6th Shaw and Partners Uranium Conference, Sep 2024 – Alligator Energy (AGE)

Shaw and Partners Financial Services
30 Sept 202419:36

Summary

TLDRGreg Halland, CEO of Alligator Energy, provides an update on the company's Sfire uranium project in South Australia, which will use ISR (In-Situ Recovery) mining. He outlines the project's progress, including resource expansion, upcoming field recovery trials, and stakeholder engagement. Halland highlights the potential for scaling up production and mentions a recent uranium discovery at the Big Lake project. Challenges, such as the need for water treatment due to saline conditions, are addressed, with trials set to begin in early 2025. Halland expresses optimism about the project's future and its contribution to uranium production in Australia.

Takeaways

  • 🔧 Alligator Energy is advancing the Samphire Uranium Project in South Australia, which will use in-situ recovery (ISR) mining similar to the Honeymoon project.
  • 📈 The company has expanded its resource footprint with a current resource of just under 20 million pounds of uranium, considered an economically viable starting point.
  • 🛠️ Field recovery trials are set to begin in early 2025 to test chemical recoveries and the project's feasibility.
  • 💰 Alligator Energy has strong financials, with $131 million in capital for the project, and an NPV based on $75 uranium prices with an all-in sustaining cost in the low to mid-30s per pound.
  • 🧑‍🔧 The team is led by Andrea Marrell Smith, COO, who brings extensive ISR experience from Heathgate Resources, and they've recruited a skilled team to ensure effective project execution.
  • 🌍 The project benefits from a favorable location, close to the town of Whyalla, with easy access to power, water, and a regional workforce.
  • 🔬 The company has completed extensive geophysical and hydrogeological work, focusing on shallow and highly permeable sand layers for uranium recovery.
  • 📅 Alligator expects construction of the field recovery trial to run from February to May 2025, with results expected shortly after, feeding into their feasibility study and mining lease application.
  • 🌊 Water salinity is a key challenge, and they plan to reduce groundwater salinity from 40,000 salts to 12,000–15,000 salts for efficient uranium recovery using salt-tolerant resins.
  • 🔍 A recent discovery at their Big Lake Uranium Project showed promising results, with plans for further drilling and expansion in 2025 to assess the uranium potential in the area.

Q & A

  • What is the main project that Alligator Energy is currently developing?

    -Alligator Energy is developing the Sfire Uranium Project located in South Australia, which will be an ISR (In-Situ Recovery) operation.

  • What are the key characteristics of the Sfire Uranium Project compared to other similar projects like Honeymoon?

    -The Sfire Uranium Project shares characteristics with the Honeymoon project, such as being an ISR operation. It involves shallow, compacted sands with high permeability and porosity, which are essential for uranium recovery.

  • What is the status of Alligator Energy's field recovery trial for the Sfire project?

    -Alligator Energy is preparing for intensive field recovery trials for the Sfire project. The pilot plant has been fully fabricated and is waiting for final approvals to begin trials in early 2025.

  • How does Alligator Energy plan to handle the high salinity of groundwater at the Sfire project site?

    -Alligator Energy plans to reduce the salinity of the groundwater from 40,000 salts down to about 12,000 to 15,000 salts, which is sufficient for salt-tolerant resins to work effectively in uranium recovery. This will help optimize the ISR process without needing to treat the water to potable levels.

  • What is the expected timeline for the Sfire project to move from trials to production?

    -The field recovery trials are expected to take place from February to May 2025. After that, Alligator Energy anticipates applying for mining lease approvals by late 2025, with potential construction starting in 2028 and production by 2029.

  • What recent discovery did Alligator Energy make at the Big Lake Uranium Project?

    -Alligator Energy made a recent discovery at the Big Lake Uranium Project, finding up to 20 meters of permeable sands with consistent uranium grades. This discovery confirmed the presence of the right paleochannel systems for further exploration.

  • How does Alligator Energy plan to expand its Black Bush deposit at the Sfire project?

    -Alligator Energy is currently drilling in the southern and eastern areas of the Black Bush deposit and expects to release an updated resource estimate in December 2023 or January 2024. They are also exploring new channels within their tenement for potential resource expansion.

  • What is the significance of Alligator Energy’s location near the town of Woomera?

    -The proximity to Woomera, just 20 km from the Sfire project, is advantageous because it provides access to local labor, existing infrastructure, and a short distance for transporting resources, reducing the need for extensive power and water line installations.

  • What kind of team has Alligator Energy assembled to ensure the success of the Sfire project?

