Metode Kerja Adhi Beton: Rigid Pavement Jalan Tol Sigli - Banda Aceh

Adhi Persada Beton
19 May 202109:43

Summary

TLDRThe video details the construction process of the Sigli Banda Aceh toll road, spanning 74 kilometers. It begins with land preparation, including clearing and installing dowels, followed by checks on machinery. The concrete laying process is highlighted, featuring an advanced paving machine and quality checks for optimal results. The finishing touches include smoothing and grooving to enhance vehicle grip, alongside curing methods to prevent cracking. The project emphasizes quality control, from initial preparations to final inspections, ensuring the roadway meets specifications. Overall, it showcases a comprehensive approach to infrastructure development.

Takeaways

  • 😀 The Sigli Banda Aceh toll road project spans 74 kilometers from Padang Tiji to Baitussalam.
  • 😀 Land preparation involves land clearing using compressors and setting up dowels for concrete work.
  • 😀 The elevation and alignment of the survey lines are checked to ensure proper height.
  • 😀 A plastic cover is laid over the cleaned area to prevent water from penetrating the concrete.
  • 😀 Equipment checks, including excavators and concrete spreaders, are crucial before beginning work.
  • 😀 The Wirzon S&P 500 concrete spreader has a production capacity of 35 to 40 meters per hour.
  • 😀 Briefings are conducted to align the team on project goals and prevent issues during work.
  • 😀 Concrete is tested during delivery to ensure quality and compliance with standards.
  • 😀 Finishing processes include smoothing, grooving, and curing to ensure product durability.
  • 😀 Joint sealing is performed carefully to maintain quality and prevent water damage.

Q & A

  • What is the length of the Sigli Banda Aceh toll road project?

    -The toll road project spans 74 kilometers from Padang Tiji to Baitussalam in Banda Aceh.

  • What is the first step in the construction process mentioned in the video?

    -The first step is land preparation, which includes clearing the land using a compressor.

  • What is the purpose of installing plastic sheeting during land preparation?

    -Plastic sheeting is used to prevent water from the concrete from seeping into the ground below.

  • What equipment is checked before starting the concrete pouring process?

    -The equipment checked includes excavators and the concrete paver, ensuring they are functioning properly.

  • What capacity does the concrete paver have?

    -The concrete paver has a maximum production capacity of 35 to 40 meters per hour.

  • What is the purpose of the finishing process in concrete work?

    -Finishing ensures the concrete meets quality specifications and includes smoothing, grooving, and curing.

  • Why is grooving applied to the concrete surface?

    -Grooving enhances tire grip on the surface, improving safety for vehicles.

  • What is the depth of the concrete cutting performed after curing?

    -The concrete cutting is performed to a depth of 7.5 to 8 cm.

  • What is checked during the joint installation process?

    -Checks include the depth of the cut and the temperature of the joint material to ensure it meets specifications.

  • How is the quality of the finished product maintained during rain?

    -A cover tent is used to protect the product from rain during production.

Outlines

plate

Esta sección está disponible solo para usuarios con suscripción. Por favor, mejora tu plan para acceder a esta parte.

Mejorar ahora

Mindmap

plate

Esta sección está disponible solo para usuarios con suscripción. Por favor, mejora tu plan para acceder a esta parte.

Mejorar ahora

Keywords

plate

Esta sección está disponible solo para usuarios con suscripción. Por favor, mejora tu plan para acceder a esta parte.

Mejorar ahora

Highlights

plate

Esta sección está disponible solo para usuarios con suscripción. Por favor, mejora tu plan para acceder a esta parte.

Mejorar ahora

Transcripts

plate

Esta sección está disponible solo para usuarios con suscripción. Por favor, mejora tu plan para acceder a esta parte.

Mejorar ahora
Rate This

5.0 / 5 (0 votes)

Etiquetas Relacionadas
ConstructionInfrastructureToll RoadBanda AcehProject ManagementQuality ControlConcrete WorkHeavy MachineryLand PreparationCivil Engineering
¿Necesitas un resumen en inglés?