

por y 20 centímetros de espesor

play00:53

elaborado con concreto resistencia 250

play00:55

de armada con varilla de media a cada 20

play00:58

centímetros en ambos sentidos

play01:01

incluye materiales mano de obra equipo y

play01:04

todo lo necesario para su frente

play01:05

ejecución bueno primeramente tenemos que

play01:07

hacer el listo de material y qué es lo

play01:10

que vamos a necesitar

play01:12

vamos a necesitar

play01:16

en concreto resistencia 250 aquí dicen

play01:18

la destrucción varilla de media y

play01:21

alambre

play01:23

el alambre para amarrar la varilla donde

play01:26

se interceptan bueno todos juramos que

play01:29

tenemos el listado vamos a vamos a hacer

play01:33

una unidad de medida el concreto por

play01:35

metro cúbico la varia por toneladas y el

play01:37

alambre por kilos necesitamos

play01:39

cuantificar

play01:41

cuántos metros cúbicos de concreto

play01:43

necesitamos para un metro lineal de

play01:46

zapata corrida

play01:51

para calcular el concreto tenemos esta

play01:53

tabla es una tablita nos va a ayudar no

play01:56

es más que una ayuda para

play01:59

multiplicar dividir y restar o sea

play02:01

calcular y porque lo hacemos aquí porque

play02:05

nos queda ya como referencia cuando

play02:08

volvamos a revisar este análisis es que

play02:11

vamos a hacer vamos a cuantificar el

play02:14

concreto para empezar cuáles son las

play02:17

medidas que vamos a colar 60 por un

play02:21

metro por 20 centímetros de espesor

play02:23

bueno pues vamos a capturar este ancho

play02:26

punto 60 largo un metro y espesor 20

play02:29

centímetros y apuntó 20 y el desperdicio

play02:32

el concreto siempre va a llevar un

play02:33

desperdicio de 5 por ciento

play02:36

y piezas eso es una una sección la que

play02:40

estamos colando entonces vamos a hacer

play02:42

el cálculo de este volumen ancho por

play02:45

largo por el espesor por el desperdicio

play02:47

por el número de pisos y tenemos puntos

play02:49

126 metros cúbicos es la cantidad que

play02:51

vamos a colocar aquí colocamos signo

play02:53

igual y lo seleccionamos y luego enter

play02:56

para que nos quede vinculado

play02:57

el precio del concreto peso unitario

play03:00

como este concreto va a ser elaborado en

play03:03

obra

play03:04

necesitamos realizar un básico

play03:08

y el básico que es es calcular la

play03:12

cantidad de cemento arena grama y agua

play03:15

que necesitamos y calcular le un precio

play03:18

como referencia tenemos el ingeniero

play03:20

suárez al azar en su libro con su tiempo

play03:23

en edificación ahí en su libro podemos

play03:26

obtener las cantidades o sea las

play03:28

proporciones que necesitamos para

play03:29

fabricar un metro cúbico de resistencia

play03:31

250 y también en ese libro podemos

play03:34

encontrar resistencias de 100 en 150 y

play03:37

200

play03:39

y mucha más información que necesitamos

play03:42

para los análisis de pres solitarios

play03:43

bueno entonces las cantidades ocupamos

play03:47

un to 400 partes y 5 toneladas de

play03:49

cemento punto 46 metros cúbicos de arena

play03:51

control desde 2 metros cúbicos de grava

play03:53

y punto 26 metros cúbicos de agua y el

play03:56

precio unitario es el precio que nos da

play03:58

el proveedor

play04:00

en el agua bueno pues este si estamos

play04:02

utilizando agua de tomás vamos a poner

play04:03

el precio que nos están dando en el

play04:05

recibo del agua de la junta de agua

