Project Management Resource Scheduling session 6

Fun Online Teaching and Learning
11 Jul 202238:35

Summary

TLDRThis session delves into resource leveling and schedule compression in project management. It explains the concept of resource leveling to balance resource allocation and prevent inefficiencies, introducing schedule compression techniques like fast tracking and crashing. The instructor guides through a hands-on activity, assigns homework for practical application, and emphasizes the importance of understanding risks and probability in project completion. The session prepares participants for a deeper dive into project risk management in subsequent lectures.

Takeaways

  • 📈 Resource leveling is a technique used to balance resource allocation throughout a project to avoid peaks and valleys in usage, aiming to use resources more effectively without changing the project end date.
  • 📊 Schedule compression includes two methods: fast tracking, which involves doing activities in parallel, and crashing, which is about reducing activity durations by applying more resources or changing the approach.
  • 🔍 The critical path in a project is the sequence of activities with zero slack time that determines the project's overall duration, and managing it is crucial for resource leveling and schedule compression.
  • 📚 Understanding the probability of completing a project within a certain timeframe is important for project managers, often requiring statistical knowledge to calculate variance, standard deviation, and confidence levels.
  • 🛠 Tools like Excel can be used for resource leveling to help visualize and manage resource allocation over time.
  • 🔑 Resource leveling can free up space for resources such as employees, machinery, or meeting rooms, allowing for more efficient use of available assets.
  • 🚧 Risk management is an integral part of project management, and resource leveling and schedule compression can introduce new risks that need to be identified, prioritized, and mitigated.
  • 💡 The concept of crashing a project involves increasing costs to reduce the project duration, but it must be analyzed carefully to ensure that the time saved justifies the additional expense.
  • 📉 Crashing a project can lead to various risks, including decreased quality, increased errors, fatigue among workers, and potential safety issues.
  • 📈 A crash cost graph is a useful tool for visualizing the relationship between the cost of crashing activities and the time saved, helping to make informed decisions about which activities to crash first.
  • 🔑 The session also covered a hands-on activity and homework assignment to apply the concepts of resource leveling and schedule compression, reinforcing learning through practical application.

Q & A

  • What are the main topics covered in session six of the project management sessions?

    -Session six focuses on resource leveling and schedule compression, including an introduction to resource leveling, different types of schedule compression such as fast tracking and crashing, a hands-on activity, and a homework assignment to apply the learned skills.

  • What is resource leveling and why might it be necessary?

    -Resource leveling is the process of smoothing out the allocation of resources over time to eliminate peaks and valleys in resource usage, ensuring effective utilization without changing the project end date. It's necessary to manage resources efficiently and address issues like over-allocation or under-allocation of resources.

  • What is the critical path in a project network diagram?

    -The critical path is the sequence of activities in a project network diagram that determines the longest possible duration of the project. It's called 'critical' because any delay in these activities will directly impact the project's overall completion time.

  • How can resource leveling be implemented using simple tools?

    -Resource leveling can be implemented using simple tools like an Excel spreadsheet, which can help in visualizing and adjusting the allocation of resources over time to achieve a more balanced resource usage.

  • What is the purpose of schedule compression in project management?

    -Schedule compression is used to shorten the project duration without reducing the project scope. It involves techniques like fast tracking and crashing to identify ways to perform activities in parallel or to reduce the duration of critical activities.

  • What are the potential risks associated with schedule compression?

    -Risks associated with schedule compression include increased fatigue and reduced motivation among team members, potential for errors and quality issues, additional costs, and the possibility of needing to find additional resources, which can further impact the project timeline and budget.

  • What is the difference between fast tracking and crashing in schedule compression?

    -Fast tracking involves performing activities in parallel that were originally planned sequentially, while crashing involves reducing the duration of critical activities by applying additional resources or changing the approach, which usually incurs additional costs.

  • How can the critical path method (CPM) help in determining the project duration and identifying risks?

    -The critical path method helps in determining the project duration by calculating the longest path of activities through the network diagram. It identifies risks by highlighting activities that, if delayed, would impact the project's overall timeline, allowing for better risk management and mitigation strategies.

Outlines

00:00

📚 Introduction to Resource Leveling and Schedule Compression

This paragraph introduces the session's focus on resource leveling and schedule compression techniques within project management. The session aims to explain what resource leveling is, its purpose, and how it can be executed using simple tools like Excel. It also covers the concept of schedule compression, which includes fast tracking and crashing, and sets the stage for a hands-on activity and homework assignment. The importance of understanding resource usage, critical path analysis, and the potential questions from stakeholders regarding project completion probabilities are highlighted.

05:02

🛠️ Understanding Resource Leveling and Its Application

The speaker delves into the specifics of resource leveling, emphasizing its goal to smooth out resource requirements without extending the project's end date. Using a sprinkler system installation as an example, the paragraph illustrates the process of creating a work breakdown structure and transforming it into a PERT network diagram. It discusses the identification of critical path, slack time, and the potential issues that may arise from uneven resource allocation, such as the need for more personnel than available on certain days.

10:02

🔍 Analyzing Resource Allocation and Identifying Bottlenecks

This section uses an Excel spreadsheet to demonstrate the allocation of resources to various activities in a project. It explains the concept of slack time and how it can be used flexibly to adjust the schedule. The paragraph identifies a specific issue where more tasks are scheduled on the same day than can be handled by the available workforce, indicating a need for resource leveling to resolve such bottlenecks.

