CIVE1265 Concrete lab Part 1
Summary
TLDRThe video script details a civil engineering lab session at Bandura East Campus, focusing on concrete casting. The process involves calculating ingredient quantities for 30 MPa concrete, measuring materials using a scale, and mixing in a concrete mixer. It demonstrates mixing dry materials first, then adding cement and water. The script also covers conducting a slump test, filling molds, and vibrating to remove air bubbles. Finally, it mentions the curing process, involving water curing for seven days before testing.
Takeaways
- 🏛️ The video is set in the Bandura East Campus, specifically focusing on the civil engineering facilities.
- 🔬 The objective is to prepare and cast 30 MPa concrete, requiring precise measurement of cement, water, sand, and aggregates.
- 📏 The script outlines the need to calculate the total volume and the required quantities of each ingredient based on a mix design.
- 📐 The calculated quantities are: cement at 5.91 kg, water at 1.9 kg, sand at 8.84 kg, and aggregate at 20.21 kg.
- ⚖️ A scale is used to measure the exact amounts of each ingredient, ensuring accuracy in the concrete mix.
- 🏗️ The smallest concrete mixer, with a 60-liter capacity, is used for mixing the concrete ingredients.
- 🔄 The mixing process involves first combining the dry materials, then adding cement, and finally, water.
- 📏 The script describes a slump test to measure the consistency of the concrete, which yields a reading of 180 millimeters.
- 🗜️ The concrete is then poured into molds, vibrated to remove air bubbles, and leveled off for uniformity.
- 🕒 After molding, the concrete specimens are left to cure for 24 hours before being demolded and placed in water curing tanks for seven days.
- 🔍 The final step involves testing the cured concrete samples, showcasing the importance of the curing process for strength and quality.
Q & A
Where is the speaker located at the beginning of the transcript?
-The speaker is located in the Bandura East Campus, specifically outside building 25253.
What type of concrete is being cast according to the transcript?
-The type of concrete being cast is 30 MPa concrete.
What are the four main ingredients required for the concrete mix as mentioned in the transcript?
-The four main ingredients required for the concrete mix are cement, water, sand, and aggregates.
How many specimens are being prepared according to the transcript?
-Five specimens are being prepared, with an additional 25% added to the total volume.
What is the required quantity of cement for the concrete mix as per the calculations in the transcript?
-The required quantity of cement for the concrete mix is 5.91 kilograms.
What is the quantity of water needed for the concrete mix as mentioned in the transcript?
-The quantity of water needed for the concrete mix is 1.9 kilograms.
What is the role of the 10 millimeter cross aggregate in the concrete mix?
-The 10 millimeter cross aggregate is used as part of the coarse aggregate in the concrete mix.
What is the procedure for mixing the concrete as described in the transcript?
-The procedure involves first mixing all the dry materials, then adding cement to the fine and coarse aggregate, and finally adding water.
What is the slump test mentioned in the transcript, and what is the recorded reading?
-The slump test is a test to measure the consistency of the concrete. The recorded reading is around 180 millimeters.
How long do the specimens need to be cured in the water tank before being tested?
-The specimens need to be cured in the water tank for seven days before being tested.
What is the purpose of the curing tanks mentioned in the transcript?
-The purpose of the curing tanks is to soak the specimens in water for the curing process, which is essential for the concrete to gain strength.
Outlines
🏗️ Concrete Mixing and Measuring Ingredients
The speaker is at the Bandura East Campus, specifically in front of Building 25253 where civil engineering is located. They discuss the process of preparing 30 MPa concrete, detailing the required ingredients: cement, water, sand, and aggregates. The quantities needed are calculated according to the lab manual, with specific amounts given for cement (5.91 kg), water (1.9 kg), sand (8.84 kg), and aggregates (20.21 kg). The ingredients are measured using a scale, and the process of mixing them in a concrete mixer is described, starting with the dry materials and ending with the addition of water.
📏 Slump Test and Mold Filling
This paragraph describes the process of performing a slump test on the concrete mixture. The speaker explains how to stack the concrete into a cone shape, tamp it 25 times, and then fill the next one-third layer, repeating the process until the cone is full. After lifting the pole, a roller is used to measure the slump, which in this case is around 180 millimeters. The paragraph then transitions into the process of filling molds with the concrete, emphasizing the importance of vibrating the mold to remove air bubbles and achieve a uniform surface.
🛠️ Curing Process and Specimen Preparation
The focus of this paragraph is on the curing process of the concrete specimens. After the concrete is poured into molds and vibrated to remove air bubbles, the speaker explains that the specimens need to be left for 24 hours before demolding. The next day, the specimens are to be placed in curing tanks for water curing, where they will be soaked for seven days before testing. The curing tanks are described as containing water to keep the specimens moist, and the speaker mentions that previously demolded samples can be seen in the tanks.
🔄 Demolding and Curing Tank Setup
The final paragraph discusses the demolding of the concrete specimens, which is to be done the following morning. The specimens are then to be brought to the curing tanks for the week-long curing process before testing. The speaker provides a view of the curing tanks and mentions that they contain previously demolded concrete samples, indicating that the process is a standard part of the concrete testing workflow.