play04:07

potable

play04:08

entonces multiplicamos las cantidades

play04:10

por el precio que nos da el proveedor y

play04:12

obtenemos un importe sumamos y ya

play04:15

tenemos un básico 2900 37.07 lo que nos

play04:18

cuesta el material

play04:21

para fabricar un metro cúbico de

play04:23

concreto esta cantidad es la que vamos a

play04:25

colocar aquí impresión itario y

play04:27

colocamos signo igual y los

play04:29

seleccionamos bueno pues ahora lo

play04:32

multiplicamos ya tenemos un importe la

play04:34

cantidad por el presión etario ahora la

play04:36

varilla hay que cuantificar cuántas

play04:38

toneladas de varilla de media

play04:39

necesitamos por cada metro lineal

play04:41

recuerda que tenemos varillas en un

play04:44

sentido que vamos a llamarle este

play04:46

sentido

play04:47

transversal

play04:49

y tenemos varias en el sentido

play04:52

longitudinal

play04:55

bueno pues hay que calcular cuánto pesan

play04:57

esas varias que necesitamos

play05:02

primeramente hay que ver nos dice aquí

play05:04

separación de la varilla aquí estamos

play05:08

viendo que la varia va a estar a cada 20

play05:10

centímetros es la separación pues vamos

play05:12

a colocar aquí punto 20

play05:16

aquí no hice pieza inicial aquí

play05:18

solamente para tenerlo de referencia

play05:20

vamos a colocar uno porque lo estamos

play05:22

refiriendo de esta pieza inicial

play05:24

ahora vamos vamos a ver por qué o para

play05:26

qué nos sirve bueno necesitamos calcular

play05:29

cuántas piezas necesitamos por cada

play05:32

sentido cuántas piezas

play05:34

en este sentido

play05:36

es una longitudinal y cuántas piezas en

play05:39

este sentido que es el transversal

play05:41

cómo lo vamos a obtener solamente es

play05:43

dividiendo

play05:45

si vamos a sacar primeramente en este

play05:47

sentido

play05:48

cuántos ocupamos aquí en el

play05:51

200 centímetros de ancho cuántas

play05:54

varillas longitudinales ocupamos lo que

play05:56

vamos a hacer es dividir estos 60

play05:59

centímetros entre la separación

play06:02

no más el primero que una calculadora

play06:04

por ejemplo

play06:06

2.60

play06:08

entre punto 20 que es la separación que

play06:11

ocupamos tres varillas más uno que es la

play06:14

varilla inicial

play06:17

o sea cuatro sería esta varilla la

play06:20

inicial también por eso que estamos

play06:22

colocando uno aquí y ocupamos cuatro

play06:26

varillas y hacemos el cálculo aquí

play06:28

piezas colocamos en igual puntos 60

play06:32

entre 1.20 más 1 ya tenemos cuatro

play06:37

presos de que largo

play06:42

estamos calculando

play06:43

cuántas varillas en el sentido

play06:45

longitudinal y de qué largo son de un

play06:48

metro y

play06:50

un metro y bueno todo va a depender si

play06:55

es una parrilla pequeña así como esta

play06:57

verdad aquí estamos viendo que son

play06:59

ganchitos de manguitos es para una una

play07:03

zapata como ésta son los gallitos de 5

play07:05

centímetros aproximadamente por eso te

play07:07

lo va a determinar el estructural

play07:11

si es una parrilla está lo que va a ser

play07:13

es una zapata va a ser una zapata con

play07:16

doble armado armado acá arriba porque se

play07:19

ve una escuadra muy grande

play07:21

entonces aquí es donde ya sacamos por

play07:25

ejemplo aquí que largo hacer un metro

play07:27

más la escuadra para si fuera una doble

play07:31

parrilla un lado de una dobla armado

play07:33

pero si es una un armado sencillo y