15:07

🚀 Exploring Schedule Compression Techniques

The paragraph introduces schedule compression as a strategy to expedite project completion, discussing methods such as eliminating unnecessary activities, substituting less time-consuming components, parallelizing activities, and revisiting duration estimations. It also touches on the potential to increase work hours and the concept of crashing the project, while cautioning about the associated risks and costs.

20:08

⚠️ Risks and Considerations in Schedule Compression

Here, the speaker outlines the potential risks associated with schedule compression, such as fatigue, decreased quality, and motivation issues among team members. It also discusses the financial implications of finding additional resources and the potential for a vicious cycle of problems that can arise from not monitoring the project closely enough. The importance of understanding the crash versus cost relationship is emphasized, as is the need to make informed decisions about which activities to crash first.

25:12

📉 Crash Cost Analysis and Decision Making

The paragraph provides a detailed example of crash cost analysis, explaining how to calculate the cost associated with crashing activities on the critical path. It illustrates the decision-making process with a step-by-step guide on how to determine the order of crashing activities based on cost-effectiveness and the potential time saved. The example includes a crash cost graph as a visual aid for making these decisions.

30:15

📝 Assignment on Crash Cost Graph and Risk Management

In the concluding paragraph, the speaker assigns the task of plotting a crash cost graph as homework, encouraging students to apply the concepts learned. The session's focus shifts to the importance of risk management in project management, with a preview of upcoming topics that will cover defining risk, managing it, and developing response strategies. The speaker emphasizes the inevitability of risk in projects and the importance of early identification and prioritization.

Mindmap

Keywords

💡Resource Leveling

Resource leveling is a project management technique aimed at smoothing out the allocation of resources over time to avoid peaks and valleys in usage. It is essential for effective resource utilization and can be done using tools like an Excel spreadsheet. In the context of the video, resource leveling is introduced as a method to balance resource requirements without extending the project's end date, ensuring efficient use of resources such as manpower, machinery, or even meeting rooms.

💡Schedule Compression

Schedule compression is a method used to shorten the project duration without changing the project scope. It includes techniques like fast tracking and crashing. Fast tracking involves performing activities in parallel that were originally planned sequentially, while crashing adds resources to critical activities to reduce their duration. The script discusses schedule compression as an alternative when resource leveling is not sufficient to meet time constraints, emphasizing the different types and their implications on the project timeline.

💡Critical Path

The critical path in project management is the sequence of activities that determines the longest possible duration of a project. Activities on the critical path have zero slack time and any delay in these activities will delay the entire project. The video script uses the critical path to illustrate the importance of timely resource allocation and the impact of delays on project completion.

💡PERT Network Diagram

A PERT (Program Evaluation and Review Technique) network diagram is a graphical representation of a project schedule, showing the sequence and duration of project activities. It helps in identifying the critical path and the slack time for non-critical activities. In the script, the PERT network diagram is used to estimate durations and find the critical path, which is crucial for resource leveling and schedule compression discussions.

💡Slack Time

Slack time refers to the amount of time that an activity can be delayed without affecting the project's overall completion date. In the script, slack time is mentioned in the context of the PERT network diagram, where it is used to determine the flexibility in scheduling activities that are not on the critical path.

💡Fast Tracking

Fast tracking is a schedule compression technique where activities that would normally be done sequentially are performed in parallel to save time. The script introduces fast tracking as an alternative approach when resource leveling is not enough to meet a project's time constraints, allowing for the simultaneous execution of certain tasks.

💡Crashing

Crashing is a schedule compression method where additional resources are added to critical activities to reduce their duration, thereby shortening the overall project timeline. The script discusses crashing in the context of increasing costs and potential risks, such as decreased quality and increased errors, when resources are added to expedite project completion.

💡Risk Management

Risk management in project management involves the processes of identifying, analyzing, and responding to project risks. The script touches on risk management towards the end, emphasizing the importance of understanding and mitigating risks associated with schedule compression techniques like crashing and fast tracking.

💡Confidence Level

In the context of project management, a confidence level refers to the probability that a project will be completed within a certain timeframe or budget. The script mentions confidence levels when discussing the likelihood of completing a project within specific durations, such as 42 hours or 32 hours, and the need for project managers to communicate these probabilities to stakeholders.

💡Work Breakdown Structure (WBS)

A Work Breakdown Structure is a hierarchical decomposition of the work involved in a project into smaller components. It is used for estimating time, cost, and resources required for each component. The script provides an example of a WBS for a sprinkler system installation project, illustrating how it helps in organizing tasks and identifying the sequence of activities.

Highlights

Introduction to resource leveling and its importance in effective resource utilization.

Explaining the concept of schedule compression, including fast tracking and crashing.

Hands-on activity and homework assignment to apply learned skills.

Understanding the critical path in project management and its impact on resource leveling.

The use of Excel spreadsheets for simple resource leveling tasks.

Calculating the probability of project completion within given timeframes.

The importance of statistical knowledge in project management for variance and standard deviation.

The connection between resource leveling and the critical path in project scheduling.

Strategies for leveling resource peaks and valleys without extending the project duration.

Example of a sprinkler system installation project to illustrate resource leveling.

The role of work breakdown structure in resource leveling and schedule compression.

Risks associated with resource leveling and schedule compression.

Differentiating between crashing and fast tracking in schedule compression.

The financial implications of crashing activities in a project.

Crash cost analysis and decision-making for project schedule compression.

Understanding the relationship between crash cost and project completion time.

Preparing for risk management in project scheduling for the upcoming session.