    -Alligator Energy has recruited a team with extensive ISR production experience, including Andrea Morel as Chief Operating Officer, who has over 17 years of experience with Heathgate Resources. They have also hired experts in geology, hydrogeology, environmental management, and chemistry to support the project.

  • How will the field recovery trial contribute to the overall feasibility study for the Sfire project?

    -The field recovery trial will test the chemistry of uranium extraction, helping to refine the ISR process, optimize the use of IX columns, and gather crucial data for the full feasibility study. The results will guide the final design of wellfields and the plant layout for future production.

Outlines

00:00

🎤 Introduction to Greg Halland and Alligator Energy's Sfire Project

Greg Halland, CEO of Alligator Energy, is introduced as he discusses the company's progress with the Sfire project in South Australia. He touches on similarities with Honeymoon, another ISR uranium project, and shares plans for intensive field trials to assess recovery before bringing the project to market. Halland also mentions an operational update and thanks Andrew for the opportunity to present, while apologizing for some delays.

05:01

🌍 Overview of Alligator Energy's Project and Resource Development

Greg elaborates on Alligator Energy’s progress, highlighting the field recovery trial for the Sfire project and their expansion efforts. He outlines the company's liquidity position, shares issuance, and its journey from past acquisitions and expansions. The main Sfire project consists of two deposits—Plum Bush and Black Bush—located in South Australia. Greg emphasizes their regional proximity to essential infrastructure, which aids the development, and provides insights into their resource base, which includes a 20 million pound JORC-compliant uranium resource.

10:03

📊 Scoping Study and ISR Mining Process for Sfire Project

Greg discusses the technical aspects of the ISR (In-Situ Recovery) mining process for the Sfire project. He highlights the shallow depth and high permeability of the sands where uranium deposits lie, the preparation of the pilot plant, and the extensive testing conducted to optimize recovery. The December 2023 scoping study shows favorable economics, with a 1.2 million pound per year production target and a low all-in sustaining cost. He also introduces key team members, including experienced professionals from previous uranium projects like Four Mile and Beverly, bringing invaluable expertise to Alligator Energy’s development plans.

15:04

🛠 Fabrication and Field Recovery Trial Preparation

Greg describes the field recovery trial for the Sfire project, mentioning that it will involve a series of rings to test the chemistry and recovery dynamics. He explains that all necessary equipment, such as tanks, skids, and pumps, is already fabricated and awaiting final approvals. The field recovery trial will be a crucial step in refining the design of the production rings and overall recovery processes, with a focus on testing salinity and the efficiency of uranium extraction. The trial will help shape the full feasibility study and will be conducted through 2025, feeding data into future operational plans.

⏳ Project Timeline and Stakeholder Engagement

Greg outlines the projected timeline for the Sfire project, with the field recovery trial starting in early 2025. The data from this trial will inform the feasibility study and mining lease application, with full production expected by 2028-2029. He also emphasizes the importance of stakeholder engagement, particularly with local communities, and the need for regulatory approvals, which have caused delays. The company is taking a meticulous approach to ensure environmental and cultural considerations are met.

📈 Big Lake Discovery and Future Drilling Plans

Greg shifts focus to Alligator Energy's Big Lake uranium discovery in the Cooper Basin. The first drilling program revealed promising results, with thick panel sands showing consistent uranium grades. The company plans to conduct more intensive drilling using rotary mud drilling techniques to further evaluate the potential. Stakeholder engagement is also a key aspect here, particularly with local Indigenous groups, and additional drilling is expected to commence in 2025 after more clearances are secured.

🚧 Next Steps and Regulatory Challenges for Sfire Project

Greg details the upcoming steps for the Sfire project, including the construction of the field recovery trial, which will test wellfield design and chemical parameters for uranium recovery. He acknowledges challenges related to obtaining regulatory approvals, particularly around the environmental impact of high-salinity groundwater, but remains optimistic about securing these soon. The team plans to carry out full feasibility and wellfield design work after the trial, with final approvals anticipated by 2028.

👥 Final Remarks and Q&A on Salinity Challenges

In the final segment, Greg responds to a technical question about managing saline groundwater for uranium recovery. He explains that while the high-salinity water leaches uranium effectively, treatment is needed to ensure that salt doesn't interfere with the extraction process. The ongoing field recovery trials are expected to refine these processes, with results available a few weeks into the trials in 2025. Greg closes by thanking Andrew and the audience, signaling excitement for the upcoming project developments.

Mindmap

Keywords

💡Alligator Energy

Alligator Energy is a company involved in uranium mining and exploration. The video focuses on its efforts to develop uranium projects, specifically in South Australia, such as the Samphire Uranium Project. It plays a central role in the discussion, representing a company in the pre-production phase with significant exploration and field trials planned.