play07:36

pequeño

play07:37

entonces que cuánto va a ser va a ser un

play07:40

metro

play07:42

y el ganchito son de 5 centímetros bueno

play07:46

pero les hago esta aclaración porque en

play07:49

el vídeo anterior no hicieron un

play07:50

comentario bueno es un metro más el

play07:52

ganchito bueno puede ser que bueno ya

play07:55

depende de tu criterio verdad pero si

play07:57

usamos este criterio si la varía la

play07:58

corte de un metro verdad me va a quedar

play08:02

al puro ras y no haber recubrimiento me

play08:04

comentaron te falta el ganchito o la

play08:07

escuadra y el recubrimiento bueno si yo

play08:09

corto la varilla de un metro no tengo

play08:11

recubrimiento pero si a ese metro le

play08:13

hago 5 centímetros d'esquadra o de

play08:16

ganchito

play08:18

ya le estoy descontando 5 centímetros

play08:20

entonces ya estoy dejándole esos 5

play08:23

centímetros como un recubrimiento y ya

play08:26

tengo también el ganchito o la escuadra

play08:30

por eso es que en el vídeo anterior de

play08:33

la zapata aislada no tenía un largo

play08:37

adicional por eso dejé un métro

play08:41

bueno

play08:44

y la longitud total serían cuatro piezas

play08:47

por un metro de largo tenemos cuatro

play08:50

metros lineales ya sabemos cuántos

play08:53

metros lineales ocupamos

play08:55

de varillas en el sentido longitudinal

play08:58

pero aquí nos están pidiendo en

play09:01

toneladas la sharía se calcula en

play09:04

toneladas bueno

play09:05

entonces lo que vamos a hacer es muy

play09:08

convertir esos cuatro metros lineales en

play09:11

toneladas perdón y primero en kilos y

play09:13

luego toneladas

play09:15

tenemos que saber cuánto pesa el metro

play09:17

lineal de varillas de media para que

play09:21

estamos analizando no hace falta con

play09:23

varilla de media

play09:25

la variedad de media tiene un peso de

play09:26

punto 995 kilos lo puede sostener un bug

play09:29

el bueno una ficha técnica de la varilla

play09:31

de media pues ahora si multiplicamos los

play09:33

cuatro metros por lo que pesa cada metro

play09:35

ya tenemos un total de 3.98 kilos y para

play09:39

convertir una tonelada solamente lo

play09:40

dividimos entre mil ya tenemos las con

play09:43

heladas que necesitamos pero hay que

play09:46

agregarle un desperdicio y el acero

play09:48

sufre un desperdicio del 3 por ciento

play09:51

los ahora si multiplicamos las toneladas

play09:53

por el desperdicio ya tenemos punto 0 0

play09:55

4 toneladas en el sentido longitudinal

play09:59

ahora vamos a calcular las varias en el

play10:00

sentido

play10:01

transversal

play10:03

en un metro cuantas varillas ocupó

play10:07

cuántas varias entran es igual a como lo

play10:10

hicimos anteriormente uno en 3.20 más

play10:15

el uno de la varilla inicial

play10:18

hoy vamos a hacerlo acá en la trágica

play10:19

naturaleza igual a un metro

play10:24

en

play10:25

3.20 + 1 ya tenemos 6 varillas y de qué

play10:31

largo

play10:32

estamos las variaciones de largo cuánto

play10:34

es son 60 centímetros nos colocamos

play10:37

puntos 60

play10:39

longitud total 4 x puntos 60 3.6 y lo

play10:44

multiplicamos por lo que pesa el metro

play10:46

lineal de varilla y obtenemos 3.6 por

play10:49

135 358 lo convertimos en toneladas

play10:53

dividiéndolo entre 1000

play10:55

y le agregamos un desperdicio

play10:58

multiplicamos las toneladas por el

play11:00

desperdicio ya tenemos un total sumamos

play11:03