Transcripts

play00:00

hello

play00:01

hi everyone welcome back to project

play00:03

management sessions

play00:04

for the summer

play00:06

this is session six

play00:08

and we are continuing today with

play00:10

resource leveling and schedule

play00:12

compression

play00:14

so today's agenda is we're going to look

play00:16

into the resource leveling what it is

play00:18

and how can it be done

play00:21

i'm going to introduce you schedule

play00:23

compression

play00:24

and you know it it appears in some

play00:26

different types

play00:28

so one is fast tracking and the other

play00:30

one is crashing

play00:32

and then i'm gonna do uh one hands-on

play00:35

activity with you and then i'll assign

play00:38

you a homework

play00:39

uh to be able to apply the skills that

play00:41

you learned today

play00:43

at home

play00:45

so i want you to think about just one

play00:48

minute what is resource leveling and why

play00:52

may you need it

play00:54

so

play00:55

in the previous sessions we came up with

play00:58

our breakdown structure and we

play01:01

transformed it into a pert network

play01:03

diagram

play01:04

and in this network diagram we estimated

play01:07

the durations

play01:08

and we were able to find out the overall

play01:11

duration of the project

play01:14

in this

play01:15

applications we also find out the select

play01:18

time zero

play01:20

and when we combine those

play01:22

zero select times we find out the

play01:24

critical path

play01:26

right at this moment this critical path

play01:29

is you know really critical that's why

play01:31

we call it critical path

play01:33

so you got to find out the risks okay

play01:35

and how you're

play01:37

how you're using your resource if

play01:40

there's peaks and valleys a lot in your

play01:42

resource usage then you want to level

play01:45

them so

play01:47

you can effectively use your resources

play01:50

that's basically what is resource

play01:51

leveling

play01:52

there's uh you know different tools that

play01:55

you can use but you can use as simple as

play01:58

an excel

play01:59

spreadsheet

play02:01

so think about it you know in the

play02:03

previous example we we looked at you

play02:06

know let's say that you can complete the

play02:08

project in 42 hours

play02:10

what were some of the uh questions that

play02:13

you know might arise

play02:15

what is the probability of completing

play02:17

the project in 42 hours or less

play02:20

you know ceo your manager your program

play02:22

manager may ask you this question

play02:26

or what is the probability of completing

play02:28

the project in 32 hours or less

play02:31

can you have this question

play02:35

asked to you

play02:36

sure because

play02:38

maybe the customer is waiting your

play02:40

delivery you know not in 42 hours but 32

play02:44

hours so your manager wants you

play02:47

to state if you can complete or what

play02:50

kind of confidence level what is the

play02:51

percentage of your confidence level that

play02:54

you can complete your project

play02:56

under 32 hours

play02:58

or if your ceo your program manager is

play03:02

really knowledgeable about the project

play03:04

and how the projects are run

play03:06

then they may ask you what is the

play03:08

probability of completing the project

play03:10

less than

play03:12

i mean more than 95 percent probability

play03:16

confidence level okay so they want you

play03:19

to

play03:20

give them a time a duration a completion

play03:23

date that

play03:24

95 percent they can be sure that the

play03:26

project will be completed

play03:30

and you needed to some statistics

play03:32

refresher

play03:33

that's why

play03:34

in the previous session we we used our

play03:37

calculators and we refreshed you know

play03:39

get the dust out of your

play03:40

old knowledge

play03:42

about statistics

play03:45

and we find out

play03:47

over an example what is the variance

play03:49

what is the standard deviation and we

play03:52

learned for a target date how to

play03:54

complete the z value and how to look it

play03:57

up the z table

play03:58

okay

play03:59

and then find out the probability of

play04:02

uh success and i'm gonna really go fast

play04:05

if this slide is not making sense to you

play04:10

i really encourage you to go look it up

play04:12

the previous session

play04:14

recording okay

play04:16

because

play04:17

next week we're gonna do the

play04:19

[Music]