💡Samphire Uranium Project

The Samphire Uranium Project is a key project being developed by Alligator Energy in South Australia. It aims to produce uranium using in-situ recovery (ISR) methods, similar to other projects like Honeymoon and Beverly. The project is significant for its potential contribution to the uranium supply, and its location near the Woomera area offers infrastructure advantages.

💡In-Situ Recovery (ISR)

In-Situ Recovery (ISR) is a method of uranium extraction that involves circulating a solution through an ore deposit to dissolve uranium and then pumping it to the surface for recovery. The video mentions ISR as the planned extraction method for the Samphire project, highlighting its advantages, such as lower capital expenditure compared to traditional mining. It is emphasized for being suitable for the permeability and porosity of the Samphire deposit.

💡Field Recovery Trial

A field recovery trial is a pilot phase to test the efficiency and feasibility of uranium extraction using ISR techniques. Alligator Energy plans to conduct field recovery trials at the Samphire project to determine chemical recovery rates and optimize operational parameters. This trial phase is crucial for assessing the viability of ISR in this region and is planned for early 2025.

💡Uranium Resource Expansion

Uranium resource expansion refers to efforts to increase the estimated reserves of uranium at the Samphire project. The video describes how Alligator Energy is expanding exploration at the Black Bush and Plumbush deposits, which are part of the Samphire Project, to increase their inferred and indicated uranium resources. The expansion is essential for achieving a larger production scale and improving project economics.

💡Stakeholder Engagement

Stakeholder engagement involves actively communicating with local communities, government authorities, and investors to gain support for the project. Alligator Energy emphasizes its ongoing efforts to engage with stakeholders, particularly as the project moves towards feasibility studies and mining lease approvals. This engagement is crucial to ensure regulatory compliance and to maintain good relationships with the local workforce and indigenous communities.

💡Indigenous Clearances

Indigenous clearances are permissions required from local indigenous groups before any drilling or mining activity can begin on their lands. Alligator Energy has secured clearances for geophysical surveys and is negotiating for additional permissions to conduct drilling at the Plumbush site. Respecting cultural heritage and gaining these clearances is a critical part of the project's progression.

💡Pilot Plant

A pilot plant is a smaller, pre-production version of the processing plant designed to test the uranium extraction process on a smaller scale. Alligator Energy has already fabricated the pilot plant for the Samphire project, which will be used in the upcoming field recovery trial. The pilot plant aims to assess the chemistry involved in the uranium recovery process and test different system components, such as IX (ion exchange) columns.

💡Scoping Study

A scoping study is a preliminary evaluation of the technical and economic viability of a mining project. Alligator Energy's scoping study for the Samphire Uranium Project provides estimates for production rates, capital expenditures, and project profitability at different uranium price points. The study shows that the project has economic potential with a capital expenditure of $131 million and production costs in the low $30s per pound, which is competitive for ISR projects.

💡Hydrogeology

Hydrogeology is the study of the distribution and movement of groundwater in the soil and rocks of the Earth's crust, often relevant to ISR operations. In the video, hydrogeology is a critical aspect of the Samphire project, particularly because the ISR process involves injecting and extracting solutions in a controlled manner. Alligator Energy has conducted extensive hydrogeological testing to ensure proper management of groundwater and minimize environmental impacts.

Highlights

Alligator Energy is advancing the Samphire Uranium Project in South Australia, with two key deposits, Black Bush and Plumbush.

The company is planning intensive field trials in 2025 to test uranium recovery and chemistry flow using in-situ recovery (ISR) mining.

Alligator Energy has a JORC-compliant uranium resource of 20 million pounds, considered an economic starting point with potential for expansion.

The Samphire Project benefits from proximity to infrastructure, with only a 25-km distance to power and water lines, and a regional workforce nearby.

Alligator Energy's pilot plant for the field trial has been fully fabricated and is ready to be deployed once the final approvals are secured.

Scoping study results from December 2023 suggest a production rate of 1.2 million pounds per annum, with a capital cost of AUD 131 million and favorable NPV at uranium prices of USD 75/lb.

The company is planning to expand the Black Bush resource with new drilling in historical areas where promising uranium intersections have been found.

Alligator Energy anticipates a two-year period for regulatory approvals, meaning mining lease approvals are likely by 2026, with production starting around 2029.

The company is focused on stakeholder engagement, particularly with local and indigenous communities, ensuring transparent and collaborative project development.

The field recovery trial, set to begin in early 2025, will involve testing the chemistry of ISR rings over four to six weeks to determine efficiency and recovery rates.