los 2 cantidades ya tenemos punto 00 7

play11:06

toneladas de varillas de media que

play11:08

necesitamos colocamos en igual y

play11:10

solamente los capturamos lo

play11:12

multiplicamos por el peso o por el

play11:14

precio de la tonelada del acero ya

play11:18

tenemos un importe ahora el alambre

play11:20

cuántos kilos de alambre necesitamos por

play11:21

cada metro lineal de zapata es muy

play11:24

sencillo tenemos que determinar cuántos

play11:27

amarres vamos a hacer o sea en cada

play11:29

intersección

play11:30

en cada intersección cuántos amarres

play11:32

vamos a hacer en un metro lineal y para

play11:35

eso es un sencillo solamente es

play11:37

multiplicar las varillas en un sentido o

play11:40

sea en un sentido tras sentido longitud

play11:43

de longitud final por las varillas en el

play11:45

sentido transversal 6 por 4 24 más es la

play11:48

longitud del alambre qué tan largo

play11:51

cortas el alambre para hacer ese amarre

play11:53

solo tienes que medir en obra y sacas un

play11:56

promedio

play11:57

nosotros ya lo medimos en obra y

play11:59

aproximadamente andan cortándolo el

play12:01

maestro ferrero en

play12:03

17 centímetros y medio y hacen el amarre

play12:07

doble o sea con dos alambres

play12:09

y hay que multiplicarlo por el peso del

play12:11

alambre cuánto pesa el alambre por cada

play12:13

metro lineal si revisa la ficha técnica

play12:16

tiene un peso de fondo 0 143 kilos y el

play12:19

desperdicio del alambre se considera un

play12:21

50% a muchos se les hace mucho 50 por

play12:24

ciento pero si lo analizas en obras vas

play12:26

a ver que el 50 por ciento muchas veces

play12:29

te va a hacer falta alambre los

play12:30

multiplicamos los amarres por la

play12:32

longitud por las piezas por el peso y

play12:34

por el desperdicio ya tenemos punto 18

play12:37

kilos es la cantidad que vamos a colocar

play12:39

aquí

play12:40

punto 18 kilos bueno pues ya tenemos el

play12:44

total del material

play12:45

ahora vamos sobre la mano de obra para

play12:47

calcular la mano de obra se calcula por

play12:49

especialidades tenemos que colocar la

play12:51

mano de obra del o de la cuadrilla del

play12:54

oficial ferrero y la cuadrilla del

play12:56

albañil el que va a colar

play12:59

y hay que calcularle el rendimiento y el

play13:03

precio unitario de la cuadrilla para

play13:06

calcular primero el precio de wii

play13:07

unitario de la cuadrilla para formar

play13:09

esta cuadrilla para formar esta

play13:11

cuadrilla tenemos la cuadrilla número

play13:12

3.5 el ferrero más un ayudante

play13:16

colocamos el ferrero el ayudante y el

play13:18

cabo de obra el ferrero ocupamos punto 5

play13:21

del ferrero y lo vamos a multiplicar por

play13:23

el salario real el cerebro real es quien

play13:26

significa que ya incluye el factor del

play13:28

salario real ya tenemos un importe el

play13:30

ayudante es uno que son ayudantes que

play13:32

ocupamos por el salario real y ya

play13:35

tenemos un importe y el cabo de ahora

play13:36

punto 10 del cabo por el salario real ya

play13:40

tenemos un importe sumamos y tenemos 935

play13:43

puntos 29 pesos que nos cuesta la

play13:46

cuadrilla por jornal o sea por un día de

play13:49

trabajo se preguntarán por qué punto 5

play13:52

bueno porque para habilitar una tonelada

play13:55

de acero necesitamos un ferrero y dos

play13:58

ayudantes que significa que ahí ya son

play14:00

dos cuadrillas

play14:01

[Música]