play04:20

progress quiz 2

play04:22

because this is really a natural break

play04:24

point for a nice quiz

play04:27

so there will be questions from

play04:29

you know these slides and

play04:32

how to calculate the variance and

play04:34

standard deviation and the success

play04:37

completion success and ratio rate

play04:40

in in network diagram so

play04:42

if this slide is not making sense to you

play04:44

please go back and review the previous

play04:46

week

play04:49

and one of the examples also i covered

play04:52

last week was you know ceo might ask you

play04:54

can't can you complete it earlier

play04:57

you know whatever is your completion

play04:59

time they may ask you can you complete

play05:01

it earlier for whatever reason

play05:04

maybe the customer wants it earlier

play05:06

maybe there's a rush to market uh you

play05:09

know from a business case perspective

play05:11

you want to be the first to hit the

play05:13

market

play05:15

and all of this

play05:16

how quick or can you deliver can you

play05:18

deliver 100 on time and

play05:21

all of these things

play05:22

let's and we said let's find out the

play05:25

ceo's question and we work on them

play05:28

so let's say this is our project okay

play05:31

starts from activity a and goes all the

play05:33

way to activated t and you have the

play05:36

durations associated with the activities

play05:39

here you have the red arrows and nodes

play05:42

as critical path okay

play05:45

and by now you should know

play05:47

why is critical path is called critical

play05:50

path

play05:51

uh

play05:52

how are the slack time on these uh red

play05:55

arrows

play05:56

and you know if something happened like

play05:59

if you're late or or

play06:01

or anything on on one of the activities

play06:03

what happens to project

play06:05

duration and if you are late on one of

play06:07

the blue arrows which are not on the

play06:09

critical path

play06:10

then what happens to your duration of

play06:12

the project so you know all these things

play06:16

so today's topic is resource leveling so

play06:19

coming from this

play06:21

to resource leveling

play06:23

how how what kind of a connection we

play06:25

should do

play06:26

okay

play06:27

so resource leveling is an attempt to

play06:29

eliminate the manpower peaks and valleys

play06:33

by smoothing out the period to period

play06:35

resource requirements

play06:39

the ideal solution is to do without

play06:41

changing the end date so when you're

play06:44

when you're making the resource leveling

play06:46

you shouldn't be making the project

play06:50

run more like run longer okay you

play06:53

shouldn't delay the overall project so

play06:56

resource leveling is something that you

play06:58

want to do

play06:59

to free up some space for some of your

play07:01

employees maybe some machinery

play07:04

or maybe some clean labs or some kind of

play07:08

classrooms

play07:09

meeting rooms right all of these things

play07:12

or or trucks

play07:13

that you do

play07:15

so you want to

play07:16

you know

play07:17

level these resources so you can use

play07:19

them effectively it's not

play07:21

when you're doing the resource leveling

play07:23

it's not desired to you know make the

play07:26

project run

play07:28

longer well if

play07:31

whatever you do the end date moves out

play07:33

and additional costs are incurred in the

play07:35

project then that's a different story so

play07:38

you need to make a

play07:39

make a new calculation

play07:42

so let's say i'm installing a sprinkler

play07:46

system

play07:48

in my backyard okay

play07:50

so here's my work breakdown structure

play07:53

so my system my main system is

play07:56

installing the sprinkler system

play07:59

here here you see here you see the

play08:03

here you see the the masters

play08:05

which are the acquire equipment and

play08:07

tools prepare yard

play08:10

dig trenches install system and finish

play08:12

job

play08:13

these are the master

play08:15

and these are the slave

play08:17

which for example preparing the yard 1.4

play08:21

requires you to clear the trash

play08:24

you know the wheels fill the holes and

play08:27

break the yard

play08:28

okay

play08:29

so this is let's say the work breakdown

play08:31

structure for my uh sprinkler system

play08:34

installation project in my

play08:36

backyard

play08:38

let's say i'm doing this with a with a

play08:41

kid like a teenager you know

play08:44

and myself okay

play08:46

so we're doing basically two-person

play08:50

but uh

play08:53

so if you look at this what do you see

play08:56

okay think about the different types the

play08:58

various types that we studied about work

play09:01

breakdown structure which one is this

play09:03

one

play09:06

exactly so this is kind of the time

play09:08

sequential or time phased or breakdown

play09:11

structure right

play09:13

not functional not material

play09:16

uh that's basically the time because

play09:19

you know it says finish the job you know

play09:22

and then right before that you're

play09:23

installing the system you're doing

play09:25

trenches preparing the yard and first

play09:28

acquiring the equipment right so it's

play09:30

kind of do this do this

play09:33

do this

play09:34

thing

play09:35

so work breakdown structure here is

play09:38

actually

play09:40

a time phase one

play09:42

and when i draw this

play09:44

i find out i find out this per network

play09:48

diagram okay

play09:50

starting from a

play09:52

to going to t

play09:55

so here's the activity durations and

play09:58

here's the critical path actually this

play10:00

is the same slide that i showed you in a

play10:02

minute ago

play10:04

so

play10:05

i just pulled out the

play10:06

excel spreadsheet

play10:08

and

play10:10

i put out

play10:12

nicely the activities and then the

play10:14

masters

play10:15

okay you see these ones are not

play10:18

not really the activities they are the

play10:21

uh what we call these masters

play10:23

they are kind of a title

play10:25

kind of a group things together and keep

play10:27

keep them neat and tidy

play10:30

so

play10:31

they don't have

play10:32

durations associated with them so when

play10:35

you do this

play10:37

you come up with this baseline schedule

play10:40

okay

play10:41

with the resources okay i'm just looking

play10:45

from a resource perspective from an

play10:47

employee perspective so this

play10:49

i'm installing my sprinkler system in my

play10:52

backyard

play10:53

with a teenager and myself right

play10:56

so

play10:57

i am basically using

play10:59

two person let's say okay right i'm not

play11:02

hiring any contractor i'm not paying

play11:04

anybody else

play11:06

so this let me explain you what are the

play11:09

colors and what are these lines

play11:11

and what are these

play11:13

red lines as well so

play11:16

as i as i mentioned before the the

play11:18

masters the colored one

play11:20

doesn't have any

play11:22

any activity duration associated with

play11:24

them because they're just kind of an

play11:26