Greg Halland, CEO of Alligator Energy, emphasized the importance of managing groundwater salinity in the Samphire project, similar to challenges faced by other ISR operations in the region.

The pilot plant will test uranium leaching in high-salinity water, reducing salinity from 40,000 to 12-15,000 ppm to optimize resin efficiency.

The field trials will inform the full feasibility study and future mining design, feeding into the broader commercial plans for the Samphire project.

Alligator Energy has expanded its project footprint, covering a larger area of paleo-channels, with significant potential for further uranium discoveries.

The company has also made a new uranium discovery at its Big Lake project in northern South Australia, with promising results from initial drilling.

Transcripts

play00:00

bring Greg Halland from alligator energy

play00:02

um Greg um is the CEO managing director

play00:06

uh alligator energy is not yet in

play00:08

production they are um developing a

play00:10

project in South Australia called the

play00:11

sfire project um and you just heard from

play00:13

from Duncan all around Honeymoon and

play00:15

boss um sire has some of the same sort

play00:17

of characteristics as as honeymoon it's

play00:19

going to be an ISR operation and uh

play00:22

Greg's going to be doing some uh pretty

play00:24

intensive field Trials of the recoveries

play00:27

before bringing this project to Market

play00:28

but Greg over to you if you wouldn't

play00:30

mind sharing your screen if you got some

play00:31

slides and um look forward to hearing

play00:34

the update on

play00:35

aligator thank you very much Andrew and

play00:37

I apologize to sha and partners for my

play00:39

delay inadvertently as it was but uh

play00:43

thank you for rearranging and also

play00:45

apologize to your listeners who are

play00:47

online um look thank you for the

play00:49

opportunity to talk uh I'm assuming you

play00:51

can share the uh I see the screen okay

play00:54

that should be good um alligator energy

play00:57

is advancing at sfire Iran project uh in

play00:59

to a uh a field recovery trial I'll talk

play01:02

about that we are doing expansion to the

play01:05

resource I'll talk a bit about that

play01:06

we've got a very good put footprint for

play01:08

a potential future resource we've got

play01:10

good scoping economics and we're well

play01:13

cached up uh along with that we have

play01:15

made a recent discovery at a big lake

play01:17

Iranian project in the north of South

play01:19

Australia which I'll mention briefly

play01:21

through this

play01:22

presentation um in terms of where we are

play01:25

we have a lot of liquidity a lot of

play01:27

shares on issue because one of the

play01:28

players that have come through the the

play01:30

doldrum days from the late

play01:32

2010s through to where we are now but we

play01:34

have been on a good path in terms of

play01:37

acquisition of projects expansion of

play01:39

projects but also some uh some

play01:41

expiration success and uh we uh we're

play01:44

progressing that well I'll talk about

play01:47

the team a little bit as we get into the

play01:48

project uh going forward our main

play01:51

project The Sire running project

play01:54

comprises two deposits one deposit one

play01:56

Prospect we'll call it because it's not

play01:58

currently Jo compliant

play02:00

plum bush and and Black Bush that's in

play02:02

the the Wala area of South Australia you

play02:05

can see the location of H gou Dam that

play02:08

that um Duncan was just talking about

play02:10

the Beverly 4 Mile complex up here and

play02:12

our big lake project in the coopa Basin

play02:14

to the north and uh a closer view of the

play02:18

Wala Town 20 km South our main black bsh

play02:21

deposit uh we have an a paral full of

play02:24

partial agreement over the black push

play02:26

deposit through the production uh we're

play02:28

negotiating to get onto the ground for

play02:30

plum bush drilling we have already been

play02:31

on there for geophysics with the paral

play02:33

so we're continuing that discussions a

play02:35

full ntma for indigenous clearances and

play02:38

cultural heritage clearances we've done

play02:40

three of them for our drilling so far

play02:41

through this

play02:43

area the beauty of the

play02:46

project is it's 20 km from a regional

play02:49

center which is a Workforce Source but

play02:51

along with that we don't have to build

play02:52

extensive power lines and water lines 25

play02:56

km power line water line we have a local

play02:58

Workforce we've already got local

play03:00

employees we have a regional um basis

play03:03

there a yard and an office in the town

play03:06

of w that we can work from with a 20

play03:08

minute to 30 minute drive out to the

play03:10

site we have just under 20 million pound

play03:13

draw compliant resource which you would

play03:15

have seen from many of the presentations

play03:17

is an economic starting project many

play03:20

projects such as Beverly uh such as the

play03:22

original boss project they all started

play03:24

with around this level of resource and

play03:26

expanded it from there the beauty of a

play03:28