play14:03

por cada por cada por cada ayudante

play14:07

ocupamos el el 50% de la capacidad del

play14:12

ferrero o sea para dividimos

play14:15

el cierre lo dividimos en dos para un

play14:18

ayudante

play14:19

ocupamos el 50% y para el otro yo ante

play14:22

el otro 50% entonces qué significa ahí

play14:25

que tenemos puntos 5 el ferrero más un

play14:28

ayudante que ya serían dos cuadrillas no

play14:32

es una cuadrilla con dos ayudas no es un

play14:33

cierre cuando los ayudantes si es punto

play14:36

5 en febrero más un ayudante ok bueno

play14:39

pues entonces éste 935 es lo que vamos a

play14:41

colocar aquí igual igual a 200 35.29 y

play14:46

bueno y cuál es el rendimiento

play14:49

el rendimiento que significa que cuanto

play14:53

en cuanto me rinden por habilitar

play14:57

punto 0 0 77 9 toneladas de hacer

play15:02

para empezar nosotros tenemos que saber

play15:04

cuánto cuántos o cuánto nos rinden para

play15:08

una tonelada de acero o cuál es el

play15:12

rendimiento para una tonelada de acero

play15:14

esto se mide en obra

play15:19

medido en obra sacas un promedio y la

play15:25

tonelada a cero tiene un promedio de

play15:27

5.88 dos jornales

play15:31

por tonelada

play15:34

esto es para una tonelada entonces qué

play15:36

vamos a hacer nosotros para obtener los

play15:39

jornales para habilitar este acero esta

play15:42

cantidad nosotros tenemos que

play15:43

multiplicar los jornales por

play15:48

los formales de naturalidad a por las

play15:50

toneladas que vamos a habilitar

play15:53

y lo multiplicamos por el precio

play15:56

unitario de la cuadrilla y ya tenemos un

play15:58

importe ahora para el colado la

play16:01

cuadrilla de colador es punto 25 oficial

play16:04

más un peón nosotros tenemos que saber

play16:07

primeramente hotel o crear la cuadrilla

play16:10

la cuadrilla número uno tenemos punto 25

play16:12

albañil más un peón

play16:15

el albañil el frío en el cabo punto 25

play16:18

del albañil por el salario real del

play16:21

albañil y tenemos un importe del peón un

play16:23

peón por el salón real de lyon y tenemos

play16:25

un importe y el cabo de obra punto 10

play16:27

por el salario real y tenemos un importe

play16:29

bueno porque punto 25 es igual para

play16:33

fabricar o más bien para colar un metro

play16:36

cúbico de concreto necesitamos

play16:38

cuatro peones y un albañil que significa

play16:41

que ahí son cuatro cuadrillas y el

play16:44

albañil si tú lo divides entre cuatro

play16:46

porque son cuatro peones por qué porque

play16:48

cada vez con cada acción está utilizando

play16:50

el

play16:51

25% su capacidad porque porque es uno

play16:54

entre los cuatro peones tenemos punto 25

play16:57

lo que quiere decir que por cada avión

play16:59

ocupamos el 25% de capacidad del albañil

play17:02

por eso es que colocamos punto 25 por el

play17:05

salario real del albañil y tenemos un

play17:06

importe para el peón

play17:09

un peón

play17:12

fue el celo real y el cabo de obra igual

play17:14

que el cabo y obra tiene la capacidad

play17:16

para supervisar 10 cuadrillas por obra

play17:19

por lo tanto por cada cuadrilla estamos

play17:22

utilizando el 10 por ciento de su

play17:23

capacidad talento es 1 entre 10 en todas

play17:28

por eso es en 3.10 los atendemos 788

play17:31

punto 86 en la cantidad que vamos a

play17:33

colocar aquí es lo que nos cuesta la

play17:35

cuadrilla

play17:36

[Música]

play17:37

por cada jornal bueno y para obtener el

play17:41

rendimiento nosotros tenemos que

play17:42

multiplicar

play17:43

[Música]