umbrella kind of a grouping uh method

play11:30

but here

play11:32

you will see the designing the yard

play11:35

takes four days

play11:37

okay

play11:38

so somebody needs to do this

play11:41

in one day and then this block let's say

play11:43

this cube one day

play11:45

and then this cube another day and then

play11:47

description

play11:49

and also

play11:51

after i designed the yard i purchased

play11:54

the materials so somebody needs to go

play11:56

and purchase the material and then

play11:58

another one

play12:01

and then

play12:03

renting the trencher is also happening

play12:05

this time but what these empty blocks

play12:08

means are the slab

play12:12

are the slack time

play12:14

so i have time

play12:17

uh i can buy the for example looking

play12:20

into

play12:20

purchasing the materials

play12:23

i can purchase the material either in

play12:25

these two days which is the fifth and

play12:27

sixth day

play12:29

or seven eight nine ten until

play12:32

let's say 15 16. okay

play12:35

i should leave i can i can buy purchase

play12:38

the materials into in these two locks so

play12:41

i have the select time of this much

play12:45

okay

play12:46

and here also renting the trencher i can

play12:48

do this here

play12:50

here here or here because i have slack

play12:52

time

play12:53

because

play12:55

uh if you look at the work breakdown

play12:56

structure i don't want to open it right

play12:58

now

play13:00

but

play13:01

i can dig the trenches well to start

play13:03

digging the trencher right thinking with

play13:06

the trencher

play13:08

i need to acquire them so before

play13:11

starting to dig with trencher

play13:14

right before that i can buy this anytime

play13:17

right

play13:18

so i can i can rent it to here here

play13:22

sixth day seventh or eighth day

play13:24

but i cannot

play13:26

rent it after

play13:28

eighth day because

play13:30

digging with trenchers starts at

play13:34

cut the point so that's how i come up

play13:37

with this echelon

play13:39

so

play13:40

what is this red line they are the

play13:42

critical path okay so whatever on this

play13:45

one they are critical path okay so let's

play13:48

let's investigate this

play13:51

okay so everything looks good

play13:53

but

play13:54

but it but does it okay is there any

play13:58

problem

play13:59

let's look at the fifth

play14:03

is there any problem on day fifth fifth

play14:05

think about it so

play14:07

i am purchasing the material

play14:09

somebody is renting the trencher

play14:11

and somebody is purchasing the tools

play14:14

wait a minute so how many person is this

play14:17

one two three so if i

play14:19

if i collapse these blocks at the bottom

play14:22

oh my god there's three blocks

play14:25

let's look at here

play14:27

so somebody needs to let's say i connect

play14:31

the installer system to

play14:34

water

play14:35

and somebody needs to install the timer

play14:38

and somebody needs to install the pipe

play14:41

okay that's good

play14:42

but

play14:44

how come i do all of this in one day

play14:46

because

play14:48

durations are one day right

play14:50

and i

play14:52

not two people can do three things so if

play14:54

you collapse these things

play14:56

you see there's three people need we

play14:59

need three people but we don't have

play15:01

so what can i do well then in this case

play15:06

i use uh

play15:08

in this case i use

play15:11

the resource leveling okay that's where

play15:13

it comes handy so because i have select

play15:16

time here okay

play15:17

for example here in this in this

play15:20

column i have only one

play15:22

rake to yard

play15:24

so

play15:25

if

play15:26

i move renting the trencher to somewhere

play15:30

here

play15:31

or here

play15:33

it means that this will only be

play15:36

two blocks

play15:39

claps here

play15:40

and this one one will be 2-2

play15:43

which is good because i am already two

play15:46

people so

play15:47

one one of the you know

play15:50

one of them can do

play15:52

one job and the other one can do another

play15:54

in the same day

play15:56

so

play15:57

i'm kind of leveling the peaks here got

play16:01

it

play16:02

and then peaks here and and i don't want

play16:04

to create more time

play16:07

to finish the project

play16:11

so take a moment to think about what we

play16:13

covered on this slide okay and then try

play16:15

to digest this and

play16:18

please compare it with the pert diagram

play16:20

and

play16:21

work breakdown structure so if you open

play16:24

up baseline schedule

play16:27

uh the pert diagram and then the work

play16:29

breakdown structure if you open up all

play16:31

of them together it will make more sense

play16:33

to you

play16:34

okay but uh which one should i do and

play16:38

how can i do right so

play16:42

what if this is not good enough what if

play16:44

this is not good enough

play16:46

so you kind of did the resource leveling

play16:49

but you know maybe there's select time

play16:53

less than what's required select time

play16:55

maybe whatever you do there will be

play16:57

still three blocks

play16:59

so if this is the case

play17:02

if this is the case what else can you do

play17:05

if this is not enough okay so

play17:08

here schedule compression kicks in

play17:11

what is that

play17:12

so you can eliminate some parts let's

play17:15

say

play17:16

you know if purchasing the material and

play17:18

renting the trencher is being done with

play17:21

two different person

play17:23

maybe in two different days

play17:25

maybe you want to eliminate one of them

play17:27

so that one person go to home depot

play17:30

louise

play17:32

and

play17:33

you know buy the material and rent the

play17:35

trencher at the same time so you can

play17:36

eliminate some part of the project makes

play17:39

sense

play17:40

okay

play17:42

maybe you can substitute some less time

play17:44

consuming

play17:45

components and activities with something

play17:47

else

play17:48

maybe you can parallelize the some of

play17:51

the activities which i will show you

play17:53

or you can shorten the activities how

play17:55

can you shorten them remember

play17:58

how we came up with the project duration

play18:01

at the first place

play18:04

what we did is actually

play18:06

we did the simpsons rule and we came up

play18:09

with the duration estimations and then

play18:11

we add them up

play18:13

and then come up with the project

play18:14

duration after we find out the critical

play18:16

path

play18:17

okay

play18:18

but uh maybe you want to revisit

play18:22

your you know maybe some of the part

play18:24

some of the activities you want to

play18:27

revisit

play18:28

and estimate

play18:29

the durations

play18:31

a little bit

play18:33

uh more realistic

play18:34

okay

play18:36

so you can try to shorten the longest

play18:39

activities

play18:40

maybe you want to do the easiest

play18:41

activities first so you can

play18:44

quickly get rid of them right you may

play18:46

want to speed up

play18:47

you may want to use more resources um

play18:51

[Music]