low capital process like ISR is you can

play03:31

start with an economic project and

play03:33

expand it as you work and as you get in

play03:36

production we have really done a lot of

play03:38

work on making sure we've got an

play03:40

expandable exploration Target going

play03:42

forward and I'll talk briefly about that

play03:44

and show that the scoping study in

play03:46

December 23 is uh has got 30 to 35% uh

play03:50

contingency in it even though it's only

play03:52

131 million capital and that's a real

play03:55

example of the jurisdiction location

play03:57

adjacent to Wala um good payback going

play04:01

with that our pilot plant is fully

play04:03

fabricated and already in our yard up at

play04:05

wer awaiting the final approvals to get

play04:08

onto the site and construct and I'll

play04:10

talk about that we're doing a massive

play04:12

amount of work in uh in stakeholder

play04:14

engagement we've been doing it so far

play04:15

we're now putting a bit more horsepower

play04:17

into this team as we move from through a

play04:20

a field recovery trial into feasibility

play04:23

and then into mining lease approvals

play04:24

late next

play04:27

year most people are familiar with the

play04:29

ISR mining process and the the the

play04:33

system we have is a layer of compacted

play04:36

Sands only 80 M deep so it's quite

play04:38

shallow uh they're very permeable

play04:40

they're very porous we've taken a big

play04:43

series of 14 to 15 cores out of this

play04:45

ground done all the V scale testing we

play04:47

required to really get the first initial

play04:49

parameters for the project and that

play04:51

helped us do the scoping study and that

play04:53

helped us design the the fuel recovery

play04:55

trial plant with three rings planned to

play04:58

operate to really up not just the the

play05:00

pregnant liquor solution qualities that

play05:03

are going to come out test the the Aro

play05:05

plant um lowering the salinity of the

play05:08

water not to pable level but just to a

play05:09

solinity where the ex columns work well

play05:12

bringing that up and through the ex

play05:14

plant and into a clean uit solution so

play05:16

that's the test work we're going to be

play05:20

doing the scoping study that we uh

play05:23

updated in December 23 with an increased

play05:26

production rate of 1.2 million pounds

play05:28

perom uh3 million capex as I mentioned a

play05:31

good npv at $75 uranium price and all in

play05:35

sustaining in the in the low to

play05:37

mid-30s and so we think this is a

play05:39

realistic level one thing I will mention

play05:42

here is the team that we have on board

play05:44

with Andrea marel and Smith is our chief

play05:46

operating officer who's been well

play05:49

probably a total of 17 years with

play05:50

heathgate resources that run the Four

play05:52

Mile and Beverly complex as she was

play05:54

instrumental in discovering forar bring

play05:56

it through into wellfield production and

play05:59

so she has now recruited a full ISR

play06:01

production experience team under her

play06:03

with a principal geologist senior Hydro

play06:05

geologist who are the the mining

play06:06

Engineers of this method of mining as

play06:08

you would have heard before and we have

play06:11

a project manager for the field trial we

play06:13

have an environmental manager recruiting

play06:15

a full full-time engagement manager now

play06:19

and a principal chemist who's operated

play06:20

also through the plant system at um he

play06:23

at

play06:24

Beverly so we have a realistic approach

play06:28

to what we believe the costs and timing

play06:31

will be here we know it's not quick and

play06:33

I agree with Duncan new production will

play06:35

come on but it will be slower than

play06:37

anticipated we have been slower than

play06:39

anticipated

play06:40

already so we've got a good level of

play06:43

scoping study we've got an expanded

play06:45

footprint which I'll talk about and

play06:48

we're we're also now looking to expand

play06:50

our Black Bush deposit so this is the uh

play06:52

Black Bush resources that stands the the

play06:54

blue is inferred the red or pink is

play06:57

indicated we have lift this already once

play07:01

we're now exploring some of these

play07:03

historical intersections out to the east

play07:06

these were all drilled by uranium SAS up

play07:08

to about

play07:09

2010 all of them are above cutoff grade

play07:12

so we're really looking at where the rle

play07:13

fronts move into these and we've already

play07:15

found some extensions to these not all

play07:17

of these will become R fronts as most

play07:19

people know you can have areas of

play07:20

uranium which don't link together in

play07:23

production level but certainly there's

play07:25

plenty of smoke out there we have

play07:27

extended to the West we put some

play07:29

information out from our drilling

play07:31

earlier this year and we're now drilling

play07:33

down to the South here so we'll have an

play07:35

updated resource out in December January

play07:37

on the Black Bush

play07:39

deposit we expanded our footprint this

play07:42

is the paleo channels at 80 to 90 M

play07:46