Mindmap
Keywords
💡Bandura Campus
💡Civil Engineering
💡Concrete
💡Mix Design
💡MPa (MegaPascal)
💡Aggregate
💡Segregate
💡Concrete Mixer
💡Slump Test
💡Curing
💡Curing Tank
Highlights
Introduction to Bandura East Campus and the civil engineering lab.
Explanation of the process to cast 30 MPa concrete.
Outline of the ingredients and their required amounts for concrete mix.
Calculation of total volume and ingredient quantities based on mix design.
Measurement of cement, water, sand, and aggregate using a scale.
Use of the smallest concrete mixer with a 60-liter capacity.
Mixing of dry materials, including sand and aggregate, in the mixer.
Addition of cement to the mixer and subsequent mixing.
Introduction of water to the mixer to complete the concrete mix.
Conducting a slump test to measure the consistency of the concrete.
Filling and vibrating the mold to remove air bubbles and ensure uniformity.
Curing process of the concrete specimens in water for seven days.
Use of a curing tank for water curing of the concrete samples.
Preparation for demolding the specimens and transferring them to curing tanks.
Overview of the lab's process from mixing to curing and future testing.
Transcripts
hi everyone
today i'm here in the bandura campus in
particular bandura east campus and this
is where this is where our civil
engineering is
so i'm outside building 25253
so our lab is on the ground level of
this building good morning everyone so
we first want to understand
the ingredients required
required amount of ingredients so
basically concrete uh we're going to
cast 30 mpa concrete uh
30 mpa concrete so then we need to
measure the cement water sand and
aggregates so according to the mix
design as outline in the
lab manual so
then we need to understand we have four
specimens five specimens all together
then we have to add additional 25
then we calculate the total volume based
on that total volume then we can
calculate the required quantities of
each ingredients basically cement 5.91
kilograms water
one nine kilograms sand eight point
eight four kilograms and aggregate
twenty point two uh to one kilograms so
once we have all the calculations then
we can use this scale
then we can start measuring each
ingredient so for an example
so this is water
so the required level is
3.19 so including the bucket weight it
is around 3.65 so then we have the right
quantity
excuse me we have the right quantity in
water
similarly
we can measure all the other three
ingredients so this is called segregate
this is a 10 millimeter cross aggregate
this is fine aggregate we use a river
sand and this is the
general portland cement
so all the ingredients we measured based
on the
quantities we calculated
okay so this is our concrete mixer we
have
different sizes of concrete mixers in
concrete lab so this is the smallest
concrete mixer
which can carry
up to 60 liter of volume
so we selected based on the volume
of the calculation so first thing we
have
we have to mix all the dry materials
you can use sand
and pour into the mixer
[Applause]
this is first aggregate
so once we have all the finite create
and pulse aggregate inside the concrete
mixer then we can mix
around one to two minutes
[Music]
oh
[Music]
so
once we have a uh
aggregate mixing so then we can add
cement into the uh fine and force
aggregate
[Music]
so then you can mix that another one to
two minutes
[Music]
so
[Music]
so then we can add water
[Music]
so
[Music]
[Music]
so
foreign
[Music]
[Applause]
so
[Applause]
so our next one islam taste
then you need to stack the corn
that's enough so then we can tamp 25
blocks
then you can fill the next
one third
so one more
okay so then you need to come back only
that one third layer so then you have to
provide another 25 laws
then you can fill the last one third
and then you can provide another 25
blocks for that
the last one sir
then you need to lift the pole
you can place your phone
then with the roller
with the roller you can measure the
slump
high into the maximum point
so then reading will be
around
180
180 millimeters
so once you finish your slump test you
can go back into the bucket then you can
start
filling your mold
is a
small filling
with concrete and vibrating so
what we want to know uh
we want to fill first half of the moles
then we can
start vibration table for a few seconds
then while vibrating we can feel the
remaining half
so let's start with the first half
[Music]
so
[Applause]
yeah you can see john
yeah next we can complete the
we can fill
to the top level then we can vibrate it
again
[Applause]
up
so
[Applause]
oh your calculations are exactly right
did you add 25
so
now we have we have filled up to the top
level then we have to vibrate it
again for
months two minutes
until we remove all the air bubbles
so
then
you almost have a very uniform surface
in the top then you can leave all your
specimens somewhere in the safe side
for the another 24 hours once we have
all the things uh probably tomorrow the
same time we will come back and we will
demold all the things then we can put
into the uh concrete uh in curing tanks
so in the curing process is water curing
then we have to soak all the specimens
in water tank for seven days
until being tested
and this is example of curing tank so
once we demold all these specimens by
tomorrow
morning so then we can bring all
specimens into this curing tanks you can
have a look some of the previously
demold concrete samples are there so
then we have to keep all these uh
samples in cured uh during tank
until being tested in next week
5.0 / 5 (0 votes)