play18:52

so these two things are critical right

play18:55

you want to have more resources

play18:59

maybe you want to add more resources

play19:01

when we say

play19:03

resources in the project management

play19:05

don't only think about money

play19:07

you can think about machinery

play19:10

you know a space like an inventory space

play19:13

you can be employee

play19:16

money time maybe a clean lab that

play19:19

everybody needs to use or you have a

play19:22

you know one testing or one software or

play19:25

one

play19:26

you know uh top secret computer network

play19:29

that you you know you need to use in by

play19:32

it needs to be used by different

play19:33

departments

play19:35

and people so these are all you should

play19:37

think as resources

play19:41

increasing the number of work hours per

play19:42

day just tell everybody hey you know we

play19:45

are

play19:46

we're running out of time in the project

play19:47

we're gonna be late so everybody will

play19:49

work you know not 18 8 hours but 12

play19:52

hours or 10 hours every day or

play19:55

come back come back on saturday

play19:58

or sunday for an eight hour shift okay

play20:02

can you do that well you can

play20:05

but uh what are the consequences okay

play20:08

everything has some consequences

play20:11

so you want to crash the project okay so

play20:13

this is called crashing

play20:16

what are some of the risk to

play20:18

compression okay what are some of the

play20:20

risk to compression

play20:22

think about it for a minute well if you

play20:24

tell people

play20:25

to work you know another four hour after

play20:28

five every day or every saturday

play20:32

then there will be you know some tests

play20:34

there will be a fatigue people will be

play20:37

you know working hungry and

play20:39

people will be working like

play20:41

not motivated and

play20:44

there will be some

play20:46

you know injuries and people forget to

play20:50

do some you know important tasks

play20:53

so quality will go down motivation will

play20:55

go down everybody will be you know tense

play20:58

and intense and angry so

play21:01

be ready for those kind of stuff if you

play21:03

want to really really like crash with

play21:05

giving you know over time

play21:08

quality issues errors but people will

play21:10

make more errors right

play21:14

more time

play21:17

finding additional resources than time

play21:19

saved

play21:20

so especially as a project manager

play21:22

you'll go out and try to find some

play21:24

additional resources which will decrease

play21:26

your time monitoring the project and

play21:28

progress

play21:29

then uh

play21:30

there will be

play21:32

like a visual cycle there will be more

play21:33

problems you will need more money so you

play21:36

will try to go out and find money

play21:38

then you will you know again decrease

play21:41

your time monitoring your project get

play21:43

your progress

play21:44

and you know guiding your people

play21:47

then

play21:48

uh you will have problems again

play21:52

new team members are not up to speed

play21:55

there will be rework and safety issues

play21:58

a lot of questions about job safety and

play22:01

product safety others sure

play22:04

you know please make you know under

play22:06

comments please write if you have any

play22:08

other if you observe if you experience

play22:11

in other problems

play22:13

with

play22:14

you know doing the compression either in

play22:15

your project or

play22:17

a project you were

play22:20

working in

play22:22

made compression and

play22:25

you had some problems

play22:28

we need to understand the crash versus

play22:31

cost relationship

play22:33

that's very critical and think about it

play22:35

because

play22:36

think about it for a while so if you

play22:38

wanna shorten an activity if you wanna

play22:40

shorten a project crash a project you

play22:43

need money but what's the relationship

play22:46

you know which activity should i

play22:48

uh crash how much money should i need

play22:50

whereas where should i start

play22:52

should i crash everything what do i do

play22:57

let's see how this can be done

play23:00

let's say you have a this kind of a

play23:02

network diagram all right it's starting

play23:05

and then you have activity d activity f

play23:08

activated g and then the project is

play23:10

ending

play23:11

how can you fast track this

play23:15

can you fast track can you do some

play23:17

activities in parallel

play23:19

there may be a few solutions to this but

play23:22

my solution for you is

play23:24

you know if you can do it you can do f

play23:27

and g in parallel at the same time

play23:30

and if you have

play23:32

resources if you have experts engineers

play23:34

to do this if you have technicians

play23:36

operators

play23:38

if g can start after d and if g can be

play23:43

conducted in you know

play23:45

processed in parallel in conjunction

play23:47

with f

play23:49

then you can change your

play23:52

pert

play23:54

with a fast tracking and now you will

play23:56

save time

play23:57

correct

play24:00

for example for this one

play24:02

now remember this was in your homework

play24:04

and you sold this

play24:07

how long is this project

play24:09

remember that look at your notes

play24:12

and then which of the activities may

play24:14

make sense to fast tracking there may be

play24:17

a lot of activities

play24:18

can they that can be done in parallel

play24:21

so think about it which cans which which

play24:24

one of these can be fast tracking

play24:28

okay

play24:30

so let's do an example now

play24:34

so here's the compression uh crash

play24:37

versus pro cost let's say

play24:40

your project is starting in zero and

play24:42

then

play24:43

a b c d e f these are the activity notes

play24:47

that you are doing

play24:48

and the numbers are the durations on the

play24:50

arrows okay

play24:53

so where to start so first of all

play24:56

let's give an answer to this question

play24:58

how long is this project

play25:01

you're gonna find out

play25:03

how much is this project

play25:05

okay

play25:06

please do this on your own

play25:11

these are the days okay four days six

play25:14

days two days

play25:15

seven days does it change the length of

play25:18

the project if an activity

play25:21

g

play25:22

is added between c and e

play25:25

with a duration duration of 24 hours

play25:28

which is duration of one day

play25:31

so if i add an activity g

play25:33

in between c and e

play25:35

what is the duration what is the overall

play25:38

uh project completion delay