depth that lie underneath our tenaments

play07:49

this is the Black Bull deposit it's

play07:51

really about 7 to 8% of the known

play07:53

channels when we did our expiration

play07:56

target range over here 14 to 75 million

play07:58

pound target range on top of what we

play08:01

have at Black Bush we only allowed for

play08:04

those channels in this top part which

play08:06

have mineralization in them which is

play08:08

really only about 35 to 40% none of the

play08:11

other channels had any drilling so we

play08:13

really have been conservative in that

play08:15

estimate we know that plum bush will

play08:17

come into resource category we've seen

play08:19

the continuity we need to close up the

play08:21

spacing this was interesting there were

play08:23

high grade and reasonable grade hits of

play08:25

uranium to the south in this tenement

play08:27

that we acquired off Stellar resources

play08:29

and as we did the ground gravity and

play08:31

picked up the channels lo and behold

play08:33

they're pretty well all sitting in the

play08:35

channels which is expected so we really

play08:37

have due to the contrasting nature of

play08:39

our sediment sitting on top of the

play08:41

granites the sourcer uranium we have

play08:43

enough contrast to do Paleo Channel

play08:45

mapping using ground gravity and with a

play08:47

drilling work intensely around black

play08:49

Force we've matched that up to where the

play08:51

channels actually are got a good scoping

play08:53

study and expandable resource The Next

play08:55

Step was to spend the cash that we've

play08:57

raised on a field recovery TR trial so

play09:00

the plants fabricated I'll talk about

play09:02

that in a moment the field recovery

play09:03

trial is intended to be a series of

play09:05

rings three of them operating for a

play09:08

period of four to 6 weeks each they are

play09:10

smaller than plann production Rings

play09:12

because we're not trying to test the

play09:13

permeability porosity we know that well

play09:16

we're trying to test the chemistry so we

play09:18

want to see with 10 m radius Rings how

play09:21

the chemistry flows up how the the preg

play09:23

solution picks up and how it curves down

play09:25

because that tells you how many um

play09:28

future rings are going to need in

play09:29

wellfields for production for required

play09:32

production going forward we operate

play09:34

through the plant to one ring we use the

play09:36

Aro plant to to lower the salinity in

play09:39

the field then circulate within that

play09:42

bring the pregnant solution back into

play09:44

the IX columns and load them uh unload

play09:47

them into clean Ood and into tanks and

play09:50

then we run a second one then we run a

play09:52

third one and they're in spread about a

play09:54

kilometer around the main Black Bush

play09:56

resource which is through here

play09:59

the the um fabrication of the pilot

play10:02

plant was in fact we slowed it down a

play10:04

little in the early part of the year

play10:06

because the approvals processed to get

play10:07

the retention lease approved took longer

play10:10

and we have that fully fabricated we

play10:11

have the wellhouse we have the pumps

play10:13

tanks skids everything we need all

play10:14

Container eyes and up on site in our

play10:16

yard in Wala that sits there the layout

play10:19

is simple but we have to operate it like

play10:22

a small uranium L uh it has to have a

play10:24

clean dirty side uh we have to operate

play10:26

this such that we're testing uh putting

play10:29

procedures in place that the

play10:31

Department's comfortable with and that

play10:33

we're running a a process right through

play10:35

from uranium coming up in the preg

play10:37

solution into the ex ex columns coming

play10:40

through the exx columns and into the El

play10:42

tanks here we don't need to take this

play10:45

volume right through in calide uranium

play10:48

uh that sort of portion of the plant is

play10:51

generally more standardized you have to

play10:53

tailor it a little bit but it's

play10:54

generally more standardized uh we can

play10:56

take Drums of this liquid to ansto and

play10:58

create the 1 kgam samples multiple

play11:01

samples we'll need for converter

play11:02

accounts for them to test the product

play11:04

and make sure it's viable to go through

play11:06

their

play11:06

converters and we have to have this at a

play11:09

pretty shm looking plant this will be

play11:12

visible we will be bringing visitors out

play11:13

every week we'll bring investors here

play11:15

we'll bring potential future customers a

play11:17

lot of people from OA while there's been

play11:19

a lot of visitors to our side already

play11:21

from the OA Council and surrounding area

play11:22

we'll bring a lot more out during the

play11:24

running of this so timeline for this um

play11:28

and we have had since we put in the the

play11:31

full response document in March we've

play11:33

had three uh requests for information

play11:36

from the Department requesting

play11:38

additional information to do with the

play11:39

operation of the plant uh in particular

play11:42

the hydrogeology and uh and this is a