play17:46

el rendimiento para un metro cúbico de

play17:48

concreto por los metros cúbicos que va a

play17:52

fabricar

play17:54

y para calcular ese rendimiento

play17:56

nosotros debemos de medir a lograr

play17:57

cuantos

play18:00

cuántos jornales

play18:02

necesitamos para fabricar un metro

play18:05

cúbico de concreto

play18:07

y para

play18:08

fabricar un metro cúbico concreto en

play18:11

medio una obra nosotros ocupamos

play18:13

1.5 jornales

play18:17

bueno pero cuál es el jornal

play18:22

cuál es el jornal por metro cúbico

play18:35

para calcular este jornal nosotros

play18:37

tenemos que primero tenemos que saber

play18:39

cuál es el rendimiento de metros cúbicos

play18:41

por formal o sea cuántos metros cúbicos

play18:43

me rinden en un jornal de trabajo y en

play18:46

un jornal de trabajo me rinden 1.5

play18:48

metros cúbicos

play18:50

bueno pero cuántos jornales me rinden

play18:54

por un metro cúbico y este es el

play18:57

rendimiento por un jornal o sea por un

play18:58

día

play19:00

en tierra fabrican 1.5 metros cúbicos

play19:03

pero cuántos

play19:05

jornales se hace el inverso cuántos

play19:08

formales me rinden

play19:10

para un metro cúbico no nosotros lo que

play19:13

tenemos que hacer es el jornal o sea 1.5

play19:17

también 1 entre 1.5 es un jornal es 1.5

play19:22

ya tenemos el portal por cada metro

play19:24

cúbico o sea ocupamos puntos 6-6

play19:26

formales para un metro purificado

play19:30

colocamos cientos 666

play19:33

bueno y para calcular el rendimiento

play19:36

para fabricar esos códigos solamente

play19:39

vamos a multiplicar

play19:41

el rendimiento por metro cúbico por los

play19:45

metros cúbicos que vamos a fabricar ya

play19:47

tenemos punto cero 81

play19:50

ahora sí ya tenemos el total de mano de

play19:52

obra vámonos a calcular lo que viene

play19:54

siendo el equipo la revolvedora ocupamos

play19:57

una revolvedora para fabricar el

play19:58

congreso en este concreto que estamos

play20:01

haciendo lo que calculamos en básico

play20:05

cuál es el rendimiento de la revolvedora

play20:06

bueno pues el rendimiento revolvedora

play20:08

son los metros cúbicos que va a fabricar

play20:11

cuántos metros cúbicos que van a

play20:13

fabricar la revolvedora

play20:15

1.126 ese es el rendimiento lo mismo con

play20:18

el vibrador

play20:19

cuántos metros cúbicos te va a vibrar

play20:23

se fabricaron y para el equipo de

play20:26

seguridad el equipo de seguridad se

play20:28

concierta una constante bueno más bien

play20:31

es un promedio o es un rango si el

play20:35

equipo de seguridad es del uno al cinco

play20:38

por ciento dependiendo por costumbre

play20:41

utilizamos el 2%

play20:43

pero muchas veces te pueden exigir otro

play20:45

porcentaje un menor o un mayor entonces

play20:48

colocamos punto 02 que es el 2% de quien

play20:51

es un porcentaje en base a la mano de

play20:53

obra lo colocamos sino igual y

play20:55

seleccionamos la mano de obra

play20:57

punto 2 por la mano de obra y tenemos un

play21:00

importe y para la herramienta menor

play21:02

también es un porcentaje hay un promedio

play21:04

iguales entre el entre el 1 y el 5 por

play21:08

ciento y por costumbre tomamos el 3% a

play21:12

excepción de que te pidan otro el 3% en

play21:16

base también a la mano de obra

play21:18

seleccionada la mano de obra y así es

play21:20

multiplicamos el 3% por el total de mano

play21:23

de obra y ya tenemos un impuesto 2 ahora

play21:26

sí ya tenemos material mano de obra y

play21:28

equipo para calcular el costo directo

play21:30

necesitamos

play21:32

sumar el material más

play21:38

la mano de obra más elegimos y ya

play21:42

tenemos un costo directo con un subtotal

play21:45

y para calcular el costo indirecto hay

play21:47

que multiplicar el costo directo por el

play21:49

indirecto que estamos cobrando así vamos

play21:51

a considerar que estamos cobrando un 30%

play21:54

entonces lo multiplicamos por punto 30

play21:56

ya tenemos un costo directo y por el

play21:59

total solamente sumamos el costo directo

play22:01

más el indirecto ya tenemos un total mil

play22:04

30 y 1.48 pesos es lo que vamos a cobrar

play22:08

por cada metro lineal de esa pata

play22:09

corrida de 60 centímetros de ancho

play22:11

espero que te haya gustado este tutorial

play22:13

o este vídeo te esperamos en el próximo

play22:16

vídeo no olvides suscribirte y dejarnos

play22:19

tu comentario hasta luego

play22:25

y

play22:30

[Música]

Rate This

5.0 / 5 (0 votes)

Ähnliche Tags
Construction AnalysisReinforced ConcreteSlab DesignEngineering TutorialArchitectural ReviewMaterial QuantificationCost CalculationConcrete MixingSteel ReinforcementLabor Estimation