play25:40

okay what is the schedule slip observed

play25:43

so i want you to do this on your own

play25:48

and and you can share it in the comments

play25:50

section

play25:52

so you can see others answers as well

play25:55

and also you can share your philosophy

play25:57

how you did it your method your way of

play25:59

doing it thinking about it

play26:01

okay

play26:04

so basically what it's saying is you

play26:05

want to add a g

play26:08

between cne

play26:10

okay

play26:12

so let's go back to the original one

play26:17

so let's investigate the cost associated

play26:20

with the activities that are to be

play26:22

crashed

play26:24

so

play26:26

this is your critical path

play26:29

four

play26:30

six

play26:31

seven and

play26:33

six

play26:33

as you can see these arrows are

play26:35

different colors so this is your

play26:37

critical path

play26:39

so

play26:39

to to analyze which nodes can be

play26:43

you know should be crashed first you

play26:45

want to go back you want to have such a

play26:48

table

play26:49

a table that says the activity what is

play26:52

the time

play26:53

what is the you know target crashing

play26:55

time what is the cost what is the weekly

play26:57

cost and you should come up

play26:59

you should have such a such a table how

play27:01

can you find that well maybe you have

play27:03

this in your project maybe you maybe you

play27:06

know it maybe you experience it if you

play27:08

ask experts okay

play27:10

you should come up with some kind of

play27:12

this table i just obscured these numbers

play27:16

because i want you to do it along with

play27:18

me

play27:21

i made red these reds are the critical

play27:24

path

play27:25

a b e and e are critical path

play27:28

okay

play27:29

so which one

play27:31

do you wanna attack first

play27:35

well first of all you want to attack

play27:37

the ones that are on the critical path

play27:39

correct

play27:40

you don't want to spend time and and by

play27:42

the way this is 8 000 i believe

play27:45

i apologize for this so this is eight

play27:48

dozen so you wanna you don't wanna crash

play27:51

the black ones right because they're not

play27:52

on the critical path they're not on the

play27:55

so even though you crash them and you

play27:57

make you

play27:59

you conduct them you know you complete

play28:01

them in in shorter shorter amount of

play28:03

time

play28:04

the project duration will not change

play28:06

because project duration is decided by

play28:09

the critical path so first of all

play28:12

you want to eliminate c and d you're

play28:14

looking for something on a b

play28:17

e and f

play28:18

okay

play28:20

so here are the target crash times

play28:22

and this is the cost like a normal cost

play28:26

and this is the crash cost so

play28:29

read it like that so normally activity

play28:32

four is four days

play28:34

you know i wanna i wanna crash

play28:37

to two days and

play28:39

the normal cost for activity a is ten

play28:41

thousand

play28:43

if i wanna crash it two weeks

play28:46

the new cost will be fourteen thousand

play28:49

okay

play28:51

so this is just activity a so you wanna

play28:53

do the same for b

play28:55

not c and d

play28:56

and this is 8000. i apologize

play28:59

and

play29:00

here it's enf you want to come up with

play29:03

these numbers okay

play29:06

then how do i decide which one to crash

play29:10

then i wanna open up one more column for

play29:12

you which is

play29:14

crash

play29:15

cost per week

play29:17

okay

play29:19

so

play29:20

i am crashing two weeks in activity a it

play29:24

cost me 14 minus 10 is 4 000

play29:27

divided by 2 is 2 000.

play29:30

i am crashing in activity b i am

play29:32

crashing one week so i'm saving i'm

play29:35

shortening it to one week

play29:37

and it cost me from thirty thousand to

play29:40

forty two thousand five hundred

play29:43

then my crash week is

play29:45

crash cost minus normal cost divided by

play29:48

the

play29:49

crash amount crash weeks okay which is

play29:51

twelve thousand

play29:53

so now you do this for enf

play29:56

so i want to ask you which one

play29:59

would you go first

play30:02

looking at this crash cost time

play30:06

which one would you go first

play30:11

and why think about the answer

play30:14

can you plot it on a crash cost graph

play30:19

can you can you plot it on a crash cost

play30:22

graph because it's easier to understand

play30:24

if we put on if you put this table

play30:28

uh on a plot

play30:30

okay

play30:33

so would you like to start with this one

play30:36

like activity b

play30:38

uh oh yeah i can hear you saying no

play30:41

because it's it's twelve thousand five

play30:43

hundred just to crash it one week

play30:46

well if i can crash

play30:49

something with

play30:51

with 2000 for a week then why not start

play30:55

from there right

play30:56

so that's the financial analysis that

play30:58

you want to do

play31:01

so if you want to put the program cost

play31:04

here

play31:05

and

play31:06

program completion time

play31:08

okay

play31:09

and here is the normal operations

play31:13

so

play31:14

if you want to start with crashing a

play31:17

okay

play31:18

you'll crash two weeks and you will only

play31:21

spend this much money

play31:24

and then which one do you want to do

play31:25

second

play31:28

i can hear what you're

play31:30

saying you want to continue with f

play31:34

because with f

play31:37

you can

play31:38

crash three weeks

play31:40

and three thousand per week

play31:44

okay

play31:45

so it brings you all the way to

play31:47

139

play31:49

okay

play31:50

so which one would you like to go next

play31:52

you want to go with e

play31:54

and you want to go with b

play31:57

well what happens after b well then

play32:02

so a b e f so if you go back

play32:06

a b e f so you all you covered all the

play32:09

critical path activities

play32:11

so

play32:12

would you like to crash

play32:15

so if you wanna if you wanna crash it

play32:17

totally like do let's say you have money

play32:20

and you wanna do you know everything you

play32:22

can

play32:23

so the minimum cost to total crash is

play32:26

around 160 000

play32:29

okay

play32:30

what's your

play32:32

save time

play32:34

you can save i believe from 23 weeks all

play32:37

the way to 15 which is eight weeks

play32:40

let's go back and uh

play32:43

calculate here two plus one

play32:46

is three plus two is five

play32:49

plus three is eight yeah you can save

play32:51

eight weeks

play32:53

as you can see it came from 23 down to

play32:56

15.