play11:44

new area there hasn't been this style of

play11:46

mining in this area it's a it's a hypine

play11:49

groundwater at 40,000 salts how we work

play11:52

that and how we handled it and make sure

play11:54

that we don't add to the to the

play11:56

groundwater and distract from the

play11:58

groundwater how it naturally attenuates

play12:00

is a very important point that they've

play12:02

been focusing on now that's been well

play12:04

proven in uh in existing minds but we

play12:07

have to model that and then show how

play12:08

we're going to prove that model and then

play12:10

show we're going to show how we're going

play12:12

to track the monitoring in the years

play12:14

after that to show that we're matching

play12:16

the attenuation model so groundwater

play12:18

returns to its original state so that's

play12:21

been the key request for information the

play12:23

last lot of those was in June we

play12:25

provided that information July August

play12:27

had some meetings now they have

play12:28

everything they need we understand but

play12:31

um I will suggest that we would

play12:34

anticipate the approval in the coming

play12:36

month or so uh such that we can be

play12:39

getting the operating plan approved and

play12:40

be on the ground but it has slipped

play12:42

substantially from when we were hoping

play12:44

to have this underway to be now in the

play12:46

first part of 2025 we'll be constructing

play12:49

operating the uh field recovery trial

play12:51

through from around February to

play12:55

May so the steps Beyond this we really

play12:58

need to get this underway this feeds in

play13:01

all the operating parameters uh into the

play13:04

feasibility study that we need to

play13:06

undertake we'll be going out for

play13:07

expressions of interest for groups to

play13:09

run that feasibility study while we have

play13:11

a good level of horsepower in our team

play13:14

uh that will give the right oversight

play13:16

going forward but we do need uh some

play13:18

horsepower on groups that are familiar

play13:20

with liquid tank pump type plants and to

play13:23

use them to help do the feasibility

play13:25

study we need the full field design um

play13:28

world field design and the plant design

play13:31

to to go into the mining lease

play13:32

application which is logically going to

play13:34

be the second half of next

play13:36

year it will be two years to get this m

play13:40

approved at least through a mining lease

play13:42

application and that's because South

play13:44

Australia while it's approved five

play13:46

Uranian mines all of which are operating

play13:48

they still will take that 2-year period

play13:50

to make sure this is approved in the

play13:52

appropriate Manner and has all the right

play13:54

public uh opportunity to review so we

play13:58

are not anticip ating to be constructing

play14:00

on the ground before 2028 and then

play14:02

commissioning production through 29 is

play14:04

the likely outcome now we haven't been

play14:07

definitive and put that into a timeline

play14:09

in these presentations very often

play14:11

because these things do take longer as

play14:13

Duncan well

play14:15

said a quick snapshot of our big lake

play14:18

Discovery this is the area where we are

play14:21

up on the Cooper Basin the same

play14:23

settlements that host the the honeymoon

play14:27

Beverly Four Mile projects extend right

play14:29

over the C Basin the nber formation the

play14:31

air formation followed underneath by

play14:33

Cretaceous Winton and we have those in

play14:37

this area we picked up these tenaments

play14:39

quite early on with this one we acquired

play14:41

from two geologist who put this scenario

play14:43

together and in our first drilling that

play14:46

we undertook this year it took a couple

play14:48

years to get the agreement for the with

play14:49

indigenous people uh that the

play14:54

yander araka people had not done uranium

play14:58

agreement before so we wanted to make

play14:59

sure that they were very familiar what

play15:00

we're doing it was delayed a bit by Co

play15:02

then getting their people together to go

play15:03

through it but nonetheless we have that

play15:04

in place we've done the clearances we

play15:06

need we did this first Drilling and we

play15:08

discovered 20 M of

play15:12

um of panel Sands thicknesses up to 20 M

play15:16

of P Tel Sands with consistent grades

play15:18

through them and if you look at a grade

play15:20

tonnage thickness here it it is getting

play15:23

towards a level of cut off of sandfire

play15:25

in our first drilling program which is

play15:26

quite impressive now they are like

play15:28

grades at

play15:29

but we can drill plenty of places at

play15:31

sandfire and hit low grades so this

play15:33

means we're in the right chemistry we're

play15:36

in the right pale Channel systems which

play15:38

we tried to depict from from uh public

play15:40

seismic data and and now we're going to

play15:43

be drilling to depict them more so our

play15:44

next steps here are to do some rotary

play15:46

mud drilling rather than air core

play15:48

drilling get the right probes pfn tools

play15:51

and things down them in a second

play15:52

drilling program as well as expand this

play15:54

footprint around this area to the south

play15:57

in particular and and it's helped us

play16:00

determine there might be two or three

play16:01

other depicted areas which we want to

play16:04

drill as well so we'll do a combination

play16:06

of rotary mud and aircore drilling to do

play16:08

take this project forward we're doing an

play16:09

additional clearance with did the YY

play16:11

people in late October early November

play16:13

and be drilling in March next

play16:17

year we do a massive amount of

play16:19

stakeholder engagement work we are

play16:21

expanding our work in this area I I want

play16:23

cannot emphasize this enough for new

play16:25

mining operations in particular that are

play16:27

starting up while there's a familiarity

play16:29

with resources industry in the Wala Port

play16:31

Augusta region there's a lot of

play16:33

generations there that have not much to

play16:36

do with resources so we still do a lot

play16:38

of work with uh with that engagement and

play16:40

we'll go wider with the mining lease

play16:42

approval so I think uh Andrew I'm happy

play16:45

to leave that there and have any

play16:46

comments or questions from you yeah

play16:48

terrific thank you Greg that's that's a

play16:50

really good overview I gu maybe a

play16:52

technical question Around The Sire BOS

play16:54

you did mention that um it's got quite

play16:57

saline groundwater conditions and we

play16:59

heard from Duncan with the honeymoon

play17:00

project that that that was an issue

play17:02

historically with that that mine and um

play17:04

you know part of what they had to do was

play17:06

put in a new water treatment plan to get

play17:09

essentially potable water is that is

play17:11

that an issue that you are contemplating

play17:13

sandfire and you know do you have to

play17:15

treat the water extensively for this to

play17:17

be through recoveries to work yeah we

play17:19

need to do the same thing so essentially

play17:21

uh we'll take our water from 40,000

play17:23

salts down about 12 to 15,000 salts so

play17:26

not pable and and you need to get it to

play17:29

a level where the the um salt tolerant

play17:32

resins work effectively and so you've

play17:34

got an efficiency through thex columns

play17:37

the the uranium itself leeches even from

play17:40

that hypersaline water with the right

play17:42

luxian and we've tested that well ano's

play17:44

tested that now behalf with the cause

play17:46

and we know that we'll get the uh The

play17:48

leeching Happening even in the high

play17:50

Salon water but it's really to make sure

play17:51

you don't have salt loading up the

play17:53

resins in preference to uranium U and

play17:56

the the key thing about that balance of

play17:58

how much do you lowerer the cinity

play17:59

versus how many EX columns do you need

play18:01

it's a capital versus operating cost

play18:03

question so we've done enough test work

play18:05

at a bench scale to say this is what we

play18:07

think three ex Columns of this size for

play18:09

this pilot trial and that will tell us

play18:12

then okay now we're going to need two

play18:13

more ex columns or we're going to need

play18:15

to lower the cylind a little more um but

play18:18

between 12 to th 12 to ,000 salts to

play18:21

kick off with and and uh make sure that

play18:24

that that field or the Rings you're

play18:26

operating at that cinity level prior to

play18:28

St ing the the circulation of the fluids

play18:31

so so that is part of the test work yes

play18:34

yeah great and I guess that's what the

play18:35

field recovery trials are going to um

play18:37

yep help you understand and uh so that

play18:40

so I think you told us that they're

play18:42

kicking off now in February next year

play18:43

they'll run till May um when do you

play18:46

think we'll first sort of get the

play18:47

results from those trials well the

play18:50

everything in an ISR plant is either in

play18:52

inline analysis or we have a

play18:54

containerized laboratory on site so once

play18:56

we get the first running of this uh the

play18:58

ring the first ring running and we get

play19:00

the the the AR plant um preconditioning

play19:03

the ground get the fluids going get that

play19:05

ring running there we know within a

play19:07

month six weeks after that our initial

play19:10

results okay great well we look forward

play19:12

toh to those results Greg I guess we're

play19:14

all you know exciting new potential

play19:17

project in the Australian context and um

play19:19

you know those field recovery trials

play19:21

will be something I'm sure the investor

play19:22

base will be watching extremely closely

play19:24

so thank you so much for giving us the

play19:25

update today and uh look forward to

play19:27

following your progress thank you very

play19:29

much Andrew and thanks to everyone bye

play19:31

great

Rate This

5.0 / 5 (0 votes)

Etiquetas Relacionadas
Alligator EnergyGreg HallandSouth AustraliaUranium RecoveryISR MiningField TrialsResource ExpansionMining UpdateSustainabilityEnergy Projects
¿Necesitas un resumen en inglés?