play32:57

doesn't make sense now

play33:00

so you can easily present this to your

play33:02

program manager and say

play33:05

no sir ma'am

play33:07

you know i can save two weeks with uh

play33:11

this much money

play33:13

and then if we still have money or if we

play33:15

still need to crash the project

play33:18

uh if the customer wants it really early

play33:20

then i want to go with the crashing f

play33:23

activity f

play33:24

and you can easily analyze then and show

play33:26

this to your supervisors

play33:29

okay if you

play33:31

here's the final things

play33:33

if you want to do even more crashing

play33:35

which means if you want to include cne c

play33:38

and d then

play33:40

then what does that mean

play33:42

all activities crashed

play33:44

so if you crash all activities your

play33:47

program cost will rise up to here

play33:49

but what's happening with your project

play33:51

completion time the project duration

play33:56

yeah you got it

play33:59

it's not really shortening the project

play34:02

so if i'm not saving any weeks why am i

play34:05

spending money right so i don't want to

play34:07

do this

play34:09

i want to save time

play34:11

and spend some money

play34:13

save more time and spend more money

play34:16

until

play34:17

until the time and i'm done with the

play34:19

activities that

play34:21

even though i spend money i cannot

play34:24

shorten anymore okay

play34:27

so that's the crashing cost analysis

play34:32

so there will be questions in progress

play34:34

quiz 2 next week on these on these kind

play34:37

of explanations

play34:41

so let's do another one

play34:42

so here i want you to

play34:45

do this one on your own okay

play34:49

so here's the normal time so here's the

play34:51

time that if i crash

play34:53

here's the normal cost this is the crash

play34:55

cost

play34:59

i want you to find out the time look

play35:02

weekly cost

play35:03

and decide which one to do first

play35:07

so find the weekly crash cost for each

play35:10

activities

play35:12

and in which order you would like to

play35:14

start crashing

play35:16

and think about you know as you can see

play35:18

everything is in red

play35:20

so we're thinking all the activities are

play35:22

on critical path

play35:26

i want you to plot crash cost graph and

play35:29

this will be a homework i'll post it on

play35:31

canvas as well

play35:33

so i want you to submit those things

play35:36

plot crash cost graph if you understood

play35:39

the previous example really good

play35:42

then you'll be okay to do that

play35:46

just one more thing before you go

play35:49

why are we doing all these things

play35:52

i want to i want to switch to a

play35:55

in

play35:56

a new topic in in this

play35:59

series of lectures

play36:00

why are we doing all this

play36:03

why are we trying to crash why are we

play36:05

trying to look you know the durations

play36:08

why are we really thinking on critical

play36:10

activities and critical path

play36:12

activities

play36:15

well it's because of risk

play36:18

because of risk so

play36:20

you know

play36:21

risk of

play36:23

not

play36:23

estimating the activity durations good

play36:26

risk of not estimating your budget risk

play36:29

of

play36:29

not being able to achieve on time risk

play36:32

of

play36:33

giving the wrong confidence

play36:36

confidence level okay

play36:39

so all these things are risks and

play36:43

we cannot really manage and complete any

play36:46

project

play36:47

without thinking of risk

play36:49

okay

play36:50

and when you crash when you start

play36:52

crashing when you you know shuffle

play36:54

people around shuffle material shuffle

play36:57

other resources around then you will

play37:00

create more risk but

play37:02

the thing is you want to you want to

play37:03

understand the risk from an impact

play37:07

from a probability and impact

play37:08

perspective what is the probability of

play37:10

risk occurring

play37:12

and what is the impact okay

play37:15

so

play37:15

we are switching next week

play37:18

we are switching to

play37:20

to definition of risk and the concept of

play37:23

risk in project environment

play37:25

we we are going to learn what is risk

play37:28

you know how can we

play37:30

define risk how can we manage the risk

play37:32

and what are some of the risk response

play37:34

strategies

play37:36

and we want to we

play37:38

want to you know identify the risk early

play37:41

prioritize them them and then attack

play37:44

them with some risk response strategies

play37:46

and then

play37:47

you want to monitor and control the risk

play37:51

all right great

play37:53

so make sure you complete the homework

play37:55

for next week on canvas and

play37:58

and you make a good review

play38:01

for the

play38:03

yeah for the topics that is covered

play38:05

after progress quiz one

play38:08

uh because this is kind of a very

play38:10

natural uh a great natural breakpoint

play38:13

for a progress quiz

play38:15

because we're switching from project

play38:16

management and schedule domain to

play38:19

project risk domain which is really fun

play38:22

so we'll see

play38:24

our progress levels

play38:26

thank you so much if you have any

play38:27

questions please reach out to me

play38:30

and i'll see you next week

play38:32

bye

Rate This

5.0 / 5 (0 votes)

Ähnliche Tags
Project ManagementResource LevelingSchedule CompressionFast TrackingCrashingPERT AnalysisCritical PathRisk ManagementWork BreakdownTime ManagementEfficiency
Benötigen Sie eine Zusammenfassung auf Englisch?